CDOT contract C26766 bid tabulation

RESURFACING OF US287 NEAR OWL CANYON RD (MM 362.76 to MP 363.56). Let by Colorado DOT on April 24, 2025, Larimer, Region 4. 3 bids received; low bid $617,733 by Martin Marietta Materials, Inc., -23% against the engineer's estimate of $800,000.

Owner
Colorado DOT
Letting
24 APR 2025
Pay items
38
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Martin Marietta Materials, Inc.$617,733Low-23%
2Coulson Excavating Company, Inc.$658,569+7.0%-18%
3Connell Resources Incorporated$661,919+7.0%-17%
CDOT contract C26766: bids by rank

Engineer's estimate: $800,000.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Martin Marietta Materials, Inc.2. Coulson Excavating Company, Inc.3. Connell Resources Incorporated
1Clearing and grubbing (201-00000)LS1$23,769$6,500.00$4,600.00$1,950.00
2Removal of asphalt mat (planing) (202-00240)SY23,273$3.00$2.55$2.80$2.25
3Removal of ground sign (202-00810)EACH20$136.70$265.00$270.00$263.00
4Potholing (203-01597)HR30$330.89$228.00$110.00$322.00
5Aggregate bag (208-00035)LF300$12.02$12.75$8.00$12.00
6Pre-fabricated vehicle tracking pad (208-00075)EACH1$10,000$3,850.00$2,500.00$7,111.00
7Removal and disposal of sediment (labor) (208-00103)HR20$79.79$105.00$50.00$46.25
8Removal and disposal of sediment (equipment) (208-00105)HR8$172.96$80.00$95.00$125.00
9Sweeping (sediment removal) (208-00106)HR20$223.02$170.00$150.00$178.00
10Aggregate base course (class 6) (special) (304-06008)CY45$166.10$185.00$150.00$168.00
11Hot mix asphalt (grading SX) (100) (PG 64- 28) (403-34851)TON2,889$125.00$111.00$105.00$106.00
12Delineator (drivable)(type I) (612-00111)EACH32$140.00$90.00$100.00$94.00
13Delineator (drivable)(type II) (612-00112)EACH4$140.00$90.00$100.00$94.00
14Delineator (drivable)(type III) (612-00113)EACH8$140.00$90.00$100.00$94.00
15Sign panel (class I) (614-00011)SF56$27.77$26.00$26.00$27.00
16Sign panel (class II) (614-00012)SF124$33.00$41.50$42.00$43.00
17Sign panel (class III) (614-00013)SF21$45.00$51.00$50.00$53.20
18Sign panel (special) (614-00037)EACH1$6,115.68$61.00$6,000.00$6,374.00
19Steel sign support (2-inch round)(post and socket) (614-01503)EACH5$517.90$345.00$360.00$360.00
20Steel sign support (2-1/2 inch round NP- 40)(post & slipbase) (614-01573)EACH16$666.94$645.00$630.00$670.00
21Flashing beacon (solar powered) (614-80001)EACH1$5,159.84$5,050.00$5,500.00$5,264.00
22Rumble strip (614-80385)LF6,472$1.00$0.50$1.10$4.80
23Sanitary facility (620-00020)EACH1$1,000.00$532.00$4,000.00$1,095.00
24Construction surveying (625-00000)LS1$18,000$11,750$6,000.00$9,835.00
25Mobilization (626-00000)LS1$97,613$40,000$80,000$42,375
26Public information services (tier IV) (626-01104)LS1$6,000.00$3,750.00$3,500.00$3,785.00
27Modified epoxy pavement marking (627-00008)GAL134$317.40$172.00$175.00$235.00
28Pavement marking paint (high build)(temporary) (627-00016)GAL112$150.00$72.00$120.00$164.00
29Preformed thermoplastic pavement marking (word-symbol) (627-30405)SF264$25.88$21.00$27.00$35.00
30Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410)SF24$24.85$10.00$22.00$28.50
31Flagging (630-00000)HR850$50.00$42.50$45.00$49.00
32Traffic control inspection (630-00007)DAY19$200.00$158.00$155.00$171.00
33Traffic control management (630-00012)DAY17$850.00$1,010.00$1,500.00$1,640.00
34Construction traffic sign (panel size A) (630-80341)EACH11$47.70$42.50$20.00$19.50
35Construction traffic sign (panel size B) (630-80342)EACH45$64.11$85.00$20.00$19.50
36Portable message sign panel (630-80355)EACH3$1,000.00$2,120.00$3,500.00$1,135.00
37Drum channelizing device (630-80360)EACH75$24.19$53.00$9.00$8.75
38Traffic cone (630-80380)EACH100$20.00$10.50$7.00$5.70
CDOT contract C26766: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy