CDOT contract C25802 bid tabulation

US 40 MP 215.90 - 219.88 IN GRAND COUNTY Safety improvement project located on US 40 from MM 215.90 extending to MM 219.88. Resurfacing will consist of a 2" overlay, full roadway and shoulder width along with full depth reclamation (shoulder), shoulder widening, striping and signing. Remove and repl. Let by Colorado DOT on February 6, 2025, Grand, Region 3. 2 bids received; low bid $5,792,197 by Oldcastle SW Group, Inc., -8.8% against the engineer's estimate of $6,352,126.

Owner
Colorado DOT
Letting
06 FEB 2025
Pay items
97
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Oldcastle SW Group, Inc.$5,792,197Low-9.0%
2Kilgore Companies, LLC dba Elam Construction$6,283,967+8.0%-1.0%
CDOT contract C25802: bids by rank

Engineer's estimate: $6,352,126.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Oldcastle SW Group, Inc.2. Kilgore Companies, LLC dba Elam Construction
1Clearing and grubbing (201-00000)LS1$10,000$70,000$122,000
2Removal of tree (202-00010)EACH6$1,500.00$3,300.00$775.00
3Removal of pipe (202-00035)LF13$115.00$225.00$103.00
4Removal of end section (202-00037)EACH1$650.00$2,000.00$460.00
5Removal of asphalt mat (202-00220)SY475$25.00$30.00$14.00
6Removal of asphalt mat (planing) (202-00240)SY689$15.00$20.00$25.00
7Removal of pavement marking (202-00250)SF44,637$1.00$0.55$0.93
8Removal of ground sign (202-00810)EACH12$200.00$250.00$258.00
9Removal of guardrail type 3 (202-01130)LF3,334$10.00$5.75$5.00
10Removal of end anchorage (202-01300)EACH6$800.00$690.00$289.00
11Clean culvert (202-04002)EACH2$6,500.00$2,500.00$2,585.00
12Unclassified excavation (complete in place) (203-00010)CY8,502$45.00$52.00$46.00
13Proof rolling (203-01100)HR40$135.00$115.00$377.00
14Blading (203-01500)HR80$200.00$150.00$393.18
15Dozing (203-01550)HR80$200.00$150.00$474.98
16Truck (203-01580)HR80$200.00$100.00$235.11
17Combination loader (203-01594)HR80$150.00$120.00$710.29
18Potholing (203-01597)HR10$600.00$490.00$325.00
19Laborer (203-02330)HR80$100.00$40.00$95.00
20Topsoil (onsite) (207-00700)CY3,692$30.00$21.00$29.00
21Erosion log type 1 (12 inch) (208-00002)LF2,000$10.00$5.00$6.82
22Erosion log type 1 (20 inch) (208-00013)LF250$20.00$7.50$9.50
23Pre-fabricated concrete washout structure (type 1) (208-00046)EACH1$4,000.00$6,100.00$7,161.00
24Vehicle tracking pad (208-00070)EACH2$2,500.00$5,000.00$2,813.00
25Construction mat (208-00082)SF800$25.00$22.00$4.00
26Removal and disposal of sediment (labor) (208-00103)HR40$75.00$53.00$211.00
27Removal and disposal of sediment (equipment) (208-00105)HR40$150.00$120.00$502.00
28Sweeping (sediment removal) (208-00106)HR40$200.00$120.00$266.00
29Removal of trash (208-00107)HR40$100.00$53.00$121.00
30Erosion control management (208-00207)DAY50$400.00$150.00$1,530.00
31Reset ground sign (210-00810)EACH12$500.00$675.00$620.00
32Organic fertilizer (212-00700)LB1,420$2.00$1.00$1.09
33Biotic soil amendments (hydraulically applied) (212-00702)LB310$3.00$3.80$2.74
34Mycorrhizae (212-00704)LB950$10.00$22.50$15.50
35Seeding (native) hydraulic (212-00707)ACRE4.72$3,000.00$1,500.00$665.00
36Spray-on mulch blanket (213-00012)ACRE4.72$4,700.00$5,580.00$8,000.00
37Bonded fiber matrix (213-00150)ACRE2$4,600.00$4,800.00$8,000.00
38Soil retention blanket (straw-coconut) (biodegradable class 1) (216-00201)SY970$5.00$4.00$4.35
39Wildlife biologist (240-00000)HR40$200.00$150.00$134.00
40Removal of nests (240-00010)HR40$200.00$100.00$134.00
41Netting (240-00020)SY500$10.00$15.00$13.00
42Aggregate base course (class 1) (304-01005)CY3,866$90.00$52.00$78.00
43Aggregate base course (class 3) (304-03005)CY39$140.00$220.00$133.50
44Aggregate base course (class 6) (304-06007)CY2,963$120.00$87.00$84.00
45Full depth reclamation of hot mix asphalt pavement (0-8") (310-00608)SY7,492$6.00$7.25$7.00
46Hot mix asphalt (patching) (asphalt) (403-00721)SY828$160.00$40.00$67.00
47Hot mix asphalt (grading SX) (75) (403-34701)TON11,568$130.00$135.00$117.00
48Asphalt cement performance grade (PG 58-28) (411-03352)TON650$650.00$400.00$470.00
49Emulsified asphalt (slow-setting) (411-10255)GAL7,313$5.00$5.50$3.10
50Riprap (12 inch) (506-00212)CY16$200.00$475.00$213.00
51Geogrid reinforcement (506-01020)SY78$8.00$13.00$10.50
5224 inch corrugated steel pipe (603-10240)LF75$300.00$155.00$126.00
5336 inch corrugated steel pipe (603-10360)LF13$400.00$750.00$132.00
54Place 24 inch steel end section (603-32024)EACH4$1,000.00$770.00$1,213.00
55Inlet type C (5 foot) (604-00305)EACH2$10,000$7,800.00$6,204.00
56Guardrail type 3 (6-3 post spacing) (606-00301)LF3,334$55.00$36.25$35.81
57Guardrail type 9 (style CA) (606-00910)LF1,511$250.00$200.00$138.23
58End anchorage (nonflared) (606-02003)EACH1$5,000.00$38.25$3,862.00
59End anchorage (flared) (606-02005)EACH5$6,000.00$4,350.00$3,841.00
60Fence (plastic) (607-11525)LF150$5.00$23.00$4.65
61Curb type 6 (section M) (609-60011)LF3,574$35.00$15.00$11.76
62Delineator (type I) (612-00001)EACH28$50.00$37.00$34.00
63Delineator (type III) (612-00003)EACH5$60.00$37.00$34.00
64Delineator (type I) (barrier) (612-00021)EACH9$95.00$120.00$108.00
65Sign panel (class II) (614-00012)SF80$35.00$42.75$39.00
66Steel sign support (2-1/2 inch round NP- 40)(post) (614-01575)LF88$25.00$33.75$31.00
67Steel sign support (2-1/2 inch round NP- 40)(slipbase) (614-01578)EACH7$350.00$310.00$284.00
68Rumble strip (grinding)(asphalt) (614-80391)LF19,508$0.50$1.00$0.67
69Embankment protector type 5 (615-00050)EACH8$2,500.00$2,000.00$2,068.00
70Field office (class 2) (620-00002)EACH1$50,000$75,000$31,637
71Field laboratory (class 2) (620-00012)EACH1$50,000$65,000$32,200
72Sanitary facility (620-00020)EACH1$5,000.00$10,000$15,500
73Construction surveying (625-00000)LS1$150,000$160,000$123,646
74Construction surveying (hourly) (625-00001)HR40$200.00$210.00$227.37
75Mobilization (626-00000)LS1$850,000$865,000$1,378,000
76Public information services (tier III) (626-01103)LS1$15,000$21,000$10,702
77Modified epoxy pavement marking (627-00008)GAL248$200.00$150.00$201.00
78Pavement marking paint (high build) (627-00013)GAL447$50.00$195.00$123.00
79Preformed thermoplastic pavement marking (word-symbol) (627-30405)SF264$40.00$36.00$29.50
80Flagging (630-00000)HR3,000$50.00$53.00$49.00
81Traffic control inspection (630-00007)DAY50$450.00$375.00$387.00
82Traffic control management (630-00012)DAY138$2,000.00$1,600.00$1,636.00
83Flashing beacon (portable) (630-80001)EACH2$2,200.00$675.00$620.00
84Barricade (type 3 M-B) (temporary) (630-80336)EACH3$200.00$315.00$326.00
85Construction traffic sign (panel size A) (630-80341)EACH14$85.00$80.00$88.00
86Construction traffic sign (panel size B) (630-80342)EACH80$120.00$100.00$103.40
87Construction information sign (630-80348)EACH2$500.00$125.00$129.00
88Portable message sign panel (630-80355)EACH2$8,000.00$14,000$12,350
89Advance warning flashing or sequencing arrow panel (C type) (630-80358)EACH2$2,000.00$2,800.00$2,896.00
90Drum channelizing device (630-80360)EACH200$35.00$45.00$46.50
91Drum channelizing device (with light) (flashing) (630-80363)EACH20$45.00$60.00$62.00
92Drum channelizing device (with light) (steady burn) (630-80364)EACH20$45.00$60.00$62.00
93Portable traffic speed monitor (630-80367)EACH2$4,000.00$3,000.00$8,789.00
94Traffic cone (630-80380)EACH500$15.00$15.00$15.50
95Stackable vertical panels (630-80393)EACH12$45.00$50.00$46.50
96Mobile pavement marking zone (630-80511)LS1$15,000$5,000.00$8,789.00
97Mobile attenuator (630-85020)EACH2$25,000$25,000$66,500
CDOT contract C25802: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of February 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy