CDOT contract C26205 bid tabulation
SH 74/KERRGULCH;SH83/GILLIAN,RUSSELLVILLE;SH30/PICCADILLY. Let by Colorado DOT on August 14, 2025, Region 1. 4 bids received; low bid $1,459,900 by Sturgeon Electric Company, Inc., -51% against the engineer's estimate of $3,000,000.
- Owner
- Colorado DOT
- Letting
- 14 AUG 2025
- Pay items
- 70
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sturgeon Electric Company, Inc. | $1,459,900 | Low | -51% |
| 2 | Lighthouse Transportation Group, LLC | $1,462,415 | 0.0% | -51% |
| 3 | Morton Electric, Inc. | $1,472,210 | +1.0% | -51% |
| 4 | Adiona Transportation Solutions LLC | $1,865,549 | +28% | -38% |
Engineer's estimate: $3,000,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Sturgeon Electric Company, Inc. | 2. Lighthouse Transportation Group, LLC | 3. Morton Electric, Inc. | 4. Adiona Transportation Solutions LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Removal of pavement marking (202-00250) | SF | 1,020 | $3.51 | $8.25 | $4.00 | $6.60 | $6.60 |
| 2 | Removal of pavement marking (12 inch) (202-00254) | SF | 658 | $4.07 | $8.25 | $4.00 | $6.60 | $6.60 |
| 3 | Removal of flashing beacon (202-00825) | EACH | 5 | $338.08 | $1,050.00 | $1,920.00 | $520.00 | $848.00 |
| 4 | Potholing (203-01597) | HR | 100 | $305.12 | $570.00 | $320.00 | $325.00 | $299.00 |
| 5 | Topsoil (onsite) (207-00700) | CY | 500 | $31.11 | $47.00 | $55.00 | $30.00 | $99.00 |
| 6 | Erosion log type 1 (12 inch) (208-00002) | LF | 500 | $7.29 | $3.50 | $10.00 | $4.73 | $10.00 |
| 7 | Aggregate bag (208-00035) | LF | 50 | $14.58 | $10.00 | $15.00 | $5.28 | $10.00 |
| 8 | Removal and disposal of sediment (labor) (208-00103) | HR | 10 | $84.82 | $105.00 | $85.00 | $50.00 | $164.00 |
| 9 | Removal and disposal of sediment (equipment) (208-00105) | HR | 10 | $144.60 | $150.00 | $135.00 | $50.00 | $203.00 |
| 10 | Sweeping (sediment removal) (208-00106) | HR | 10 | $188.87 | $120.00 | $170.00 | $50.00 | $258.00 |
| 11 | Removal of trash (208-00107) | HR | 10 | $116.91 | $120.00 | $85.00 | $50.00 | $170.00 |
| 12 | Pre-fabricated concrete washout structure (type 2) (208-00146) | EACH | 1 | $1,846.14 | $2,600.00 | $1,950.00 | $3,850.00 | $2,931.00 |
| 13 | Reset ground sign (210-00810) | EACH | 1 | $554.54 | $160.00 | $730.00 | $268.00 | $1,109.00 |
| 14 | Reset sign panel (210-00815) | EACH | 8 | $186,171 | $130.00 | $170.00 | $62.00 | $392.00 |
| 15 | Biotic soil amendments (hydraulically applied) (212-00702) | LB | 2,450 | $1.71 | $7.00 | $3.00 | $1.88 | $1.40 |
| 16 | Mycorrhizae (212-00704) | LB | 42 | $16.87 | $46.00 | $15.00 | $58.88 | $22.00 |
| 17 | Seeding (native) hydraulic (212-00707) | ACRE | 1 | $3,874.97 | $5,000.00 | $4,170.00 | $5,340.00 | $1,540.00 |
| 18 | Spray-on mulch blanket (213-00012) | ACRE | 1 | $6,232.14 | $9,700.00 | $5,125.00 | $3,510.00 | $5,225.00 |
| 19 | Wildlife biologist (240-00000) | HR | 16 | $429.70 | $200.00 | $210.00 | $220.00 | $198.00 |
| 20 | Drilled shaft (18 inch) (503-00018) | LF | 95 | $365.48 | $380.00 | $250.00 | $325.00 | $649.00 |
| 21 | Drilled shaft (36 inch) (503-00036) | LF | 17 | $743.74 | $810.00 | $815.00 | $785.00 | $1,040.00 |
| 22 | Location marker (fiber optic)(dome) (612-00260) | EACH | 1 | $205.20 | $100.00 | $245.00 | $177.00 | $93.00 |
| 23 | Location marker (utility)(flat slat) (612-00270) | EACH | 25 | $131.70 | $72.00 | $160.00 | $146.00 | $154.00 |
| 24 | 2 inch electrical conduit (bored) (613-00206) | LF | 2,920 | $24.48 | $34.50 | $32.00 | $22.00 | $34.00 |
| 25 | 3 inch electrical conduit (bored) (613-00306) | LF | 276 | $40.79 | $44.50 | $42.00 | $24.00 | $44.00 |
| 26 | 2 inch electrical conduit (plastic) (613-01200) | LF | 9,270 | $14.33 | $21.00 | $22.00 | $22.00 | $26.00 |
| 27 | 3 inch electrical conduit (plastic) (613-01300) | LF | 50 | $22.80 | $24.00 | $42.00 | $24.00 | $44.00 |
| 28 | Type one pull box (613-07001) | EACH | 47 | $1,010.29 | $1,200.00 | $1,250.00 | $1,155.00 | $1,150.00 |
| 29 | Type four pull box (613-07004) | EACH | 3 | $2,026.63 | $2,300.00 | $2,700.00 | $1,958.00 | $2,966.00 |
| 30 | Pull box (24"X16"X24") (613-07030) | EACH | 4 | $5,000.00 | $2,300.00 | $2,700.00 | $1,958.00 | $2,966.00 |
| 31 | Wiring (613-10000) | LS | 1 | $45,000 | $75,500 | $61,295 | $76,880 | $157,624 |
| 32 | Troubleshooting (613-60700) | HR | 8 | $246.57 | $160.00 | $175.00 | $134.00 | $204.00 |
| 33 | Service meter cabinet (613-80130) | EACH | 3 | $6,688.72 | $9,600.00 | $10,520 | $6,562.00 | $12,163 |
| 34 | Sign panel (class II) (614-00012) | SF | 117 | $35.90 | $80.00 | $45.00 | $58.36 | $51.00 |
| 35 | Steel signpost (4 inch round) (slipbase) (614-01554) | LF | 272 | $57.24 | $105.00 | $125.00 | $171.18 | $91.00 |
| 36 | Steel sign support (2-1/2 inch round SCH 80) (post) removal of pavement marking (614-01585) | LF | 32 | $33.47 | $57.00 | $50.00 | $60.50 | $37.00 |
| 37 | Steel sign support (2-1/2 inch round SCH 80)(slipbase) (614-01588) | EACH | 2 | $568.68 | $340.00 | $495.00 | $385.00 | $463.00 |
| 38 | 1310NM SFP optic module (614-70024) | EACH | 2 | $589.83 | $680.00 | $600.00 | $1,210.00 | $550.00 |
| 39 | Traffic signal controller cabinet (614-72855) | EACH | 4 | $19,841 | $29,000 | $27,350 | $30,027 | $29,086 |
| 40 | Traffic signal vehicle detector (micro wave type) (614-72884) | EACH | 5 | $9,257.77 | $12,500 | $12,675 | $13,658 | $15,825 |
| 41 | Microwave vehicle radar detector (614-72887) | EACH | 9 | $13,519 | $9,700.00 | $9,860.00 | $10,703 | $12,525 |
| 42 | Flashing beacon (614-80000) | EACH | 14 | $3,247.89 | $6,400.00 | $4,150.00 | $3,023.00 | $8,763.00 |
| 43 | Telemetry (field) (614-86105) | EACH | 3 | $2,906.24 | $3,200.00 | $3,925.00 | $3,391.00 | $5,278.00 |
| 44 | Traffic signal controller (type 2070LC) (614-86248) | EACH | 4 | $8,195.86 | $7,100.00 | $7,875.00 | $8,521.00 | $9,992.00 |
| 45 | Uninterrupted power supply (614-86800) | EACH | 4 | $10,149 | $8,000.00 | $7,000.00 | $7,405.00 | $10,224 |
| 46 | Fiber optic cable (single mode) (12 fiber) (614-87010) | LF | 185 | $10.09 | $8.00 | $8.00 | $6.00 | $18.00 |
| 47 | Buffer tube fan out kit (614-87015) | EACH | 1 | $305.09 | $400.00 | $600.00 | $550.00 | $88.00 |
| 48 | Fiber optic termination panel (24 fiber) (614-87024) | EACH | 1 | $2,621.39 | $1,200.00 | $834.00 | $2,750.00 | $1,652.00 |
| 49 | Closed circuit television (614-87320) | EACH | 1 | $6,482.63 | $7,100.00 | $5,715.00 | $6,900.00 | $7,630.00 |
| 50 | Test fiber optic cable (614-87350) | LS | 1 | $20,000 | $1,750.00 | $4,000.00 | $2,790.00 | $4,455.00 |
| 51 | Closed circuit television pole with lowering device (50 feet) (614-87364) | EACH | 1 | $41,013 | $25,500 | $53,710 | $28,592 | $32,339 |
| 52 | Ethernet switch type II (614-87692) | EACH | 4 | $4,826.44 | $9,200.00 | $10,425 | $7,480.00 | $5,500.00 |
| 53 | Construction surveying (625-00000) | LS | 1 | $35,000 | $15,000 | $21,895 | $14,080 | $22,000 |
| 54 | Mobilization (626-00000) | LS | 1 | $377,911 | $65,000 | $106,507 | $205,000 | $165,400 |
| 55 | Public information management (tier IV) (626-01114) | DAY | 50 | $123.38 | $91.00 | $95.00 | $176.00 | $176.00 |
| 56 | Modified epoxy pavement marking (627-00008) | GAL | 12 | $614.85 | $810.00 | $310.00 | $864.00 | $864.00 |
| 57 | Preformed thermoplastic pavement marking (word-symbol) (627-30405) | SF | 48.30 | $28.71 | $22.00 | $30.00 | $30.79 | $31.00 |
| 58 | Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410) | SF | 54 | $23.04 | $19.00 | $20.00 | $24.20 | $25.00 |
| 59 | Flagging (630-00000) | HR | 40 | $39.62 | $38.00 | $48.00 | $38.50 | $50.00 |
| 60 | Uniformed traffic control (630-00003) | HR | 40 | $156.78 | $110.00 | $134.00 | $55.00 | $132.00 |
| 61 | Uniformed traffic control (vehicle) (630-00006) | HR | 40 | $54.13 | $110.00 | $34.00 | $55.00 | $11.00 |
| 62 | Traffic control inspection (630-00007) | DAY | 20 | $126.72 | $380.00 | $295.00 | $385.00 | $594.00 |
| 63 | Traffic control management (630-00012) | DAY | 50 | $573.98 | $1,550.00 | $1,451.00 | $1,298.00 | $1,936.00 |
| 64 | Construction traffic sign (panel size A) (630-80341) | EACH | 20 | $49.80 | $43.00 | $50.00 | $44.00 | $61.00 |
| 65 | Construction traffic sign (panel size B) (630-80342) | EACH | 90 | $74.03 | $43.00 | $61.00 | $44.00 | $61.00 |
| 66 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 2 | $1,157.61 | $1,650.00 | $1,583.00 | $1,650.00 | $1,835.00 |
| 67 | Portable message sign panel (630-80359) | DAY | 20 | $68.58 | $165.00 | $82.00 | $165.00 | $138.00 |
| 68 | Traffic cone (630-80380) | EACH | 100 | $7.88 | $13.00 | $13.00 | $13.20 | $7.00 |
| 69 | Stackable vertical panels (630-80393) | EACH | 20 | $29.25 | $38.00 | $39.00 | $38.50 | $17.00 |
| 70 | Mobile attenuator (630-85041) | DAY | 50 | $835.27 | $540.00 | $895.00 | $550.00 | $1,089.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of August 14, 2025. Compiled by Mirage Metrics.