CDOT contract C26234 bid tabulation

Culvert (11) remove & replace culvert locations combined with (8)rehab culvert locations. remove & replace culvert locations as shown in the plans; sh 41 (mm 8.64), us 160 (mm 47.81, 64 & 194.42), us. Let by Colorado DOT on December 18, 2025. 3 bids received; low bid $8,859,323 by Native Sun Materials Inc, +31% against the engineer's estimate of $6,786,947.

Owner
Colorado DOT
Letting
18 DEC 2025
Pay items
137
Data through
10 SEP 2026

2 of the 3 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Native Sun Materials Inc$8,859,323Low+31%
3American West Construction, LLC$10,084,223+14%+49%
CDOT contract C26234: bids by rank

Engineer's estimate: $6,786,947.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Native Sun Materials Inc2. American West Construction, LLC
1Clearing and grubbing (201-00000)LS1$12,300$87,485$170,000
2Removal of structure (202-00001)EACH1$250.00$14,636$690.00
3Removal of headwall (202-00015)EACH1$250.00$2,295.17$3,300.00
4Removal of pipe (202-00035)LF840$95.00$28.87$55.00
5Removal of pipe (special (202-00036)LF240$120.00$36.34$140.00
6Removal of delineator (202-00090)EACH46$25.00$121.00$16.00
7Removal of concrete box culvert (202-00120)LF40$330.00$76.24$540.00
8Removal of asphalt mat (202-00220)SY2,332$23.00$25.71$45.00
9Removal of guardrail type 3 (202-01130)LF2,201$5.00$18.15$7.00
10Removal of end anchorage (202-01300)EACH12$400.00$665.50$520.00
11Clean culvert (202-04002)EACH7$5,000.00$4,567.20$6,200.00
12Plug culvert (202-04007)CY115$400.00$594.00$480.00
13Unclassified excavation (203-00000)CY29$180.00$295.34$110.00
14Unsuitable material (203-00050)CY50$200.00$295.34$170.00
15Embankment material (complete in place (203-00060)CY720$200.00$160.79$130.00
16Combination loader (203-01594)HR40$185.00$346.50$250.00
17Potholing (203-01597)HR40$425.00$880.00$610.00
18Structure excavation (206-00000)CY1,943$40.00$57.30$140.00
19Structure backfill (flow-fill (206-00065)CY539$300.00$555.50$400.00
20Structure backfill (class 1 (206-00100)CY349$90.00$85.18$470.00
21Shoring (area 1 41 MP 8.64 (206-01781)LS1$22,000$5,957.56$21,000
22Shoring (area 2 184 MP 18.24 (206-01782)LS1$22,000$26,378$9,900.00
23Shoring (area 3 160 MP 47.81 (206-01783)LS1$22,000$10,094$33,000
24Shoring (area 4 160 MP 64 (206-01784)LS1$22,000$9,750.91$26,000
25Shoring (area 5 550 MP 28.71 (206-01785)LS1$22,000$15,940$28,000
26Shoring (area 6 172 MP 3.4 (206-01786)LS1$22,000$18,416$35,000
27Shoring (area 7 151 MP .2.72 (206-01787)LS1$22,000$11,140$21,000
28Shoring (area 8 160 MP 194.42 (206-01788)LS1$22,000$8,776.61$21,000
29Shoring (area 9 285 MP 7.29 (206-01789)LS1$22,000$10,390$21,000
30Shoring (area 10 285 MP 53.28 (206-01790)LS1$22,000$9,815.52$23,000
31Shoring (area 11 285 MP 85.5 (206-01791)LS1$22,000$8,361.34$23,000
32Shoring (area 12 17 MP 10.46 (206-01792)LS1$22,000$26,945$28,000
33Shoring (area 13 17 MP 15.02 (206-01793)LS1$22,000$11,620$19,000
34Shoring (area 14 151 MP 4.32 (206-01794)LS1$22,000$43,899$21,000
35Erosion log type 1 (12 inch (208-00002)LF4,360$9.00$6.66$7.00
36Aggregate bag (208-00035)LF800$10.00$14.52$15.00
37Prefabricated concrete washout structure (208-00046)EACH1$10,000$10,285$10,000
38Pre tabrcated vehicle tracking pad (208-00075)EACH4$4,000.00$11,495$4,600.00
39Removal and disposal of sediment (labor (208-00103)HR40$85.00$220.00$97.00
40Removal and disposal of sediment (208-00105)HR40$155.00$220.00$200.00
41Sweeping (sediment removal (208-00106)HR40$250.00$330.00$210.00
42Removal of trash (208-00107)HR40$200.00$220.00$97.00
43Fre-fapricated concrete washout structure (208-00146)EACH19$4,300.00$4,235.00$530.00
44Wee control 151 MP 4.32 (208-00400)LS1$32,000$30,250$10,000
45Water control 160 MP 47.81 (208-00400)LS1$32,000$18,150$10,000
46Water control 160 MP 54.72 (208-00400)LS1$32,000$10,285$8,000.00
47Water control 17 MP 10.46 (208-00400)LS1$32,000$42,350$8,000.00
48Water control 17 MP 15.02 (208-00400)LS1$32,000$30,250$9,200.00
49Water control 172 MP 3.4 (208-00400)LS1$32,000$78,650$66,000
50Water control 172 MP 4.36 (208-00400)LS1$32,000$36,300$10,000
51Water control 184 MP 8.64 (208-00400)LS1$32,000$30,250$11,000
52Water control 285 MP 85.5 (208-00400)LS1$32,000$18,150$6,800.00
53Water control 550 MP 28.71 (208-00400)LS1$32,000$30,250$8,600.00
54Reset fence (210-01000)LF1,790$15.00$18.15$32.00
55Relay riprap (210-02900)CY106$50.00$275.00$470.00
56Cement grout (voids (211-02277)CY34$2,500.00$759.00$2,100.00
57Nore sol amendments (hydraulically (212-00702)LB14,070$3.00$2.42$1.50
58Vocontizae (212-00704)LB241$21.00$26.62$28.00
59Seeding (native hydraulic (212-00707)ACRE4.02$2,000.00$4,235.00$2,000.00
60Seeding (wetland hydraulic (212-00710)ACRE0.32$4,700.00$18,755$2,100.00
61Mulching (weed free (213-00003)ACRE3.02$4,300.00$3,388.00$3,700.00
62Spray-on mulch blanket (213-00012)ACRE1$6,500.00$9,317.00$10,000
63Mulch tackifier (213-00061)LB182$6.00$6.05$6.00
64Live willow stakes (214-01013)EACH784$8.50$26.62$28.00
65Wildlife biologist (240-00000)HR40$325.00$363.00$410.00
66Aggregate base course (class 2 (304-02000)TON879$70.00$66.71$85.00
67Aggregate base course (class 6 (304-06000)TON678$80.00$60.66$310.00
68Hot mix asphalt (patching (asphalt (403-00720)TON530$250.00$616.74$580.00
69Hot mix asphalt (patching (asphalt (403-00721)SY863$200.00$330.52$480.00
70Pot mix asphalt (grading SX (100 (PG 64- (403-34851)TON449$250.00$2.42$1.00
71Foint sealant (408-01100)LF934$32.00$12.10$58.00
72Geotextile (drainage (class 2 (420-00113)SY507$6.00$42.35$16.00
73Geogrid pavement reinforcement (420-00520)SY1,469$15.00$5.72$5.00
74Steel sheet piling (type 1 (501-00000)SF594$80.00$114.95$120.00
75Steel sheet piling cap (501-00210)LF22$120.00$423.50$1,100.00
76Riprap (9 inch (506-00209)CY17$275.00$151.25$590.00
77Riprap (18 inch (506-00218)CY550$200.00$186.45$350.00
78In-channel boulder feature (boulder (506-00602)EACH2$300.00$6,875.00$3,900.00
79Concrete slope and ditch paving (507-00000)CY5$2,200.00$1,298.00$4,200.00
80Structural steel (509-00000)LB328$62.00$10.34$260.00
81Concrete sealer (515-00400)SY558$30.00$60.50$20.00
82Concrete class D (601-03000)CY157.40$1,100.00$1,419.00$3,500.00
83Concrete class D (special (baffles (601-03027)CY5$1,200.00$2,134.00$4,100.00
84Concrete class D (special (invert pave (601-03027)CY84$1,200.00$2,134.00$3,600.00
85Reinforcing steel (epoxy coated (602-00020)LB16,523$2.00$2.43$3.00
86Welded wire fabric (602-00210)SY1,284$30.00$113.71$22.00
87Annular space grouting (603-00001)CY75$400.00$869.00$1,500.00
88Culvert lining (48 inch (special (603-00049)LF211$600.00$681.86$710.00
89Culver lining (48 inch (special (48 inch (603-00049)LF88$600.00$505.71$810.00
90Inch reinforced concrete pipe (603-01420)LF60$300.00$582.88$1,300.00
9154 inch reinforced concrete pipe item 603- (603-01540)LF80$500.00$671.99$1,300.00
9260 inch reinforced concrete pipe (603-01600)LF408$350.00$767.17$1,200.00
9353X34 inch reinforced concrete pipe (603-02420)LF184$360.00$936.27$1,200.00
9468X43 inch reinforced concrete pipe (603-02540)LF64$450.00$694.27$1,300.00
9542 inch reinforced concrete end section (603-05042)EACH2$4,280.00$4,345.00$5,600.00
9654 inch reinforced concrete end section (603-05054)EACH2$3,025.00$6,985.00$7,400.00
9753X34 inch reinforced concrete end (603-05142)EACH4$3,000.00$10,615$7,700.00
9836 inch corrugated steel pipe (603-10360)LF140$200.00$416.45$640.00
9966 inch equivalent corrugated steel pipe (603-15066)LF100$350.00$579.32$1,300.00
10072 inch equivalent corrugated steel pipe (603-15072)LF40$625.00$657.97$2,000.00
10136 inch steel end section (603-30036)EACH1$2,800.00$4,038.77$2,400.00
10260 inch steel end section (603-30060)EACH2$3,000.00$6,579.71$5,800.00
10366 inch equivalent arch steel end section (603-31366)EACH2$3,000.00$8,152.71$6,600.00
10410X6 foot concrete box culvert (precast (603-71006)LF56$3,000.00$1,918.66$3,900.00
105Guardrail type 3 (31 inch midwest guardrail (606-00302)LF2,700$50.00$60.50$43.00
106End anchorage (nonflared (606-02003)EACH3$4,500.00$6,050.00$5,100.00
107End anchorage (flared (606-02005)EACH9$4,600.00$5,808.00$5,100.00
108Fence (plastic (607-11525)LF200$13.00$6.05$6.00
109Fence (temporary (607-11580)LF160$7.00$12.10$19.00
110Delineator (type (612-00001)EACH9$50.00$181.50$40.00
111Delineator (type III (612-00003)EACH37$80.00$181.50$47.00
112Flashing beacon (614-80000)EACH16$4,000.00$786.50$650.00
113Field office (class 1 (620-00001)EACH2$60,000$90,750$60,000
114Sanitary facility (620-00020)EACH2$7,500.00$21,780$11,000
115Detour 141 MP 8.64 (621-00425)LS1$25,460$18,663$166,000
116Detour 151 MP 2.72 (621-00425)LS1$25,460$7,168.04$166,000
117Detour 151 MP 4.32 (621-00425)LS1$25,460$7,168.04$100.00
118Detour 17 MP 15.02 (621-00425)LS1$25,460$7,168.04$166,000
119Construction surveying (625-00000)LS1$60,000$336,320$96,000
120Mobilization (626-00000)LS1$1,200,000$946,861$983,000
121Public information services (tier IV (626-01104)LS1$92.00$50,820$24,000
122Pavement marking paint (high build (627-00013)GAL18$61.00$544.50$92.00
123Pavement marking paint (high (627-00016)GAL11$175.00$605.00$79.00
124Flagging (630-00000)HR8,500$48.00$76.44$55.00
125Traffic control inspection (630-00007)DAY160$435.00$229.14$620.00
126Traffic control management (630-00012)DAY350$1,650.00$2,292.09$1,300.00
127Construction traffic sign (panel size A (630-80341)EACH56$55.00$113.44$210.00
128Construction traffic sign (panel size B (630-80342)EACH24$67.00$128.56$210.00
129Construction traffic sign (special (630-80344)SF128$38.00$18.26$41.00
130Portable message sign panel (630-80355)EACH4$8,800.00$5,445.00$19,000
131Advance warning flashing or sequencing (630-80357)EACH4$2,830.00$27,225$1,400.00
132Drum channelizing device (630-80360)EACH430$35.00$66.55$2.50
133Drum channelizing device (with light (630-80364)EACH200$45.00$96.80$55.00
134Concrete barrier (temporary (furnish and (630-80372)LF400$110.00$102.85$820.00
135Portable rumble strips (temporary (630-80440)EACH12$2,800.00$9,075.00$690.00
136Impact attenuator (temporary (630-85010)EACH4$8,000.00$15,881$4,800.00
137Traffic signal (temporary (1 EA= 1 pair (630-86810)EACH2$30,000$164,863$69,000
CDOT contract C26234: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy