Preformed thermoplastic pavement marking (word-symbol), CDOT 627-30405

Low bidders on CDOT contracts carried a median of $28.20 per SF for this item, over the 24 months to 10 SEP 2026, across 33 low bids. Half of all 123 bids fell between $25.00 and $36.97.

Owner
Colorado DOT
Item
627-30405
Unit
SF
Data through
10 SEP 2026

CDOT prints this item as “Preformed Thermoplastic Pavement Marking (Word-Symbol)”.

$28.20Low bidder's median, per SF
$30.00Median of all bids, per SF
33Contracts in the window
$26.29Engineer's estimate, median per SF

By year of letting

Preformed thermoplastic pavement marking (word-symbol), CDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20242727$29.00100$30.00
20251414$22.6048$25.66

Bid prices as published, not adjusted for inflation.

By region

RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 110$29.4543$31.00
Region 49$29.0033$29.00
Region 28$21.8827$29.00
Region 54$28.6017$29.00
Preformed thermoplastic pavement marking (word-symbol), CDOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

By quantity

Quantity (SF)Low bidsLow-bid median
16 to 1168$30.25
118 to 2648$32.00
264 to 6708$27.57
877 to 15,3019$19.00
Preformed thermoplastic pavement marking (word-symbol), CDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Oldcastle SW Group, Inc.114 (36%)
Martin Marietta Materials, Inc.112 (18%)
Jalisco International, Inc.52 (40%)
Rodriguez Construction Org., LLC81 (13%)
Morton Electric, Inc.61 (17%)
Capital Paving & Construction, LLC51 (20%)
Preformed thermoplastic pavement marking (word-symbol), CDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
18 SEP 2025C25393Region 2210$25.00$28.25$32.068Siete, Inc.CDOT
14 AUG 2025C26205Region 148.30$22.00$30.39$28.714Sturgeon Electric Company, Inc.CDOT
11 JUL 2025C259602,690$41.50$41.50$41.501Kraemer North America, LLCCDOT
26 JUN 2025C26803Region 215,301$18.00$18.00$13.501Roadsafe Traffic Systems, IncCDOT
24 APR 2025C26766Region 4264$21.00$27.00$25.883Martin Marietta Materials, Inc.CDOT
10 APR 2025C26304Region 291.90$16.00$24.00$26.522Morton Electric, Inc.CDOT
03 APR 2025C26489Region 4630$26.95$26.95$20.001Brannan Sand and Gravel, LLCCDOT
27 MAR 2025C23177Region 1877$24.47$25.40$19.984Oldcastle SW Group, Inc.CDOT
20 MAR 2025C23369Region 11,323$23.20$25.00$24.153Oldcastle SW Group, Inc.CDOT
06 MAR 2025C26804Region 54,629$16.00$18.00$16.006Streamline Markings, IncCDOT
20 FEB 2025C26314Region 41,634$19.00$21.80$21.004Asphalt Specialties Co., Inc.CDOT
06 FEB 2025C25802Region 3264$36.00$32.75$40.002Oldcastle SW Group, Inc.CDOT
16 JAN 2025C24278Region 182$42.40$41.70$26.296Structures, Inc.CDOT
09 JAN 2025C23780Region 11,941$18.85$18.85$23.003Brannan Sand and Gravel, LLCCDOT
19 DEC 2024C19934Region 1260$29.91$29.45$24.116Brannan Sand and Gravel, LLCCDOT
Latest CDOT contracts carrying Preformed thermoplastic pavement marking (word-symbol)

Filter this item by your own quantity, region and period, or check your price against it, in the CDOT explorer.

How these prices were read

CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are CDOT's own: this item is compared with CDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the CDOT letting of 10 SEP 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy