CDOT contract C26489 bid tabulation

CO119 AND CO 7 FROM US36 (28TH ST) TO BOULDER. Let by Colorado DOT on April 3, 2025, Boulder, Region 4. 1 bid received; low bid $4,654,490 by Brannan Sand and Gravel, LLC, -3.0% against the engineer's estimate of $4,797,502.

Owner
Colorado DOT
Letting
03 APR 2025
Pay items
82
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Brannan Sand and Gravel, LLC$4,654,490Low-3.0%
CDOT contract C26489: bids by rank

Engineer's estimate: $4,797,502.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Brannan Sand and Gravel, LLC
1Clearing and grubbing (201-00000)LS1$50,000$34,000
2Removal of delineator (202-00090)EACH25$12.00$20.00
3Removal of gutter (202-00202)LF47$15.00$29.90
4Removal of curb and gutter (202-00203)LF1,416$14.00$23.95
5Removal of curb, gutter and sidewalk (202-00204)LF30$50.00$53.80
6Removal of concrete curb ramp (202-00206)SY13$30.00$59.80
7Removal of brick pavers (202-00207)SY108$75.00$32.30
8Removal of concrete pavement (202-00210)SY109$35.00$32.30
9Removal of asphalt mat (202-00220)SY27,980$12.00$7.75
10Removal of asphalt mat (planing) (202-00240)SY52,147$3.50$3.40
11Removal of pavement marking (202-00250)SF866$1.00$5.60
12Removal of guardrail type 3 (202-01130)LF90$7.00$10.50
13Removal of end anchorage (202-01300)EACH4$525.00$490.00
14Unclassified excavation (203-00000)CY1,229$50.00$99.00
15Topsoil (onsite) (207-00700)CY162$20.00$80.00
16Erosion log type 2 (12 inch) (208-00008)LF2,300$10.00$7.30
17Aggregate bag (208-00035)LF900$12.00$8.00
18Storm drain inlet protection (type I) (84 inch) (208-00053)EACH6$300.00$165.00
19Storm drain inlet protection (type II) (208-00054)EACH36$300.00$230.00
20Storm drain inlet protection (type I) (144 inch) (208-00057)EACH4$450.00$250.00
21Storm drain inlet protection (type I) (204 inch) (208-00058)EACH1$300.00$320.00
22Pre-fabricated vehicle tracking pad (208-00075)EACH4$8,000.00$5,000.00
23Removal and disposal of sediment (labor) (208-00103)HR40$85.00$115.00
24Removal and disposal of sediment (equipment) (208-00105)HR8$175.00$250.00
25Sweeping (sediment removal) (208-00106)HR96$175.00$220.00
26Pre-fabricated concrete washout structure (type 2) (208-00146)EACH6$1,750.00$2,080.00
27Erosion control management (208-00207)DAY12$750.00$600.00
28Reset delineator (210-00090)EACH5$50.00$50.00
29Adjust manhole (210-04010)EACH34$1,250.00$1,475.00
30Adjust valve box (210-04050)EACH97$675.00$935.00
31Adjust water meter (210-04060)EACH1$1,000.00$1,475.00
32Sod (212-00050)SF600$3.00$2.80
33Organic fertilizer (212-00700)LB210$2.00$1.85
34Compost (mechanically applied) (212-00701)CY4$70.00$150.00
35Biotic soil amendments (hydraulically applied) (212-00702)LB700$2.00$2.00
36Humate (212-00703)LB30$2.00$4.50
37Mycorrhizae (212-00704)LB4$18.00$57.00
38Seeding (native) hydraulic (212-00707)ACRE0.20$3,000.00$7,900.00
39Spray-on mulch blanket (213-00012)ACRE0.40$4,800.00$7,300.00
40Herbicide treatment (217-00000)SY28,700$1.50$0.30
41Aggregate base course (class 6) (304-06007)CY775$100.00$114.00
42Reconditioning (306-01000)SY27,400$4.00$2.80
43Hot mix asphalt (patching) (asphalt) (403-00720)TON500$275.00$276.50
44Hot mix asphalt (grading SX) (75) (PG 64- 28) 00 00 (403-34751)TON15,698$135.00$130.50
45Concrete pavement (6 inch) (412-00600)SY109$150.00$131.50
46Concrete pavement (8 inch) (special) (412-00801)SY108$200.00$143.50
47Guardrail type 3 (31 inch midwest guardrail system) (stained) (606-00303)LF200$115.00$75.30
48End anchorage type 3D (606-01340)EACH1$2,700.00$3,225.00
49End anchorage (nonflared) (stained) (606-02004)EACH1$8,000.00$8,495.00
50End anchorage (flared) (stained) (606-02006)EACH4$8,000.00$8,090.00
51Concrete sidewalk (608-00000)SY5$110.00$107.00
52Concrete curb ramp (608-00010)SY13$240.00$355.00
53Curb and gutter type 2 (section I-B) (609-21010)LF405$45.00$35.90
54Curb and gutter type 2 (section II-B) (609-21020)LF970$50.00$42.00
55Curb, gutter and sidewalk type 2 (section II-B) (609-22022)LF30$100.00$72.00
56Gutter type 2 (5 foot) (609-24005)LF48$100.00$60.00
57Delineator (flexible) (type II) (612-00042)EACH4$110.00$100.00
58Delineator (drivable)(type II) (612-00112)EACH43$135.00$85.00
59Barricade (type 3 M-A) (614-80321)EACH37$150.00$95.00
60Field laboratory (class 2) (620-00012)EACH1$50,000$39,000
61Sanitary facility (620-00020)EACH1$8,000.00$7,500.00
62Construction surveying (625-00000)LS1$90,000$62,000
63Mobilization (626-00000)LS1$500,000$569,659
64Public information services (tier III) (626-01103)LS1$7,000.00$7,000.00
65Pavement marking paint (627-00001)GAL5$90.00$150.00
66Modified epoxy pavement marking(inlaid) (627-00009)GAL80$290.00$508.50
67Preformed thermoplastic pavement marking (word-symbol) (627-30405)SF630$20.00$26.95
68Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410)SF6,408$15.00$14.65
69Flagging (630-00000)HR1,200$50.00$49.50
70Uniformed traffic control (630-00003)HR600$200.00$242.50
71Traffic control inspection (630-00007)DAY26$450.00$350.00
72Traffic control management (630-00012)DAY70$1,750.00$1,700.00
73Flashing beacon (portable) (630-80001)EACH6$1,600.00$650.00
74Pedestrian barricade (ADA) (630-80340)LF150$75.00$13.30
75Construction traffic sign (panel size A) (630-80341)EACH328$100.00$94.50
76Construction traffic sign (panel size B) (630-80342)EACH17$130.00$250.50
77Construction traffic sign (special) (630-80344)SF144$45.00$48.40
78Portable message sign panel (630-80355)EACH4$5,000.00$5,650.00
79Advance warning flashing or sequencing arrow panel (C type) (630-80358)EACH1$3,200.00$2,350.00
80Drum channelizing device (630-80360)EACH160$60.00$37.50
81Traffic cone (630-80380)EACH100$17.00$12.15
82Traffic signal (temporary) (630-86802)DAY20$500.00$600.00
CDOT contract C26489: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of April 3, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy