CDOT contract C26234 bid tabulation
Culvert (11) remove & replace culvert locations combined with (8)rehab culvert locations. remove & replace culvert locations as shown in the plans; sh 41 (mm 8.64), us 160 (mm 47.81, 64 & 194.42), us. Let by Colorado DOT on December 18, 2025. 3 bids received; low bid $8,859,323 by Native Sun Materials Inc, +31% against the engineer's estimate of $6,786,947.
- Owner
- Colorado DOT
- Letting
- 18 DEC 2025
- Pay items
- 137
- Data through
- 10 SEP 2026
2 of the 3 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Native Sun Materials Inc | $8,859,323 | Low | +31% |
| 3 | American West Construction, LLC | $10,084,223 | +14% | +49% |
Engineer's estimate: $6,786,947.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Native Sun Materials Inc | 2. American West Construction, LLC |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201-00000) | LS | 1 | $12,300 | $87,485 | $170,000 |
| 2 | Removal of structure (202-00001) | EACH | 1 | $250.00 | $14,636 | $690.00 |
| 3 | Removal of headwall (202-00015) | EACH | 1 | $250.00 | $2,295.17 | $3,300.00 |
| 4 | Removal of pipe (202-00035) | LF | 840 | $95.00 | $28.87 | $55.00 |
| 5 | Removal of pipe (special (202-00036) | LF | 240 | $120.00 | $36.34 | $140.00 |
| 6 | Removal of delineator (202-00090) | EACH | 46 | $25.00 | $121.00 | $16.00 |
| 7 | Removal of concrete box culvert (202-00120) | LF | 40 | $330.00 | $76.24 | $540.00 |
| 8 | Removal of asphalt mat (202-00220) | SY | 2,332 | $23.00 | $25.71 | $45.00 |
| 9 | Removal of guardrail type 3 (202-01130) | LF | 2,201 | $5.00 | $18.15 | $7.00 |
| 10 | Removal of end anchorage (202-01300) | EACH | 12 | $400.00 | $665.50 | $520.00 |
| 11 | Clean culvert (202-04002) | EACH | 7 | $5,000.00 | $4,567.20 | $6,200.00 |
| 12 | Plug culvert (202-04007) | CY | 115 | $400.00 | $594.00 | $480.00 |
| 13 | Unclassified excavation (203-00000) | CY | 29 | $180.00 | $295.34 | $110.00 |
| 14 | Unsuitable material (203-00050) | CY | 50 | $200.00 | $295.34 | $170.00 |
| 15 | Embankment material (complete in place (203-00060) | CY | 720 | $200.00 | $160.79 | $130.00 |
| 16 | Combination loader (203-01594) | HR | 40 | $185.00 | $346.50 | $250.00 |
| 17 | Potholing (203-01597) | HR | 40 | $425.00 | $880.00 | $610.00 |
| 18 | Structure excavation (206-00000) | CY | 1,943 | $40.00 | $57.30 | $140.00 |
| 19 | Structure backfill (flow-fill (206-00065) | CY | 539 | $300.00 | $555.50 | $400.00 |
| 20 | Structure backfill (class 1 (206-00100) | CY | 349 | $90.00 | $85.18 | $470.00 |
| 21 | Shoring (area 1 41 MP 8.64 (206-01781) | LS | 1 | $22,000 | $5,957.56 | $21,000 |
| 22 | Shoring (area 2 184 MP 18.24 (206-01782) | LS | 1 | $22,000 | $26,378 | $9,900.00 |
| 23 | Shoring (area 3 160 MP 47.81 (206-01783) | LS | 1 | $22,000 | $10,094 | $33,000 |
| 24 | Shoring (area 4 160 MP 64 (206-01784) | LS | 1 | $22,000 | $9,750.91 | $26,000 |
| 25 | Shoring (area 5 550 MP 28.71 (206-01785) | LS | 1 | $22,000 | $15,940 | $28,000 |
| 26 | Shoring (area 6 172 MP 3.4 (206-01786) | LS | 1 | $22,000 | $18,416 | $35,000 |
| 27 | Shoring (area 7 151 MP .2.72 (206-01787) | LS | 1 | $22,000 | $11,140 | $21,000 |
| 28 | Shoring (area 8 160 MP 194.42 (206-01788) | LS | 1 | $22,000 | $8,776.61 | $21,000 |
| 29 | Shoring (area 9 285 MP 7.29 (206-01789) | LS | 1 | $22,000 | $10,390 | $21,000 |
| 30 | Shoring (area 10 285 MP 53.28 (206-01790) | LS | 1 | $22,000 | $9,815.52 | $23,000 |
| 31 | Shoring (area 11 285 MP 85.5 (206-01791) | LS | 1 | $22,000 | $8,361.34 | $23,000 |
| 32 | Shoring (area 12 17 MP 10.46 (206-01792) | LS | 1 | $22,000 | $26,945 | $28,000 |
| 33 | Shoring (area 13 17 MP 15.02 (206-01793) | LS | 1 | $22,000 | $11,620 | $19,000 |
| 34 | Shoring (area 14 151 MP 4.32 (206-01794) | LS | 1 | $22,000 | $43,899 | $21,000 |
| 35 | Erosion log type 1 (12 inch (208-00002) | LF | 4,360 | $9.00 | $6.66 | $7.00 |
| 36 | Aggregate bag (208-00035) | LF | 800 | $10.00 | $14.52 | $15.00 |
| 37 | Prefabricated concrete washout structure (208-00046) | EACH | 1 | $10,000 | $10,285 | $10,000 |
| 38 | Pre tabrcated vehicle tracking pad (208-00075) | EACH | 4 | $4,000.00 | $11,495 | $4,600.00 |
| 39 | Removal and disposal of sediment (labor (208-00103) | HR | 40 | $85.00 | $220.00 | $97.00 |
| 40 | Removal and disposal of sediment (208-00105) | HR | 40 | $155.00 | $220.00 | $200.00 |
| 41 | Sweeping (sediment removal (208-00106) | HR | 40 | $250.00 | $330.00 | $210.00 |
| 42 | Removal of trash (208-00107) | HR | 40 | $200.00 | $220.00 | $97.00 |
| 43 | Fre-fapricated concrete washout structure (208-00146) | EACH | 19 | $4,300.00 | $4,235.00 | $530.00 |
| 44 | Wee control 151 MP 4.32 (208-00400) | LS | 1 | $32,000 | $30,250 | $10,000 |
| 45 | Water control 160 MP 47.81 (208-00400) | LS | 1 | $32,000 | $18,150 | $10,000 |
| 46 | Water control 160 MP 54.72 (208-00400) | LS | 1 | $32,000 | $10,285 | $8,000.00 |
| 47 | Water control 17 MP 10.46 (208-00400) | LS | 1 | $32,000 | $42,350 | $8,000.00 |
| 48 | Water control 17 MP 15.02 (208-00400) | LS | 1 | $32,000 | $30,250 | $9,200.00 |
| 49 | Water control 172 MP 3.4 (208-00400) | LS | 1 | $32,000 | $78,650 | $66,000 |
| 50 | Water control 172 MP 4.36 (208-00400) | LS | 1 | $32,000 | $36,300 | $10,000 |
| 51 | Water control 184 MP 8.64 (208-00400) | LS | 1 | $32,000 | $30,250 | $11,000 |
| 52 | Water control 285 MP 85.5 (208-00400) | LS | 1 | $32,000 | $18,150 | $6,800.00 |
| 53 | Water control 550 MP 28.71 (208-00400) | LS | 1 | $32,000 | $30,250 | $8,600.00 |
| 54 | Reset fence (210-01000) | LF | 1,790 | $15.00 | $18.15 | $32.00 |
| 55 | Relay riprap (210-02900) | CY | 106 | $50.00 | $275.00 | $470.00 |
| 56 | Cement grout (voids (211-02277) | CY | 34 | $2,500.00 | $759.00 | $2,100.00 |
| 57 | Nore sol amendments (hydraulically (212-00702) | LB | 14,070 | $3.00 | $2.42 | $1.50 |
| 58 | Vocontizae (212-00704) | LB | 241 | $21.00 | $26.62 | $28.00 |
| 59 | Seeding (native hydraulic (212-00707) | ACRE | 4.02 | $2,000.00 | $4,235.00 | $2,000.00 |
| 60 | Seeding (wetland hydraulic (212-00710) | ACRE | 0.32 | $4,700.00 | $18,755 | $2,100.00 |
| 61 | Mulching (weed free (213-00003) | ACRE | 3.02 | $4,300.00 | $3,388.00 | $3,700.00 |
| 62 | Spray-on mulch blanket (213-00012) | ACRE | 1 | $6,500.00 | $9,317.00 | $10,000 |
| 63 | Mulch tackifier (213-00061) | LB | 182 | $6.00 | $6.05 | $6.00 |
| 64 | Live willow stakes (214-01013) | EACH | 784 | $8.50 | $26.62 | $28.00 |
| 65 | Wildlife biologist (240-00000) | HR | 40 | $325.00 | $363.00 | $410.00 |
| 66 | Aggregate base course (class 2 (304-02000) | TON | 879 | $70.00 | $66.71 | $85.00 |
| 67 | Aggregate base course (class 6 (304-06000) | TON | 678 | $80.00 | $60.66 | $310.00 |
| 68 | Hot mix asphalt (patching (asphalt (403-00720) | TON | 530 | $250.00 | $616.74 | $580.00 |
| 69 | Hot mix asphalt (patching (asphalt (403-00721) | SY | 863 | $200.00 | $330.52 | $480.00 |
| 70 | Pot mix asphalt (grading SX (100 (PG 64- (403-34851) | TON | 449 | $250.00 | $2.42 | $1.00 |
| 71 | Foint sealant (408-01100) | LF | 934 | $32.00 | $12.10 | $58.00 |
| 72 | Geotextile (drainage (class 2 (420-00113) | SY | 507 | $6.00 | $42.35 | $16.00 |
| 73 | Geogrid pavement reinforcement (420-00520) | SY | 1,469 | $15.00 | $5.72 | $5.00 |
| 74 | Steel sheet piling (type 1 (501-00000) | SF | 594 | $80.00 | $114.95 | $120.00 |
| 75 | Steel sheet piling cap (501-00210) | LF | 22 | $120.00 | $423.50 | $1,100.00 |
| 76 | Riprap (9 inch (506-00209) | CY | 17 | $275.00 | $151.25 | $590.00 |
| 77 | Riprap (18 inch (506-00218) | CY | 550 | $200.00 | $186.45 | $350.00 |
| 78 | In-channel boulder feature (boulder (506-00602) | EACH | 2 | $300.00 | $6,875.00 | $3,900.00 |
| 79 | Concrete slope and ditch paving (507-00000) | CY | 5 | $2,200.00 | $1,298.00 | $4,200.00 |
| 80 | Structural steel (509-00000) | LB | 328 | $62.00 | $10.34 | $260.00 |
| 81 | Concrete sealer (515-00400) | SY | 558 | $30.00 | $60.50 | $20.00 |
| 82 | Concrete class D (601-03000) | CY | 157.40 | $1,100.00 | $1,419.00 | $3,500.00 |
| 83 | Concrete class D (special (baffles (601-03027) | CY | 5 | $1,200.00 | $2,134.00 | $4,100.00 |
| 84 | Concrete class D (special (invert pave (601-03027) | CY | 84 | $1,200.00 | $2,134.00 | $3,600.00 |
| 85 | Reinforcing steel (epoxy coated (602-00020) | LB | 16,523 | $2.00 | $2.43 | $3.00 |
| 86 | Welded wire fabric (602-00210) | SY | 1,284 | $30.00 | $113.71 | $22.00 |
| 87 | Annular space grouting (603-00001) | CY | 75 | $400.00 | $869.00 | $1,500.00 |
| 88 | Culvert lining (48 inch (special (603-00049) | LF | 211 | $600.00 | $681.86 | $710.00 |
| 89 | Culver lining (48 inch (special (48 inch (603-00049) | LF | 88 | $600.00 | $505.71 | $810.00 |
| 90 | Inch reinforced concrete pipe (603-01420) | LF | 60 | $300.00 | $582.88 | $1,300.00 |
| 91 | 54 inch reinforced concrete pipe item 603- (603-01540) | LF | 80 | $500.00 | $671.99 | $1,300.00 |
| 92 | 60 inch reinforced concrete pipe (603-01600) | LF | 408 | $350.00 | $767.17 | $1,200.00 |
| 93 | 53X34 inch reinforced concrete pipe (603-02420) | LF | 184 | $360.00 | $936.27 | $1,200.00 |
| 94 | 68X43 inch reinforced concrete pipe (603-02540) | LF | 64 | $450.00 | $694.27 | $1,300.00 |
| 95 | 42 inch reinforced concrete end section (603-05042) | EACH | 2 | $4,280.00 | $4,345.00 | $5,600.00 |
| 96 | 54 inch reinforced concrete end section (603-05054) | EACH | 2 | $3,025.00 | $6,985.00 | $7,400.00 |
| 97 | 53X34 inch reinforced concrete end (603-05142) | EACH | 4 | $3,000.00 | $10,615 | $7,700.00 |
| 98 | 36 inch corrugated steel pipe (603-10360) | LF | 140 | $200.00 | $416.45 | $640.00 |
| 99 | 66 inch equivalent corrugated steel pipe (603-15066) | LF | 100 | $350.00 | $579.32 | $1,300.00 |
| 100 | 72 inch equivalent corrugated steel pipe (603-15072) | LF | 40 | $625.00 | $657.97 | $2,000.00 |
| 101 | 36 inch steel end section (603-30036) | EACH | 1 | $2,800.00 | $4,038.77 | $2,400.00 |
| 102 | 60 inch steel end section (603-30060) | EACH | 2 | $3,000.00 | $6,579.71 | $5,800.00 |
| 103 | 66 inch equivalent arch steel end section (603-31366) | EACH | 2 | $3,000.00 | $8,152.71 | $6,600.00 |
| 104 | 10X6 foot concrete box culvert (precast (603-71006) | LF | 56 | $3,000.00 | $1,918.66 | $3,900.00 |
| 105 | Guardrail type 3 (31 inch midwest guardrail (606-00302) | LF | 2,700 | $50.00 | $60.50 | $43.00 |
| 106 | End anchorage (nonflared (606-02003) | EACH | 3 | $4,500.00 | $6,050.00 | $5,100.00 |
| 107 | End anchorage (flared (606-02005) | EACH | 9 | $4,600.00 | $5,808.00 | $5,100.00 |
| 108 | Fence (plastic (607-11525) | LF | 200 | $13.00 | $6.05 | $6.00 |
| 109 | Fence (temporary (607-11580) | LF | 160 | $7.00 | $12.10 | $19.00 |
| 110 | Delineator (type (612-00001) | EACH | 9 | $50.00 | $181.50 | $40.00 |
| 111 | Delineator (type III (612-00003) | EACH | 37 | $80.00 | $181.50 | $47.00 |
| 112 | Flashing beacon (614-80000) | EACH | 16 | $4,000.00 | $786.50 | $650.00 |
| 113 | Field office (class 1 (620-00001) | EACH | 2 | $60,000 | $90,750 | $60,000 |
| 114 | Sanitary facility (620-00020) | EACH | 2 | $7,500.00 | $21,780 | $11,000 |
| 115 | Detour 141 MP 8.64 (621-00425) | LS | 1 | $25,460 | $18,663 | $166,000 |
| 116 | Detour 151 MP 2.72 (621-00425) | LS | 1 | $25,460 | $7,168.04 | $166,000 |
| 117 | Detour 151 MP 4.32 (621-00425) | LS | 1 | $25,460 | $7,168.04 | $100.00 |
| 118 | Detour 17 MP 15.02 (621-00425) | LS | 1 | $25,460 | $7,168.04 | $166,000 |
| 119 | Construction surveying (625-00000) | LS | 1 | $60,000 | $336,320 | $96,000 |
| 120 | Mobilization (626-00000) | LS | 1 | $1,200,000 | $946,861 | $983,000 |
| 121 | Public information services (tier IV (626-01104) | LS | 1 | $92.00 | $50,820 | $24,000 |
| 122 | Pavement marking paint (high build (627-00013) | GAL | 18 | $61.00 | $544.50 | $92.00 |
| 123 | Pavement marking paint (high (627-00016) | GAL | 11 | $175.00 | $605.00 | $79.00 |
| 124 | Flagging (630-00000) | HR | 8,500 | $48.00 | $76.44 | $55.00 |
| 125 | Traffic control inspection (630-00007) | DAY | 160 | $435.00 | $229.14 | $620.00 |
| 126 | Traffic control management (630-00012) | DAY | 350 | $1,650.00 | $2,292.09 | $1,300.00 |
| 127 | Construction traffic sign (panel size A (630-80341) | EACH | 56 | $55.00 | $113.44 | $210.00 |
| 128 | Construction traffic sign (panel size B (630-80342) | EACH | 24 | $67.00 | $128.56 | $210.00 |
| 129 | Construction traffic sign (special (630-80344) | SF | 128 | $38.00 | $18.26 | $41.00 |
| 130 | Portable message sign panel (630-80355) | EACH | 4 | $8,800.00 | $5,445.00 | $19,000 |
| 131 | Advance warning flashing or sequencing (630-80357) | EACH | 4 | $2,830.00 | $27,225 | $1,400.00 |
| 132 | Drum channelizing device (630-80360) | EACH | 430 | $35.00 | $66.55 | $2.50 |
| 133 | Drum channelizing device (with light (630-80364) | EACH | 200 | $45.00 | $96.80 | $55.00 |
| 134 | Concrete barrier (temporary (furnish and (630-80372) | LF | 400 | $110.00 | $102.85 | $820.00 |
| 135 | Portable rumble strips (temporary (630-80440) | EACH | 12 | $2,800.00 | $9,075.00 | $690.00 |
| 136 | Impact attenuator (temporary (630-85010) | EACH | 4 | $8,000.00 | $15,881 | $4,800.00 |
| 137 | Traffic signal (temporary (1 EA= 1 pair (630-86810) | EACH | 2 | $30,000 | $164,863 | $69,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.