CDOT contract C23177 bid tabulation

US 40 - EMPIRE JUNCTION TO BERTHOD PASS BEGINNING AT M.P. 252 AND EXTENDING TO M.P. 258.3. THIS PROJECT CONSISTS OF REMOVING 2.5" OF EXISTING ASPHALT PAVEMENT AND PLACING 2.5" OF HMA. IN ADDITION, THIS PROJECT INCLUDES CLEANING INLETS AND CULVERTS, UPGRADING EXISTING ADA CURB RAMPS, CROSSWALKS, MAKI. Let by Colorado DOT on March 27, 2025, Clear Creek, Region 1. 4 bids received; low bid $11,822,057 by Oldcastle SW Group, Inc., +4.6% against the engineer's estimate of $11,300,000.

Owner
Colorado DOT
Letting
27 MAR 2025
Pay items
204
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Oldcastle SW Group, Inc.$11,822,057Low+5.0%
2Kilgore Companies, LLC dba Elam Construction$14,634,409+24%+30%
3Martin Marietta Materials, Inc.$14,736,457+25%+30%
4Brannan Sand and Gravel, LLC$17,686,997+50%+57%
CDOT contract C23177: bids by rank

Engineer's estimate: $11,300,000.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Oldcastle SW Group, Inc.2. Kilgore Companies, LLC dba Elam Construction3. Martin Marietta Materials, Inc.4. Brannan Sand and Gravel, LLC
1Clearing and grubbing (201-00000)LS1$50,000$32,136$100,000$20,667$196,321
2Removal of tree (202-00010)EACH13$695.99$642.70$1,000.00$799.39$6,000.00
3Removal of inlet (202-00019)EACH3$1,848.22$2,448.38$1,900.00$3,045.29$9,200.00
4Removal of pipe (202-00035)LF2,152$25.10$51.01$53.00$63.44$94.00
5Removal of fiber optic cable (202-00055)LF1,280$2.17$3.06$3.50$3.83$3.80
6Removal of travel time indicator (202-00060)EACH1$488.56$280.56$290.00$350.67$350.00
7Removal of delineator (202-00090)EACH300$7.71$12.36$8.50$15.26$15.50
8Removal of sidewalk (202-00200)SY70$38.83$31.21$70.00$38.25$57.50
9Removal of curb and gutter (202-00203)LF451$29.44$15.61$33.00$19.13$25.75
10Removal of concrete curb ramp (202-00206)SY91$84.41$34.33$91.00$42.08$57.50
11Removal of concrete pavement (202-00210)SY6$137.64$52.02$243.00$63.76$64.25
12Removal of asphalt mat (202-00220)SY1,244$30.00$139.31$70.00$279.51$235.00
13Removal of asphalt mat (planing) (202-00240)SY209,269$5.00$4.90$5.00$7.07$7.20
14Removal of pavement marking (202-00250)SF24,129$1.06$1.29$1.00$0.95$1.60
15Removal of ground sign (202-00810)EACH27$147.93$190.61$121.00$235.32$240.00
16Removal of sign panel (202-00821)EACH200$60.43$128.79$84.50$159.00$160.00
17Removal of pull box (202-00827)EACH2$250.31$1,377.27$1,400.00$1,721.46$1,700.00
18Removal of traffic signal equipment (202-00828)LS1$50,000$17,343$18,000$21,678$21,000
19Removal of traffic signal controller cabinet (202-00855)EACH1$892.24$3,213.64$3,325.00$4,016.74$4,000.00
20Removal of traffic signal vehicle detector amplifier (202-00880)EACH3$600.00$76.52$79.00$95.64$96.00
21Removal of radar detection system (202-00887)EACH1$322.06$561.11$581.00$701.33$700.00
22Removal of guardrail type 3 (202-01130)LF1,870$10.00$3.61$5.00$5.52$5.50
23Removal of end anchorage (202-01300)EACH10$417.11$489.39$301.00$361.63$370.00
24Plug culvert (202-04001)EACH1$4,126.30$3,570.55$1,583.00$4,441.05$5,300.00
25Clean culvert (202-04002)EACH27$1,545.08$3,381.31$2,956.00$4,164.67$5,600.00
26Clean inlet (202-04010)EACH15$1,438.21$1,040.40$1,478.00$1,281.44$2,430.00
27Embankment material (complete in place) (203-00060)CY56$120.00$204.03$232.00$274.43$390.00
28Blading (203-01500)HR80$205.47$252.53$165.00$215.96$245.00
29Dozing (203-01550)HR40$191.57$252.53$234.00$200.88$410.00
30Combination loader (203-01594)HR80$176.86$176.77$349.00$178.27$200.00
31Potholing (203-01597)HR100$331.70$357.07$475.00$446.30$450.00
32Laborer (203-02330)HR40$67.35$101.01$47.00$68.65$100.00
33Wetland topsoil (207-00305)CY7$152.56$1,019.76$500.00$495.88$2,200.00
34Topsoil (offsite) (207-00702)CY2,700$120.00$35.42$20.00$111.51$185.00
35Erosion log type 1 (12 inch) (208-00002)LF820$6.77$5.20$5.00$6.54$8.90
36Erosion log type 1 (20 inch) (208-00013)LF370$11.15$8.32$7.75$11.21$14.00
37Silt fence (reinforced) (208-00021)LF1,100$7.60$5.72$2.50$3.20$12.00
38Aggregate bag (208-00035)LF252$13.95$9.36$8.00$11.53$13.50
39Concrete washout structure (208-00045)EACH1$6,000.00$780.30$2,930.00$4,399.28$4,000.00
40Storm drain inlet protection (type I) (208-00051)LF86$13.30$10.40$23.00$11.53$24.00
41Vehicle tracking pad (208-00070)EACH2$3,297.25$2,496.97$3,046.00$2,056.20$6,500.00
42Removal and disposal of sediment (labor) (208-00103)HR120$84.22$72.83$46.50$176.26$130.00
43Removal and disposal of sediment (equipment) (208-00105)HR40$177.41$119.65$114.00$531.04$200.00
44Sweeping (sediment removal) (208-00106)HR50$146.88$140.45$310.00$277.20$200.00
45Removal of trash (208-00107)HR20$134.32$78.03$148.00$176.26$150.00
46Erosion control management (208-00207)DAY50$404.34$312.12$750.00$725.77$650.00
47Rebuild timber deck (210-00650)LS1$8,500.00$15,152$10,000$4,397.08$2,000.00
48Reset flashing beacon (210-00825)EACH2$1,581.20$5,407.07$1,637.00$6,758.32$6,800.00
49Reset fence (210-01000)LF19$65.92$505.05$250.00$323.56$96.65
50Reset guardrail type 3 (210-01130)LF500$13.70$25.76$66.00$78.86$80.90
51Compost (mechanically applied) (212-00701)CY7$211.00$86.68$148.00$185.81$185.00
52Biotic soil amendments (hydraulically applied) (212-00702)LB6,548$1.52$1.07$1.50$1.13$1.40
53Humate (212-00703)LB125$2.34$6.12$3.50$0.56$4.00
54Mycorrhizae (212-00704)LB32$27.36$12.24$13.00$12.11$16.00
55Seeding (native) hydraulic (212-00707)ACRE1.46$1,609.70$1,376.68$648.11$2,084.26$820.00
56Seeding (native) broadcast (212-00708)ACRE0.10$3,275.00$4,079.05$1,040.00$10,770$1,300.00
57Seeding (wetland) hydraulic (212-00710)ACRE0.10$4,200.00$6,628.46$7,880.00$11,642$9,900.00
58Mulching (hydraulic) (213-00011)ACRE1.46$2,792.41$3,059.29$1,655.67$4,356.88$2,050.00
59Mulch tackifier (213-00061)LB219$4.39$3.06$1.50$3.65$1.90
60Rock mulch (weed free) (213-00067)SF885$7.52$5.10$3.80$4.16$4.75
61Extended landscape preservation (214-00008)LS1$32,500$4,079.05$51,000$32,036$64,565
62Deciduous tree (#5 container) (214-00205)EACH8$69.21$96.88$303.00$121.74$380.00
63Deciduous shrub (#1 container) (214-00310)EACH10$36.64$50.99$80.00$44.85$100.00
64Evergreen tree (#5 container) (214-00450)EACH2$67.35$96.88$294.00$288.32$370.00
65Live willow stakes (214-01013)EACH105$6.94$10.20$9.00$15.38$11.00
66Dormant log cutting (214-01025)EACH15$88.74$25.49$25.00$70.48$31.00
67Soil retention blanket (straw-coconut) (biodegradable class 1) (216-00201)SY50$6.00$35.69$10.50$32.04$66.00
68Herbicide treatment (217-00020)HR40$188.87$127.47$338.00$219.85$425.00
69Wildlife biologist (240-00000)HR40$171.03$115.61$367.50$332.92$190.00
70Removal of nests (240-00010)HR40$171.00$115.61$367.50$320.36$150.00
71Aggregate base course (class 5) (304-05000)TON2,750$35.00$63.74$40.00$56.45$126.00
72Hot mix asphalt (patching) (asphalt) (403-00721)SY1,082$300.00$299.80$150.00$564.27$740.00
73Emergency pothole repair (403-00800)TON100$656.29$530.75$100.00$844.72$675.00
74Hot mix asphalt (grading SX) (75) (PG 58- 28) 00 34 00 (403-34721)TON30,062$105.00$127.57$144.00$126.69$151.00
75Concrete pavement (8 inch) (412-00800)SY21$37.00$112.36$1,055.00$137.72$258.00
76Geotextile (erosion control) (class 1) (420-00102)SY397$10.80$5.10$16.00$6.34$63.00
77Drilled shaft (18 inch) (503-00018)LF10$227.97$1,020.20$1,055.00$1,275.15$1,285.00
78Drilled shaft (36 inch) (503-00036)LF38$1,244.30$1,428.28$1,478.00$1,785.22$1,800.00
79Riprap (9 inch) (506-00209)CY105$168.82$367.26$275.00$456.79$518.00
80Riprap (12 inch) (506-00212)CY49$283.86$392.76$221.00$488.52$505.00
81Concrete class B (601-01000)CY36$1,614.54$3,264.50$3,060.00$4,060.39$1,935.00
82Reinforcing steel (602-00000)LB1,436$3.87$3.06$4.75$3.81$2.50
83Welded wire fabric (602-00210)SY4$86.91$25.50$400.00$31.72$385.00
8418 inch reinforced concrete pipe (complete in place) (603-01185)LF42$112.02$438.67$1,845.00$545.62$725.00
8524 inch reinforced concrete pipe (complete in place) 00 (603-01245)LF1,833$184.26$540.68$1,071.00$672.50$438.15
8630 inch reinforced concrete pipe (complete in place) (603-01305)LF448$230.21$550.88$1,161.00$685.19$516.75
8736 inch reinforced concrete pipe (complete in place) (603-01365)LF254$333.64$571.29$1,012.00$710.57$677.85
8860 inch reinforced concrete pipe (complete in place) (603-01605)LF132$902.99$1,407.82$2,530.00$1,751.04$1,650.00
8918 inch reinforced concrete end section (603-05018)EACH2$1,928.16$2,907.45$2,850.00$3,616.29$7,435.00
9024 inch reinforced concrete end section (603-05024)EACH21$2,272.89$3,876.59$3,167.00$4,821.72$6,455.00
9130 inch reinforced concrete end section (603-05030)EACH7$1,139.70$4,284.66$3,590.00$5,329.27$8,300.00
9236 inch reinforced concrete end section (603-05036)EACH3$1,427.00$4,896.75$4,434.00$6,090.59$11,690
93Place 24 inch steel end section (603-32024)EACH2$3,000.00$2,244.34$1,900.00$2,791.52$6,550.00
94Inlet type C (5 foot) (604-00305)EACH1$6,378.94$6,120.94$7,495.00$7,613.24$12,150
95Inlet type D (5 foot) (604-00505)EACH3$3,967.33$7,141.10$9,500.00$8,882.11$17,150
96Inlet type D (10 foot) (604-00510)EACH1$4,967.81$7,549.16$12,655$9,389.66$26,175
97Inlet type 13 (5 foot) (604-13005)EACH1$6,401.87$5,916.91$9,700.00$7,359.46$13,000
98Inlet type R L 10 (5 foot) (604-19205)EACH1$5,562.46$11,222$15,800$13,958$21,000
99Manhole slab base (5 foot) (604-30005)EACH2$5,492.24$7,141.10$9,250.00$8,882.11$23,000
100Manhole special (604-39000)EACH1$15,820$15,303$23,000$8,882.11$35,950
101Guardrail type 3 (31 inch midwest guardrail system) (606-00302)LF1,870$55.00$35.03$49.00$59.13$60.75
102End anchorage type 3B (606-01320)EACH1$1,312.91$1,287.88$5,230.00$6,293.61$6,500.00
103End anchorage (nonflared) (606-02003)EACH4$2,441.03$3,482.42$6,100.00$7,435.59$7,625.00
104End anchorage (flared) (606-02005)EACH5$4,743.16$3,554.55$6,900.00$8,330.15$8,545.00
105Fence (plastic) (607-11525)LF3,449$2.73$3.38$5.25$2.82$2.40
1063 foot gate (607-60103)EACH1$5,000.00$3,606.06$1,950.00$1,922.15$2,400.00
107Road closure gate (607-60620)EACH1$21,413$51,010$52,500$56,704$64,000
108Concrete sidewalk (608-00000)SY18$207.30$101.96$600.00$124.97$386.50
109Concrete curb ramp (608-00010)SY184$223.56$145.66$453.00$178.52$206.25
110Detectable warnings (608-00015)SF288$49.28$104.04$76.00$127.52$96.65
111Curb and gutter type 2 (section I-B) (609-21010)LF113$43.20$59.30$137.00$72.68$58.00
112Curb and gutter type 2 (section II-B) (609-21020)LF310$54.77$55.14$142.00$67.58$64.50
113Gutter type 2 (4 foot) (609-24004)LF112$70.69$90.52$450.00$110.94$103.00
114Gutter type 2 (8 foot) (609-24008)LF27$70.55$145.66$750.00$178.52$155.00
115Curb type 6 (section M) (609-60011)LF2,025$21.00$24.84$14.50$19.14$47.50
116Median cover material (patterned concrete) (610-00020)SF457$16.61$28.09$83.00$34.43$25.80
117Delineator (type I) (612-00001)EACH255$31.37$35.03$27.00$43.25$49.50
118Delineator (type II) (612-00002)EACH30$34.24$35.03$31.00$43.25$44.40
119Delineator (type III) (612-00003)EACH35$38.64$35.03$34.00$43.25$44.40
120Delineator (type I) (extra height) (612-00031)EACH20$49.66$70.06$55.00$86.50$88.75
121Delineator (type III) (extra height) (612-00033)EACH20$40.94$70.06$64.00$86.50$88.75
122Location marker (fiber optic)(dome) (612-00260)EACH3$328.17$178.54$185.00$223.15$225.50
123Location marker (utility)(flat slat) (612-00270)EACH8$83.67$178.54$185.00$223.15$225.50
1242 inch electrical conduit (bored) (613-00206)LF1,665$46.92$96.92$100.00$121.14$122.50
1253 inch electrical conduit (bored) (613-00306)LF440$87.06$112.22$116.00$140.27$141.75
1262 inch electrical conduit (plastic) (613-01200)LF1,235$22.92$35.71$37.00$44.63$45.10
1273 inch electrical conduit (plastic) (613-01300)LF410$22.11$40.81$42.00$51.01$51.55
128Electrical system modifications (613-04100)LS1$12,000$3,774.75$3,900.00$4,718.07$4,775.00
129Type one pull box (613-07001)EACH21$973.15$1,683.33$1,741.00$2,104.00$2,130.00
130Type four pull box (613-07004)EACH6$1,945.44$3,723.74$3,800.00$4,654.31$4,700.00
131Type five pull box (613-07005)EACH3$1,075.48$5,611.11$5,800.00$7,013.35$7,085.00
132Wiring (613-10000)LS1$70,000$35,707$36,000$44,630$45,102
133Luminaire (LED) (8,000 lumens) (613-13008)EACH2$1,086.99$816.16$850.00$1,020.12$1,030.00
134Meter power pedestal (613-50109)EACH1$10,974$11,222$11,600$14,027$14,175
135Troubleshooting (613-60700)HR124$195.06$204.04$211.00$255.03$257.75
136Safety switch NEMA 3R, 30 ampere, 2- pole, 240 volt (613-81699)EACH1$1,933.42$2,346.46$2,448.00$2,932.86$2,975.00
137Sign panel (class I) (614-00011)SF1,181$26.22$25.76$29.50$31.80$32.50
138Sign panel (class II) (614-00012)SF1,057$31.50$39.15$37.00$48.34$49.75
139Sign panel (class III) (614-00013)SF129$44.70$49.45$42.00$61.06$62.75
140Steel signpost (W 6X15) (614-00615)LF29$113.44$164.85$137.00$203.52$209.00
141Steel signpost (W 8X18) (614-00818)LF71$56.06$185.45$162.00$782.29$235.00
142Steel sign support (2-1/2 inch round NP- 40)(post & slipbase) (614-01573)EACH100$535.75$633.64$653.00$782.29$800.00
143Concrete footing (type 2) (614-03002)EACH2$1,262.31$3,606.06$2,586.00$4,452.05$4,570.00
144Concrete footing (type 3) (614-03003)EACH4$1,282.35$3,863.64$3,167.00$4,770.05$4,900.00
145CWDM multiplexor demultiplexor module (614-70026)EACH2$9,182.27$9,793.94$10,135$12,241$12,370
146CWDM SFP optic module (614-70028)EACH4$993.85$1,224.24$1,265.00$1,530.19$1,550.00
147Optical filter (614-70032)EACH4$740.88$1,428.28$1,478.00$1,785.22$1,800.00
148Pedestrian signal face (16) (countdown) (614-70150)EACH4$1,015.02$994.70$1,029.00$1,243.28$1,260.00
149Traffic signal face (12-12-12) (614-70336)EACH12$1,015.64$1,581.31$1,636.00$1,976.49$2,000.00
150Conflict monitor (614-72836)EACH1$1,395.62$1,530.30$1,583.00$1,912.73$1,950.00
151Traffic signal controller cabinet (614-72855)EACH1$31,409$27,035$27,977$33,792$34,000
152Pedestrian push button (614-72860)EACH4$248.11$1,683.33$1,741.00$2,104.00$2,125.00
153Pedestrian push button post assembly (614-72863)EACH1$1,776.02$1,938.38$2,000.00$2,422.79$2,450.00
154Loop detector wire (614-72875)LF1,200$3.25$21.42$22.00$26.78$27.00
155Traffic signal vehicle detector (micro wave type) (614-72884)EACH4$8,805.06$12,855$13,300$16,067$16,240
156Traffic signal vehicle detector (special) (614-72885)EACH1$14,110$11,732$12,140$14,664$14,820
157Microwave vehicle radar detector (614-72887)EACH1$20,155$13,518$13,988$16,896$17,075
158Rectangular rapid flashing beacon (614-80003)EACH4$8,686.07$10,712$11,085$13,389$13,530
159Rumble strip (614-80385)LF76,153$3.12$0.19$0.30$0.23$0.35
160Traffic signal-light pole steel (1-50 foot mast arm) (614-81150)EACH1$35,000$26,015$26,920$32,516$32,860
161Traffic signal-light pole steel (1-55 foot mast arm) (614-81155)EACH1$40,000$26,525$27,500$33,154$33,504
162Traffic signal pedestal pole steel (614-84000)EACH2$6,560.62$4,386.87$4,500.00$5,483.16$5,550.00
163Telemetry (field) (614-86105)EACH2$8,489.76$2,346.46$2,428.00$2,932.86$2,975.00
164Traffic signal controller (type 2070LC) (614-86248)EACH3$7,853.71$9,181.82$9,500.00$11,476$11,600
165Uninterrupted power supply (614-86800)EACH2$7,076.90$10,202$10,500$12,752$12,890
166Fiber optic cable (single mode) (12 fiber) (614-87010)LF325$8.99$5.10$5.25$6.38$6.50
167Buffer tube fan out kit (614-87015)EACH1$583.79$127.53$131.00$159.39$161.10
168Fiber optic termination panel (24 fiber) (614-87024)EACH1$2,477.26$714.14$739.00$892.61$902.05
169Automatic traffic recording station (614-87100)EACH1$18,758$22,444$23,255$28,053$28,350
170Closed circuit television (614-87320)EACH2$6,781.49$6,835.35$7,000.00$8,543.53$8,635.00
171Test fiber optic cable (614-87350)LS1$20,000$3,570.71$3,695.00$4,463.04$4,510.00
172Fiber optic cable (single mode) (96 strands) (614-87496)LF1,320$9.21$7.14$7.25$8.93$9.00
173Ethernet switch type II (614-87692)EACH1$10,467$9,079.80$9,396.00$11,349$11,500
174Field office (class 2) (620-00002)EACH1$21,740$38,664$30,737$69,160$140,000
175Field laboratory (class 2) (620-00012)EACH1$16,429$31,889$26,000$58,104$106,730
176Sanitary facility (620-00020)EACH2$3,806.88$3,825.00$11,401$4,836.79$24,800
177Construction surveying (625-00000)LS1$75,000$128,788$48,000$133,126$120,000
178Mobilization (626-00000)LS1$2,059,753$749,650$1,100,000$1,077,859$2,038,546
179Public information management (tier III) (626-01113)DAY200$74.18$151.52$81.00$186.56$95.00
180Modified epoxy pavement marking (627-00008)GAL766$141.53$190.61$146.00$175.74$241.00
181Pavement marking paint (high build)(temporary) (627-00016)GAL903$133.00$108.18$100.00$121.18$137.00
182Preformed plastic pavement marking (type I)(inlaid) (627-01010)SF3,164$22.55$23.44$23.00$27.60$29.75
183Preformed thermoplastic pavement marking (word-symbol) (627-30405)SF877$19.98$24.47$22.00$26.33$30.95
184Preformed thermoplastic pavement marking (shield) (627-30408)SF814$26.73$29.36$34.00$40.60$37.10
185Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410)SF952$16.41$18.55$17.50$21.25$23.50
186Flagging (630-00000)HR500$42.00$48.94$63.00$49.98$62.00
187Uniformed traffic control (630-00003)HR800$146.00$123.64$221.00$288.32$156.00
188Uniformed traffic control (vehicle) (630-00006)HR800$93.00$123.64$58.00$76.89$156.00
189Traffic control inspection (630-00007)DAY60$500.00$324.55$500.00$640.72$415.00
190Traffic control management (630-00012)DAY126$1,500.00$1,493.94$1,794.00$1,922.15$5,875.00
191Flashing beacon (solar) (630-80002)EACH7$716.09$669.70$1,698.00$2,306.58$850.00
192Barricade (type 3 M-B) (temporary) (630-80336)EACH10$231.41$334.85$843.00$256.29$425.00
193Construction traffic sign (panel size A) (630-80341)EACH144$51.46$61.82$110.00$57.66$78.30
194Construction traffic sign (panel size B) (630-80342)EACH86$65.36$72.12$116.00$64.07$91.35
195Construction traffic sign (panel size C) (630-80343)EACH26$74.02$82.42$126.00$76.89$104.40
196Portable message sign panel (630-80355)EACH5$5,518.20$11,848$22,384$20,260$15,000
197Advance warning flashing or sequencing arrow panel (C type) (630-80358)EACH3$1,141.64$2,472.73$2,600.00$4,290.25$3,135.00
198Drum channelizing device (630-80360)EACH350$40.89$46.36$42.00$64.07$58.75
199Barrier (temporary) (630-80370)LF1,400$80.00$51.10$252.00$59.29$58.00
200Traffic cone (630-80380)EACH175$8.47$15.45$15.50$5.13$19.60
201Stackable vertical panels (630-80393)EACH50$28.91$46.36$37.00$64.07$58.75
202Mobile pavement marking zone (630-80511)LS1$20,000$12,879$10,558$12,689$16,270
203Impact attenuator (temporary) (630-85010)EACH2$4,744.72$8,757.58$11,000$10,251$11,100
204Mobile attenuator (630-85041)DAY65$1,500.00$875.76$1,300.00$1,742.75$1,105.00
CDOT contract C23177: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of March 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy