CDOT contract C26207 bid tabulation

Project 26207 is a critical culvert project that involves the maintenance of numerous culverts throughout R4. Maintenance mostly involves Cured-in-place-pipe (CIPP) lining with one location being a culvert replacement. The following are major items of work associated with this project...culvert lini. Let by Colorado DOT on July 17, 2025, Region 4. 3 bids received; low bid $1,864,083 by Subsurface, Inc, +7.4% against the engineer's estimate of $1,736,010.

Owner
Colorado DOT
Letting
17 JUL 2025
Pay items
66
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Subsurface, Inc$1,864,083Low+7.0%
2American West Construction, LLC$1,983,402+6.0%+14%
3Edge Contracting, Inc.$2,310,616+24%+33%
CDOT contract C26207: bids by rank

Engineer's estimate: $1,736,010.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Subsurface, Inc2. American West Construction, LLC3. Edge Contracting, Inc.
1Clearing and grubbing (201-00000)LS1$16,378$22,000$100,000$60,000
2Removal of pipe (202-00035)LF48$63.08$330.00$140.00$210.00
3Removal of end section (202-00037)EACH4$458.17$550.00$840.00$975.00
4Removal of delineator (202-00090)EACH38$15.64$11.00$31.00$90.00
5Removal of asphalt mat (202-00220)SY49$56.68$27.50$36.00$290.00
6Removal of pavement marking (202-00250)SF2,550$3.71$4.50$1.00$1.50
7Clean culvert (202-04002)EACH20$2,751.63$3,800.00$7,100.00$12,000
8Unclassified excavation (203-00000)CY130$98.01$220.00$75.00$230.00
9Backhoe (203-01510)HR15$123.46$192.50$140.00$210.00
10Sweeping (with pickup broom) (203-01622)HR54$187.18$158.13$190.00$135.00
11Erosion log type 1 (12 inch) (208-00002)LF1,950$7.21$11.00$7.00$15.00
12Aggregate bag (208-00035)LF1,525$10.60$11.00$12.00$18.00
13Concrete washout structure (208-00045)EACH12$1,529.90$3,000.00$2,600.00$700.00
14Rigid inlet protection device (208-00055)EACH2$408.52$1,650.00$6,100.00$1,200.00
15Reset fence (210-01000)LF140$26.50$82.50$17.00$22.00
16Cement grout (voids) (211-02277)CY20$692.96$1,600.00$2,500.00$2,850.00
17Organic fertilizer (212-00700)LB219$3.04$2.48$1.00$11.00
18Compost (mechanically applied) (212-00701)CY50$103.93$165.00$98.00$240.00
19Mycorrhizae (212-00704)LB49$16.88$13.75$37.00$24.00
20Seeding (native) broadcast (212-00708)ACRE0.73$2,542.00$3,162.50$1,200.00$21,500
21Soil retention blanket (straw-coconut) (biodegradable class 1) (216-00201)SY3,305$4.42$6.88$3.00$7.00
22Hot mix asphalt (patching) (asphalt) (403-00721)SY49$253.26$423.50$350.00$300.00
23Joint sealant (408-01100)LF684$18.58$35.00$33.00$22.00
24Geotextile (drainage) (class 1) (420-00112)SY29$17.51$55.00$32.00$11.00
25Riprap (9 inch) (506-00209)CY9$264.74$1,100.00$210.00$420.00
26Structural steel (509-00000)LB230$4.94$20.00$280.00$155.00
27Concrete sealer (515-00400)SY339$23.08$25.00$38.00$17.50
28Concrete class B (601-01000)CY4.40$2,252.60$3,850.00$8,400.00$5,200.00
29Concrete class D (601-03000)CY44$2,582.86$3,000.00$2,100.00$2,200.00
30Reinforcing steel (602-00000)LB422$6.01$11.00$14.00$8.00
31Welded wire fabric (602-00210)SY707$25.76$34.00$25.00$27.00
32Culvert lining (603-00000)LF161$248.24$295.00$230.00$255.00
33Culvert lining (18 inch) (603-00018)LF46$400.00$215.00$470.00$710.00
34Culvert lining (24 inch) (603-00026)LF620$358.41$278.00$300.00$535.00
35Culvert lining (30 inch) (603-00030)LF57$225.30$365.00$550.00$540.00
36Culvert lining (48 inch) (603-00048)LF76$606.26$550.00$650.00$1,100.00
37Culvert lining (48 inch)(special) (603-00049)LF64$865.38$773.00$700.00$1,400.00
38Culvert lining (60 inch) (603-00060)LF117$449.14$1,170.00$750.00$1,725.00
3953X34 inch reinforced concrete pipe elliptical (complete in place) (603-02425)LF53$262.27$2,750.00$970.00$1,400.00
4018 inch steel end section (603-30018)EACH2$808.58$550.00$680.00$1,400.00
4124 inch steel end section (603-30024)EACH6$880.99$770.00$910.00$1,700.00
42Fence (plastic) (607-11525)LF630$4.72$11.00$6.00$7.00
43Delineator (type III) (612-00003)EACH38$41.94$50.00$62.00$120.00
44Sanitary facility (620-00020)EACH2$2,054.82$4,500.00$1,800.00$680.00
45Detour pavement (621-00450)SY410$694.60$467.50$160.00$285.00
46Construction surveying (hourly) (625-00001)HR16$245.29$350.00$370.00$520.00
47Mobilization (626-00000)LS1$120,000$175,000$235,000$225,000
48Public information services (tier IV) (626-01104)LS1$7,500.00$4,950.00$4,900.00$7,000.00
49Modified epoxy pavement marking (627-00008)GAL20$362.20$400.00$180.00$160.00
50Pavement marking paint (waterborne) (627-00011)GAL30$76.78$125.00$120.00$80.00
51Flagging (630-00000)HR550$40.00$57.20$65.00$70.00
52Traffic control inspection (630-00007)DAY18$164.83$396.00$450.00$400.00
53Traffic control management (630-00012)DAY45$542.78$1,914.00$2,200.00$2,265.00
54Barricade (type 3 M-A) (temporary) (630-80335)EACH11$177.38$82.50$93.00$80.00
55Barricade (type 3 M-B) (temporary) (630-80336)EACH9$229.97$165.00$190.00$160.00
56Construction traffic sign (panel size A) (630-80341)EACH33$49.29$55.00$62.00$55.00
57Construction traffic sign (panel size B) (630-80342)EACH166$74.47$55.00$62.00$51.00
58Vertical panel (630-80350)EACH60$35.54$18.15$21.00$20.00
59Portable message sign panel (630-80355)EACH4$5,267.93$6,215.00$7,000.00$8,500.00
60Drum channelizing device (630-80360)EACH75$31.40$24.75$28.00$25.00
61Barrier (temporary) (630-80370)LF260$240.00$110.00$61.00$45.00
62Traffic cone (630-80380)EACH75$8.31$9.35$11.00$12.00
63Tubular marker (630-80384)EACH75$29.70$13.75$16.00$14.00
64Impact attenuator (temporary) (630-85010)EACH2$7,000.00$11,000$2,900.00$10,900
65Mobile attenuator (630-85020)EACH6$36,823$4,400.00$36,000$3,500.00
66Traffic signal (temporary) (630-86802)DAY50$1,100.00$214.50$240.00$200.00
CDOT contract C26207: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of July 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way