CDOT contract C26489 bid tabulation
CO119 AND CO 7 FROM US36 (28TH ST) TO BOULDER. Let by Colorado DOT on April 3, 2025, Boulder, Region 4. 1 bid received; low bid $4,654,490 by Brannan Sand and Gravel, LLC, -3.0% against the engineer's estimate of $4,797,502.
- Owner
- Colorado DOT
- Letting
- 03 APR 2025
- Pay items
- 82
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Brannan Sand and Gravel, LLC | $4,654,490 | Low | -3.0% |
Engineer's estimate: $4,797,502.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Brannan Sand and Gravel, LLC |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201-00000) | LS | 1 | $50,000 | $34,000 |
| 2 | Removal of delineator (202-00090) | EACH | 25 | $12.00 | $20.00 |
| 3 | Removal of gutter (202-00202) | LF | 47 | $15.00 | $29.90 |
| 4 | Removal of curb and gutter (202-00203) | LF | 1,416 | $14.00 | $23.95 |
| 5 | Removal of curb, gutter and sidewalk (202-00204) | LF | 30 | $50.00 | $53.80 |
| 6 | Removal of concrete curb ramp (202-00206) | SY | 13 | $30.00 | $59.80 |
| 7 | Removal of brick pavers (202-00207) | SY | 108 | $75.00 | $32.30 |
| 8 | Removal of concrete pavement (202-00210) | SY | 109 | $35.00 | $32.30 |
| 9 | Removal of asphalt mat (202-00220) | SY | 27,980 | $12.00 | $7.75 |
| 10 | Removal of asphalt mat (planing) (202-00240) | SY | 52,147 | $3.50 | $3.40 |
| 11 | Removal of pavement marking (202-00250) | SF | 866 | $1.00 | $5.60 |
| 12 | Removal of guardrail type 3 (202-01130) | LF | 90 | $7.00 | $10.50 |
| 13 | Removal of end anchorage (202-01300) | EACH | 4 | $525.00 | $490.00 |
| 14 | Unclassified excavation (203-00000) | CY | 1,229 | $50.00 | $99.00 |
| 15 | Topsoil (onsite) (207-00700) | CY | 162 | $20.00 | $80.00 |
| 16 | Erosion log type 2 (12 inch) (208-00008) | LF | 2,300 | $10.00 | $7.30 |
| 17 | Aggregate bag (208-00035) | LF | 900 | $12.00 | $8.00 |
| 18 | Storm drain inlet protection (type I) (84 inch) (208-00053) | EACH | 6 | $300.00 | $165.00 |
| 19 | Storm drain inlet protection (type II) (208-00054) | EACH | 36 | $300.00 | $230.00 |
| 20 | Storm drain inlet protection (type I) (144 inch) (208-00057) | EACH | 4 | $450.00 | $250.00 |
| 21 | Storm drain inlet protection (type I) (204 inch) (208-00058) | EACH | 1 | $300.00 | $320.00 |
| 22 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 4 | $8,000.00 | $5,000.00 |
| 23 | Removal and disposal of sediment (labor) (208-00103) | HR | 40 | $85.00 | $115.00 |
| 24 | Removal and disposal of sediment (equipment) (208-00105) | HR | 8 | $175.00 | $250.00 |
| 25 | Sweeping (sediment removal) (208-00106) | HR | 96 | $175.00 | $220.00 |
| 26 | Pre-fabricated concrete washout structure (type 2) (208-00146) | EACH | 6 | $1,750.00 | $2,080.00 |
| 27 | Erosion control management (208-00207) | DAY | 12 | $750.00 | $600.00 |
| 28 | Reset delineator (210-00090) | EACH | 5 | $50.00 | $50.00 |
| 29 | Adjust manhole (210-04010) | EACH | 34 | $1,250.00 | $1,475.00 |
| 30 | Adjust valve box (210-04050) | EACH | 97 | $675.00 | $935.00 |
| 31 | Adjust water meter (210-04060) | EACH | 1 | $1,000.00 | $1,475.00 |
| 32 | Sod (212-00050) | SF | 600 | $3.00 | $2.80 |
| 33 | Organic fertilizer (212-00700) | LB | 210 | $2.00 | $1.85 |
| 34 | Compost (mechanically applied) (212-00701) | CY | 4 | $70.00 | $150.00 |
| 35 | Biotic soil amendments (hydraulically applied) (212-00702) | LB | 700 | $2.00 | $2.00 |
| 36 | Humate (212-00703) | LB | 30 | $2.00 | $4.50 |
| 37 | Mycorrhizae (212-00704) | LB | 4 | $18.00 | $57.00 |
| 38 | Seeding (native) hydraulic (212-00707) | ACRE | 0.20 | $3,000.00 | $7,900.00 |
| 39 | Spray-on mulch blanket (213-00012) | ACRE | 0.40 | $4,800.00 | $7,300.00 |
| 40 | Herbicide treatment (217-00000) | SY | 28,700 | $1.50 | $0.30 |
| 41 | Aggregate base course (class 6) (304-06007) | CY | 775 | $100.00 | $114.00 |
| 42 | Reconditioning (306-01000) | SY | 27,400 | $4.00 | $2.80 |
| 43 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 500 | $275.00 | $276.50 |
| 44 | Hot mix asphalt (grading SX) (75) (PG 64- 28) 00 00 (403-34751) | TON | 15,698 | $135.00 | $130.50 |
| 45 | Concrete pavement (6 inch) (412-00600) | SY | 109 | $150.00 | $131.50 |
| 46 | Concrete pavement (8 inch) (special) (412-00801) | SY | 108 | $200.00 | $143.50 |
| 47 | Guardrail type 3 (31 inch midwest guardrail system) (stained) (606-00303) | LF | 200 | $115.00 | $75.30 |
| 48 | End anchorage type 3D (606-01340) | EACH | 1 | $2,700.00 | $3,225.00 |
| 49 | End anchorage (nonflared) (stained) (606-02004) | EACH | 1 | $8,000.00 | $8,495.00 |
| 50 | End anchorage (flared) (stained) (606-02006) | EACH | 4 | $8,000.00 | $8,090.00 |
| 51 | Concrete sidewalk (608-00000) | SY | 5 | $110.00 | $107.00 |
| 52 | Concrete curb ramp (608-00010) | SY | 13 | $240.00 | $355.00 |
| 53 | Curb and gutter type 2 (section I-B) (609-21010) | LF | 405 | $45.00 | $35.90 |
| 54 | Curb and gutter type 2 (section II-B) (609-21020) | LF | 970 | $50.00 | $42.00 |
| 55 | Curb, gutter and sidewalk type 2 (section II-B) (609-22022) | LF | 30 | $100.00 | $72.00 |
| 56 | Gutter type 2 (5 foot) (609-24005) | LF | 48 | $100.00 | $60.00 |
| 57 | Delineator (flexible) (type II) (612-00042) | EACH | 4 | $110.00 | $100.00 |
| 58 | Delineator (drivable)(type II) (612-00112) | EACH | 43 | $135.00 | $85.00 |
| 59 | Barricade (type 3 M-A) (614-80321) | EACH | 37 | $150.00 | $95.00 |
| 60 | Field laboratory (class 2) (620-00012) | EACH | 1 | $50,000 | $39,000 |
| 61 | Sanitary facility (620-00020) | EACH | 1 | $8,000.00 | $7,500.00 |
| 62 | Construction surveying (625-00000) | LS | 1 | $90,000 | $62,000 |
| 63 | Mobilization (626-00000) | LS | 1 | $500,000 | $569,659 |
| 64 | Public information services (tier III) (626-01103) | LS | 1 | $7,000.00 | $7,000.00 |
| 65 | Pavement marking paint (627-00001) | GAL | 5 | $90.00 | $150.00 |
| 66 | Modified epoxy pavement marking(inlaid) (627-00009) | GAL | 80 | $290.00 | $508.50 |
| 67 | Preformed thermoplastic pavement marking (word-symbol) (627-30405) | SF | 630 | $20.00 | $26.95 |
| 68 | Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410) | SF | 6,408 | $15.00 | $14.65 |
| 69 | Flagging (630-00000) | HR | 1,200 | $50.00 | $49.50 |
| 70 | Uniformed traffic control (630-00003) | HR | 600 | $200.00 | $242.50 |
| 71 | Traffic control inspection (630-00007) | DAY | 26 | $450.00 | $350.00 |
| 72 | Traffic control management (630-00012) | DAY | 70 | $1,750.00 | $1,700.00 |
| 73 | Flashing beacon (portable) (630-80001) | EACH | 6 | $1,600.00 | $650.00 |
| 74 | Pedestrian barricade (ADA) (630-80340) | LF | 150 | $75.00 | $13.30 |
| 75 | Construction traffic sign (panel size A) (630-80341) | EACH | 328 | $100.00 | $94.50 |
| 76 | Construction traffic sign (panel size B) (630-80342) | EACH | 17 | $130.00 | $250.50 |
| 77 | Construction traffic sign (special) (630-80344) | SF | 144 | $45.00 | $48.40 |
| 78 | Portable message sign panel (630-80355) | EACH | 4 | $5,000.00 | $5,650.00 |
| 79 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 1 | $3,200.00 | $2,350.00 |
| 80 | Drum channelizing device (630-80360) | EACH | 160 | $60.00 | $37.50 |
| 81 | Traffic cone (630-80380) | EACH | 100 | $17.00 | $12.15 |
| 82 | Traffic signal (temporary) (630-86802) | DAY | 20 | $500.00 | $600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of April 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.