CDOT contract C26304 bid tabulation
US50/MAPLE & US287/CEDAR, LAMAR PROWERS COUNTY. Let by Colorado DOT on April 10, 2025, Prowers, Region 2. 2 bids received; low bid $1,482,503 by Morton Electric, Inc., -7.3% against the engineer's estimate of $1,600,000.
- Owner
- Colorado DOT
- Letting
- 10 APR 2025
- Pay items
- 88
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Morton Electric, Inc. | $1,482,503 | Low | -7.0% |
| 2 | Sturgeon Electric Company, Inc. | $1,758,653 | +19% | +10% |
Engineer's estimate: $1,600,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Morton Electric, Inc. | 2. Sturgeon Electric Company, Inc. |
|---|---|---|---|---|---|---|
| 1 | Tree trimming (202-00008) | HR | 6 | $280.14 | $100.00 | $1,200.00 |
| 2 | Removal of median cover (202-00195) | SY | 12 | $68.53 | $108.00 | $90.00 |
| 3 | Removal of sidewalk (202-00200) | SY | 9.50 | $61.54 | $105.00 | $120.00 |
| 4 | Removal of curb (202-00201) | LF | 14 | $25.88 | $39.00 | $80.00 |
| 5 | Removal of curb and gutter (202-00203) | LF | 32 | $42.09 | $50.00 | $46.00 |
| 6 | Removal of concrete curb ramp (202-00206) | SY | 7 | $39.52 | $132.00 | $150.00 |
| 7 | Removal of concrete pavement (202-00210) | SY | 7.50 | $78.31 | $138.00 | $200.00 |
| 8 | Removal of pavement marking (202-00250) | SF | 2,454 | $3.36 | $4.00 | $4.00 |
| 9 | Removal of sign panel (202-00821) | EACH | 16 | $59.56 | $101.00 | $230.00 |
| 10 | Removal of pull box (202-00827) | EACH | 10 | $257.44 | $200.00 | $700.00 |
| 11 | Removal of traffic signal equipment (202-00828) | LS | 1 | $15,000 | $24,750 | $50,000 |
| 12 | Removal of radar detection system (202-00887) | EACH | 1 | $330.00 | $1,150.00 | $350.00 |
| 13 | Removal of concrete foundation and slab (202-00950) | SY | 8 | $286.14 | $110.00 | $250.00 |
| 14 | Unclassified excavation (203-00000) | CY | 10.40 | $242.92 | $275.00 | $350.00 |
| 15 | Potholing (203-01597) | HR | 186 | $281.67 | $75.00 | $650.00 |
| 16 | Topsoil (offsite) (207-00702) | CY | 2 | $112.22 | $275.00 | $350.00 |
| 17 | Subgrade soil preparation (207-00704) | SY | 145 | $11.15 | $110.00 | $6.00 |
| 18 | Erosion log type 1 (12 inch) (208-00002) | LF | 24 | $11.80 | $46.00 | $21.00 |
| 19 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 1 | $3,250.35 | $6,475.00 | $4,200.00 |
| 20 | Storm drain inlet protection (type I) (208-00051) | LF | 68 | $17.57 | $17.00 | $22.00 |
| 21 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 2 | $5,165.59 | $1,000.00 | $14,000 |
| 22 | Sweeping (sediment removal) (208-00106) | HR | 21 | $171.58 | $94.00 | $230.00 |
| 23 | Portable pan-tilt-zoom camera (reset) (210-00892) | EACH | 1 | $1,417.31 | $1,250.00 | $2,200.00 |
| 24 | Organic fertilizer (212-00700) | LB | 9 | $7.71 | $43.00 | $38.00 |
| 25 | Compost (mechanically applied) (212-00701) | CY | 2 | $379.81 | $440.00 | $1,200.00 |
| 26 | Mycorrhizae (212-00704) | LB | 2 | $70.33 | $165.00 | $100.00 |
| 27 | Seeding (native) broadcast (212-00708) | ACRE | 0.03 | $17,401 | $73,333 | $30,000 |
| 28 | Environmental health and safety management (250-00010) | LS | 1 | $15,000 | $11,385 | $6,000.00 |
| 29 | Aggregate base course (class 6) (304-06000) | TON | 10.20 | $107.53 | $314.00 | $300.00 |
| 30 | Replace concrete pavement (412-04999) | SY | 7.50 | $300.00 | $418.00 | $650.00 |
| 31 | Drilled shaft (36 inch) (503-00036) | LF | 126 | $803.63 | $850.00 | $900.00 |
| 32 | Drilled shaft (48 inch) (503-00048) | LF | 21 | $1,061.54 | $900.00 | $1,200.00 |
| 33 | Drilled shaft (54 inch) (503-00054) | LF | 21 | $1,011.42 | $950.00 | $1,300.00 |
| 34 | Concrete sidewalk (608-00000) | SY | 9.50 | $165.78 | $374.00 | $390.00 |
| 35 | Concrete curb ramp (608-00010) | SY | 8 | $319.68 | $957.00 | $560.00 |
| 36 | Curb and gutter type 2 (section II-B) (609-21020) | LF | 16 | $103.80 | $138.00 | $280.00 |
| 37 | Median cover material (patterned concrete) (610-00020) | SF | 9 | $41.00 | $358.00 | $90.00 |
| 38 | 2 inch electrical conduit (bored) (613-00206) | LF | 2,280 | $20.00 | $24.00 | $27.00 |
| 39 | 3 inch electrical conduit (bored) (613-00306) | LF | 562 | $97.55 | $25.00 | $32.00 |
| 40 | 2 inch electrical conduit (plastic) (613-01200) | LF | 218 | $27.01 | $24.00 | $27.00 |
| 41 | 3 inch electrical conduit (plastic) (613-01300) | LF | 218 | $23.79 | $25.00 | $32.00 |
| 42 | Type two pull box (613-07002) | EACH | 9 | $1,300.91 | $2,053.00 | $2,000.00 |
| 43 | Type four pull box (613-07004) | EACH | 10 | $1,971.49 | $2,932.00 | $3,500.00 |
| 44 | Wiring (613-10000) | LS | 1 | $45,000 | $62,700 | $98,000 |
| 45 | Luminaire (LED) (8,000 lumens) (613-13008) | EACH | 5 | $1,090.77 | $1,134.00 | $1,200.00 |
| 46 | Meter power pedestal (613-50109) | EACH | 3 | $12,000 | $8,163.00 | $13,000 |
| 47 | Sign panel (class I) (614-00011) | SF | 238.50 | $41.32 | $34.00 | $85.00 |
| 48 | Pedestrian signal face (16) (countdown) (614-70150) | EACH | 20 | $970.26 | $720.00 | $1,200.00 |
| 49 | Traffic signal face (12-12-12) (614-70336) | EACH | 39 | $850.00 | $906.00 | $1,800.00 |
| 50 | Traffic signal face (12-12-12-12) (614-70448) | EACH | 9 | $1,200.00 | $1,086.00 | $2,100.00 |
| 51 | Traffic signal controller cabinet (614-72855) | EACH | 2 | $40,000 | $44,750 | $46,000 |
| 52 | Pedestal pole (3 foot 6 inch) (614-72858) | EACH | 4 | $1,015.10 | $1,053.00 | $2,800.00 |
| 53 | Pedestrian push button (614-72860) | EACH | 3 | $257.61 | $466.00 | $900.00 |
| 54 | Coordination unit (614-72870) | EACH | 2 | $5,000.00 | $1,150.00 | $9,000.00 |
| 55 | Vehicle detection system (single camera) (614-72895) | EACH | 3 | $8,688.86 | $5,067.00 | $7,800.00 |
| 56 | Flashing beacon (614-80000) | EACH | 2 | $7,034.80 | $6,004.00 | $9,800.00 |
| 57 | Traffic signal-light pole steel (1-35 foot mast arm) (614-81135) | EACH | 3 | $28,217 | $25,872 | $22,500 |
| 58 | Traffic signal-light pole steel (1-40 foot mast arm) (614-81140) | EACH | 1 | $30,000 | $22,116 | $24,000 |
| 59 | Traffic signal-light pole steel (1-45 foot mast arm) (614-81145) | EACH | 2 | $35,000 | $22,640 | $24,500 |
| 60 | Traffic signal-light pole steel (1-50 foot mast arm) (614-81150) | EACH | 1 | $40,000 | $23,409 | $25,500 |
| 61 | Traffic signal-light pole steel (1-55 foot mast arm) (614-81155) | EACH | 1 | $42,000 | $23,525 | $26,000 |
| 62 | Traffic signal light pole steel (1-60 foot mast arm) (614-81160) | EACH | 1 | $24,334 | $36,050 | $38,500 |
| 63 | Traffic signal-light pole steel (1-70 foot mast arm) (614-81170) | EACH | 1 | $45,000 | $38,660 | $41,000 |
| 64 | Traffic signal pedestal pole steel (614-84000) | EACH | 5 | $1,826.59 | $2,686.00 | $5,600.00 |
| 65 | Controller (type 2070) (614-86748) | EACH | 2 | $6,359.66 | $8,248.00 | $7,800.00 |
| 66 | Fiber optic cable (single mode) (12 fiber) (614-87010) | LF | 150 | $12.44 | $16.00 | $18.00 |
| 67 | Fiber optic termination panel (12 fiber) (614-87012) | EACH | 2 | $1,421.71 | $522.00 | $600.00 |
| 68 | Buffer tube fan out kit (614-87015) | EACH | 2 | $346.87 | $308.00 | $390.00 |
| 69 | Closed circuit television camera (traffic surveillance) (614-87333) | EACH | 2 | $8,166.52 | $6,030.00 | $6,400.00 |
| 70 | Splice fiber optic cable (12 strand) (614-87512) | EACH | 2 | $1,627.98 | $770.00 | $850.00 |
| 71 | Terminate fiber optic cable (12 strand) (614-87612) | EACH | 2 | $1,500.15 | $660.00 | $750.00 |
| 72 | Mobilization (626-00000) | LS | 1 | $286,420 | $228,900 | $120,000 |
| 73 | Public information services (tier IV) (626-01104) | LS | 1 | $10,000 | $7,700.00 | $9,500.00 |
| 74 | Thermoplastic pavement marking (xwalk- stopline) (627-30210) | SF | 2,448 | $22.50 | $13.00 | $21.00 |
| 75 | Preformed thermoplastic pavement marking (word-symbol) (627-30405) | SF | 91.90 | $26.52 | $16.00 | $32.00 |
| 76 | Flagging (630-00000) | HR | 30 | $37.11 | $36.00 | $50.00 |
| 77 | Uniformed traffic control (630-00003) | HR | 65 | $132.48 | $165.00 | $280.00 |
| 78 | Traffic control inspection (630-00007) | DAY | 10 | $400.00 | $550.00 | $760.00 |
| 79 | Traffic control management (630-00012) | DAY | 69 | $1,200.00 | $1,513.00 | $1,600.00 |
| 80 | Uniformed traffic control coordination (630-00015) | HR | 18 | $28.50 | $59.00 | $225.00 |
| 81 | Barricade (type 3 F-A) (temporary) (630-80331) | EACH | 6 | $236.12 | $220.00 | $60.00 |
| 82 | Construction traffic sign (panel size A) (630-80341) | EACH | 4 | $49.35 | $55.00 | $60.00 |
| 83 | Construction traffic sign (panel size B) (630-80342) | EACH | 42 | $65.84 | $61.00 | $120.00 |
| 84 | Construction traffic sign (panel size C) (630-80343) | EACH | 16 | $74.36 | $66.00 | $220.00 |
| 85 | Portable message sign panel (630-80355) | EACH | 4 | $5,247.14 | $7,150.00 | $6,500.00 |
| 86 | Advance warning flashing or sequencing arrow panel (A type) (630-80356) | EACH | 1 | $1,316.65 | $1,100.00 | $3,200.00 |
| 87 | Drum channelizing device (630-80360) | EACH | 36 | $34.90 | $17.00 | $26.00 |
| 88 | Mobile attenuator (630-85041) | DAY | 60 | $230.37 | $798.00 | $290.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of April 10, 2025. Compiled by Mirage Metrics.