CDOT contract C26391 bid tabulation
This is a priority repair culvert rehabilitation project. The scope of this work is to line 58 corrugated metal pipes (CMP) using UV Cured-in-Place Pipe in Region 1. All 58 CMPs are less than 48 inches in diameter. CMPs are located in various areas/counties such as Floyd Hill, Mount Blue Sky, Bertho. Let by Colorado DOT on June 5, 2025, Clear Creek, Gilpin, and Jefferson, Region 1. 3 bids received; low bid $2,422,341 by Insituform Technologies, LLC, -10% against the engineer's estimate of $2,695,118.
- Owner
- Colorado DOT
- Letting
- 05 JUN 2025
- Pay items
- 42
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Insituform Technologies, LLC | $2,422,341 | Low | -10% |
| 2 | HCG Construction LLC | $3,223,846 | +33% | +20% |
| 3 | American West Construction, LLC | $3,674,540 | +52% | +36% |
Engineer's estimate: $2,695,118.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Insituform Technologies, LLC | 2. HCG Construction LLC | 3. American West Construction, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Tree trimming (202-00008) | HR | 32 | $205.73 | $225.00 | $200.00 | $820.00 |
| 2 | Removal of pipe (202-00035) | LF | 8 | $137.64 | $530.00 | $250.00 | $810.00 |
| 3 | Removal of end section (202-00037) | EACH | 49 | $700.00 | $1,145.00 | $1,000.00 | $1,400.00 |
| 4 | Removal of delineator (202-00090) | EACH | 124 | $14.08 | $25.00 | $25.00 | $26.00 |
| 5 | Clean culvert (202-04002) | EACH | 61 | $5,000.00 | $1,740.00 | $2,500.00 | $7,000.00 |
| 6 | Potholing (203-01597) | HR | 50 | $360.95 | $125.00 | $475.00 | $400.00 |
| 7 | Erosion log type 1 (12 inch) (208-00002) | LF | 1,160 | $7.09 | $8.50 | $10.00 | $11.00 |
| 8 | Removal and disposal of sediment (labor) (208-00103) | HR | 40 | $80.11 | $120.00 | $75.00 | $50.00 |
| 9 | Removal and disposal of sediment (equipment) (208-00105) | HR | 40 | $169.39 | $175.00 | $150.00 | $135.00 |
| 10 | Reset end section (210-00015) | EACH | 50 | $1,800.00 | $450.00 | $1,000.00 | $900.00 |
| 11 | Reset delineator (210-00090) | EACH | 124 | $36.02 | $50.00 | $150.00 | $26.00 |
| 12 | Cement grout (voids) (211-02277) | CY | 61 | $3,500.00 | $850.00 | $2,500.00 | $2,400.00 |
| 13 | Wildlife biologist (240-00000) | HR | 40 | $159.15 | $125.00 | $175.00 | $250.00 |
| 14 | Aggregate base course (class 6) (304-06007) | CY | 4 | $191.62 | $1,650.00 | $400.00 | $3,100.00 |
| 15 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 4 | $508.35 | $650.00 | $1,000.00 | $7,700.00 |
| 16 | Culvert lining (603-00000) | LF | 75 | $248.24 | $145.00 | $225.00 | $500.00 |
| 17 | Culvert lining (15 inch) (603-00015) | LF | 44 | $85.00 | $260.00 | $235.00 | $600.00 |
| 18 | Culvert lining (18 inch) (603-00018) | LF | 239 | $120.00 | $140.00 | $255.00 | $360.00 |
| 19 | Culvert lining (24 inch) (603-00026) | LF | 4,377 | $191.28 | $163.00 | $295.00 | $295.00 |
| 20 | Culvert lining (36 inch) (603-00036) | LF | 64 | $499.56 | $325.00 | $525.00 | $800.00 |
| 21 | 18 inch steel end section (603-30018) | EACH | 1 | $859.01 | $1,905.00 | $2,500.00 | $1,500.00 |
| 22 | 24 inch steel end section (603-30024) | EACH | 49 | $356.86 | $1,950.00 | $2,000.00 | $1,700.00 |
| 23 | Fence (plastic) (607-11525) | LF | 764 | $4.77 | $2.50 | $9.00 | $7.00 |
| 24 | Delineator (type III) (612-00003) | EACH | 124 | $38.94 | $95.00 | $80.00 | $50.00 |
| 25 | Sanitary facility (620-00020) | EACH | 2 | $3,601.29 | $650.00 | $7,500.00 | $5,100.00 |
| 26 | Mobilization (626-00000) | LS | 1 | $438,289 | $287,165 | $300,000 | $364,000 |
| 27 | Public information management (tier IV) (626-01114) | DAY | 225 | $131.71 | $85.00 | $125.00 | $57.00 |
| 28 | Pavement marking paint (high build) (627-00013) | GAL | 5 | $318.72 | $125.00 | $500.00 | $1,300.00 |
| 29 | Flagging (630-00000) | HR | 1,000 | $50.00 | $60.00 | $35.00 | $70.00 |
| 30 | Traffic control inspection (630-00007) | DAY | 76 | $300.00 | $685.00 | $400.00 | $710.00 |
| 31 | Traffic control management (630-00012) | DAY | 152 | $1,600.00 | $2,235.00 | $1,100.00 | $2,300.00 |
| 32 | Uniformed traffic control coordination (630-00015) | HR | 40 | $60.62 | $30.00 | $100.00 | $29.00 |
| 33 | Barricade (type 3 M-B) (temporary) (630-80336) | EACH | 6 | $243.62 | $105.00 | $400.00 | $110.00 |
| 34 | Construction traffic sign (panel size A) (630-80341) | EACH | 29 | $50.50 | $70.00 | $150.00 | $72.00 |
| 35 | Construction traffic sign (panel size B) (630-80342) | EACH | 103 | $74.45 | $70.00 | $200.00 | $72.00 |
| 36 | Vertical panel (630-80350) | EACH | 150 | $32.53 | $25.00 | $55.00 | $26.00 |
| 37 | Portable message sign panel (630-80355) | EACH | 12 | $9,200.00 | $4,750.00 | $17,000 | $4,900.00 |
| 38 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 6 | $1,256.34 | $2,120.00 | $8,500.00 | $2,200.00 |
| 39 | Drum channelizing device (630-80360) | EACH | 300 | $42.58 | $25.00 | $55.00 | $26.00 |
| 40 | Traffic cone (630-80380) | EACH | 300 | $12.07 | $8.00 | $20.00 | $8.00 |
| 41 | Portable rumble strips (temporary) (630-80440) | EACH | 6 | $1,722.66 | $1,730.00 | $1,200.00 | $1,800.00 |
| 42 | Impact attenuator (truck mounted attenuator) (temporary) (630-85040) | EACH | 6 | $15,107 | $59,485 | $50,000 | $48,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of June 5, 2025. Compiled by Mirage Metrics.