CDOT contract C26314 bid tabulation

Project 26314 is in Boulder County on CO7 between 28th St (MP 52.3) to Cherryvale Rd (MP 55.5) and includes the following major operations: -HMA Mill & Overlay -HMA reconstruction -Construction Traffic Control -ADA Ramp -Permanent Pavement Markings A mandatory pre bid conference will be held on Janu. Let by Colorado DOT on February 20, 2025, Boulder, Region 4. 4 bids received; low bid $8,058,761 by Asphalt Specialties Co., Inc., -12% against the engineer's estimate of $9,199,932.

Owner
Colorado DOT
Letting
20 FEB 2025
Pay items
80
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Asphalt Specialties Co., Inc.$8,058,761Low-12%
2Martin Marietta Materials, Inc.$9,062,537+12%-1.0%
3Brannan Sand and Gravel, LLC$10,233,633+27%+11%
4Oldcastle SW Group, Inc.$11,603,923+44%+26%
CDOT contract C26314: bids by rank

Engineer's estimate: $9,199,932.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Asphalt Specialties Co., Inc.2. Martin Marietta Materials, Inc.3. Brannan Sand and Gravel, LLC4. Oldcastle SW Group, Inc.
1Removal of bollard (202-00039)EACH18$150.00$350.00$260.27$630.00$360.00
2Removal of delineator (202-00090)EACH82$20.00$17.00$7.10$19.00$23.00
3Removal of concrete median cover material (202-00190)SY604$25.00$20.35$9.51$25.25$26.00
4Removal of sidewalk (202-00200)SY809$35.00$22.70$9.51$25.25$26.00
5Removal of curb (202-00201)LF104$25.00$12.50$4.75$12.65$13.00
6Removal of curb and gutter (202-00203)LF3,552$15.00$10.65$5.23$13.90$14.00
7Removal of concrete curb ramp (202-00206)SY1,829$45.00$20.45$9.51$25.25$26.00
8Removal of brick pavers (202-00207)SY3$48.00$50.00$23.76$65.00$65.00
9Removal of concrete pavement (202-00210)SY245$53.00$25.00$11.88$32.00$32.00
10Removal of asphalt mat (202-00220)SY24,598$12.00$7.50$4.87$6.50$11.00
11Removal of asphalt mat (planing) (202-00240)SY83,156$3.50$4.20$2.41$4.35$8.00
12Removal of pavement marking (202-00250)SF44,566$1.00$0.60$0.26$0.80$1.50
13Removal of ground sign (202-00810)EACH4$200.00$285.00$49.21$315.00$380.00
14Removal of sign panel (202-00821)EACH5$100.00$170.00$29.34$190.00$230.00
15Removal of pull box (202-00827)EACH69$250.00$580.00$257.53$725.00$680.00
16Removal of pedestal pole (202-00858)EACH3$2,300.00$580.00$889.64$725.00$2,340.00
17Removal of pedestrian push button (202-00860)EACH42$130.00$115.00$199.00$130.00$520.00
18Unclassified excavation (203-00000)CY5,318$85.00$49.65$30.12$75.50$42.00
19Proof rolling (203-01100)HR8$150.00$300.00$46.99$260.00$190.00
20Potholing (203-01597)HR40$350.00$225.00$351.17$550.00$400.00
21Sweeping (with pickup broom) (203-01622)HR40$200.00$195.00$79.43$250.00$250.00
22Pre-fabricated concrete washout structure (type 1) (208-00046)EACH2$3,000.00$1,700.00$2,376.27$3,300.00$16,600
23Erosion control (curb ramp) (208-00090)EACH95$600.00$2,100.00$156.86$730.00$610.00
24Reset ground sign (210-00810)EACH17$700.00$505.00$106.47$570.00$690.00
25Reset sign panel (210-00815)EACH4$250.00$225.00$59.63$255.00$310.00
26Reset pedestrian push button (210-00860)EACH1$600.00$375.00$280.94$426.50$740.00
27Adjust manhole (210-04010)EACH4$1,200.00$900.00$393.88$3,000.00$2,100.00
28Adjust valve box (210-04050)EACH2$600.00$475.00$105.49$2,500.00$1,200.00
29Aggregate base course (class 6) (304-06007)CY4,615$90.00$101.50$35.27$98.00$84.00
30Reconditioning (306-01000)SY24,256$3.00$4.50$1.30$3.95$2.80
31Hot mix asphalt (patching) (asphalt) (403-00720)TON157$400.00$320.00$174.62$375.00$900.00
32Hot mix asphalt (grading SX) (100) (PG 64- 28) (403-34851)TON6,462$140.00$121.50$48.12$148.00$165.00
33Hot mix asphalt (grading SX) (100) (PG 76- 28) 00 00 (403-34871)TON15,416$130.00$127.00$51.97$136.00$181.00
34Joint sealant (408-01100)LF160$36.00$28.30$10.30$19.00$45.00
35Concrete pavement (patching) (412-00190)SY211$250.00$115.00$42.77$129.00$120.00
36Concrete pavement (8 inch) (fast track) (412-00805)SY78$150.00$135.00$54.65$165.00$150.00
37Concrete sidewalk (608-00000)SY728$120.00$80.00$42.30$127.50$120.00
38Concrete curb ramp (608-00010)SY1,804$180.00$145.00$61.78$186.50$170.00
39Curb type 2 (section B) (609-20010)LF415$50.00$28.50$14.73$44.50$40.00
40Curb and gutter type 2 (section I-B) (609-21010)LF2,671$50.00$24.00$15.68$47.50$43.00
41Curb and gutter type 2 (section II-B) (609-21020)LF949$60.00$30.50$17.58$53.00$48.00
42Median cover material (6 inch patterned concrete) (610-00026)SF7,645$20.00$16.00$9.98$30.00$27.00
43Delineator (flexible) (type I) (612-00041)EACH81$110.00$125.00$27.92$165.00$170.00
442 inch electrical conduit (613-00200)LF706$38.00$35.00$23.41$44.00$61.00
45Type one pull box (613-07001)EACH13$1,500.00$1,800.00$772.58$2,350.00$2,030.00
46Type two pull box (613-07002)EACH37$2,000.00$2,200.00$913.05$2,800.00$2,400.00
47Type three pull box (613-07003)EACH16$2,500.00$2,650.00$1,217.40$3,450.00$3,200.00
48Type four pull box (613-07004)EACH3$3,000.00$3,750.00$1,755.87$4,850.00$4,610.00
49Sign panel (class I) (614-00011)SF665$40.00$27.50$15.62$31.00$37.00
50Signpost (special) (614-00040)LF770$700.00$24.00$8.99$27.25$33.00
51Pedestrian push button (614-72860)EACH44$1,000.00$525.00$795.99$680.00$2,090.00
52Pedestrian push button post assembly (614-72863)EACH44$3,500.00$2,850.00$913.05$3,625.00$2,400.00
53Field office (class 2) (620-00002)EACH1$35,000$60,000$29,522$77,665$65,000
54Field laboratory (class 2) (620-00012)EACH1$35,000$32,000$25,565$74,485$60,000
55Sanitary facility (620-00020)EACH2$3,000.00$2,500.00$1,896.34$7,200.00$6,000.00
56Detour pavement (621-00450)SY916$130.00$175.00$65.02$250.00$180.00
57Bollard (622-00270)EACH17$1,000.00$730.00$237.63$630.00$1,440.00
58Construction surveying (625-00000)LS1$20,000$195,000$17,137$187,000$130,000
59Mobilization (626-00000)LS1$918,270$625,000$409,216$1,429,250$1,900,000
60Modified epoxy pavement marking (627-00008)GAL276$145.00$165.00$68.57$206.50$320.00
61Pavement marking paint (high build)(temporary) (627-00016)GAL516$75.00$75.00$30.98$93.25$160.00
62Preformed thermoplastic pavement marking (word-symbol) (627-30405)SF1,634$21.00$19.00$8.16$24.60$32.00
63Preformed thermoplastic pavement marking (word-symbol) (special) (627-30407)SF4,632$25.00$25.00$10.64$32.00$32.00
64Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410)SF14,441$16.00$14.00$5.79$17.50$23.00
65Preformed thermoplastic pavement marking (xwalk-stop line) (special) (627-30411)SF9,609$16.00$18.50$7.80$23.50$25.00
66Monument box (629-01050)EACH8$2,500.00$1,685.00$57.50$435.00$1,500.00
67Flagging (630-00000)HR4,000$50.00$52.60$587.22$64.50$55.00
68Traffic control inspection (630-00007)DAY67$300.00$550.00$2,012.45$350.00$340.00
69Traffic control management (630-00012)DAY140$1,600.00$1,840.00$97.87$1,850.00$1,650.00
70Barricade (type 3 M-A) (temporary) (630-80335)EACH12$160.00$89.00$67.29$155.00$240.00
71Construction traffic sign (panel size A) (630-80341)EACH281$65.00$61.50$26.65$63.00$79.00
72Construction traffic sign (panel size B) (630-80342)EACH74$80.00$61.50$8,270.01$75.50$79.00
73Portable message sign panel (630-80355)EACH8$6,000.00$7,500.00$3,025.41$10,715$12,800
74Advance warning flashing or sequencing arrow panel (B type) (630-80357)EACH5$2,500.00$2,800.00$24.47$3,150.00$3,050.00
75Drum channelizing device (630-80360)EACH300$46.00$22.50$26.91$44.00$49.00
76Drum channelizing device (with light) (flashing) (630-80363)EACH50$75.00$24.65$12.23$50.00$55.00
77Traffic cone (630-80380)EACH250$15.00$11.50$8,953.69$25.00$21.00
78Mobile pavement marking zone (630-80511)LS1$7,500.00$8,500.00$25,914$10,650$32,000
79Traffic signal (temporary) (630-86810)EACH4$35,000$23,000$93,178$50,670$26,400
80Night work lighting (632-00000)LS1$50,000$65,000$36,911$186,300$150,000
CDOT contract C26314: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of February 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy