CDOT contract C26804 bid tabulation
REGION 5 - REGION WIDE STRIPING. Let by Colorado DOT on March 6, 2025, Chafee, Rio Grande, and San Miguel, Region 5. 6 bids received; low bid $1,834,022 by Streamline Markings, Inc, -28% against the engineer's estimate of $2,554,168.
- Owner
- Colorado DOT
- Letting
- 06 MAR 2025
- Pay items
- 19
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Streamline Markings, Inc | $1,834,022 | Low | -28% |
| 2 | Roadsafe Traffic Systems, Inc | $1,982,147 | +8.0% | -22% |
| 3 | Branson Traffic Control Company, Inc | $2,038,229 | +11% | -20% |
| 4 | Straight Stripe Painting, Inc. | $2,290,654 | +25% | -10% |
| 5 | S & L Industrial | $2,296,674 | +25% | -10% |
| 6 | Prestigious Paving LLC | $2,381,631 | +30% | -7.0% |
Engineer's estimate: $2,554,168.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Streamline Markings, Inc | 2. Roadsafe Traffic Systems, Inc | 3. Branson Traffic Control Company, Inc | 4. Straight Stripe Painting, Inc. | 5. S & L Industrial | 6. Prestigious Paving LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removal of pavement marking (202-00250) | SF | 8,397 | $2.75 | $3.50 | $2.75 | $2.00 | $20.00 | $5.00 | $9.50 |
| 2 | Mobilization (626-00000) | LS | 1 | $250,000 | $27,500 | $100,000 | $172,950 | $130,000 | $100,000 | $195,000 |
| 3 | Pavement marking paint (high build) (627-00013) | GAL | 39,054 | $48.00 | $40.00 | $42.00 | $41.50 | $41.00 | $43.50 | $41.01 |
| 4 | Preformed thermoplastic pavement marking (word-symbol) (627-30405) | SF | 4,629 | $16.00 | $16.00 | $15.75 | $15.00 | $20.00 | $30.00 | $20.42 |
| 5 | Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410) | SF | 3,768 | $17.00 | $18.00 | $11.75 | $12.00 | $20.00 | $25.00 | $16.24 |
| 6 | Flagging (630-00000) | HR | 528 | $50.00 | $20.00 | $12.00 | $5.00 | $15.00 | $55.00 | $60.00 |
| 7 | Traffic control inspection (630-00007) | DAY | 28 | $150.00 | $250.00 | $150.00 | $150.00 | $100.00 | $300.00 | $1,200.00 |
| 8 | Traffic control management (630-00012) | DAY | 66 | $1,200.00 | $200.00 | $150.00 | $200.00 | $250.00 | $1,400.00 | $1,700.00 |
| 9 | Barricade (type 3 M-B) (temporary) (630-80336) | EACH | 4 | $300.00 | $50.00 | $20.00 | $397.00 | $150.00 | $200.00 | $700.00 |
| 10 | Construction traffic sign (panel size A) (630-80341) | EACH | 64 | $50.00 | $10.00 | $15.00 | $76.85 | $120.00 | $40.00 | $45.00 |
| 11 | Construction traffic sign (panel size B) (630-80342) | EACH | 8 | $60.00 | $10.00 | $15.00 | $88.75 | $120.00 | $250.00 | $60.00 |
| 12 | Portable message sign panel (630-80355) | EACH | 2 | $6,000.00 | $1,000.00 | $750.00 | $500.00 | $18,000 | $6,000.00 | $9,500.00 |
| 13 | Advance warning flashing or sequencing arrow panel (B type) (630-80357) | EACH | 2 | $5,000.00 | $1.00 | $500.00 | $250.00 | $1,500.00 | $3,000.00 | $850.00 |
| 14 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 2 | $3,000.00 | $100.00 | $500.00 | $250.00 | $1,500.00 | $3,000.00 | $1,000.00 |
| 15 | Drum channelizing device (630-80360) | EACH | 58 | $30.00 | $1.00 | $5.00 | $47.85 | $20.00 | $35.00 | $25.00 |
| 16 | Traffic cone (630-80380) | EACH | 44 | $12.00 | $1.00 | $5.00 | $12.75 | $10.00 | $35.00 | $17.00 |
| 17 | Mobile pavement marking zone (630-80511) | LS | 1 | $80,000 | $35,000 | $75,000 | $75,000 | $80,000 | $40,000 | $95,000 |
| 18 | Impact attenuator (truck mounted attenuator) (temporary) (630-85040) | EACH | 2 | $14,220 | $2,000.00 | $250.00 | $2,250.00 | $31,500 | $5,000.00 | $8,000.00 |
| 19 | Night work lighting (632-00000) | LS | 1 | $15,000 | $100.00 | $500.00 | $1,000.00 | $500.00 | $10,000 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of March 6, 2025. Compiled by Mirage Metrics.