CDOT contract C26564 bid tabulation

SH 50 CULVERT REPAIRS IN CANON CITY IN FREMONT COUNTY REGION 2. Let by Colorado DOT on September 11, 2025, Fremont, Region 2. 5 bids received; low bid $1,440,920 by Insituform Technologies, LLC, -3.9% against the engineer's estimate of $1,500,000.

Owner
Colorado DOT
Letting
11 SEP 2025
Pay items
31
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Insituform Technologies, LLC$1,440,920Low-4.0%
2American West Construction, LLC$1,478,874+3.0%-1.0%
3Inliner Solutions, LLC$1,518,883+5.0%+1.0%
4Siete, Inc.$1,618,263+12%+8.0%
5Subsurface, Inc$1,632,951+13%+9.0%
CDOT contract C26564: bids by rank

Engineer's estimate: $1,500,000.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Insituform Technologies, LLC2. American West Construction, LLC3. Inliner Solutions, LLC4. Siete, Inc.5. Subsurface, Inc
1Clearing and grubbing (201-00000)LS1$15,000$9,055.00$20,000$725.00$35,000$12,000
2Removal of debris (201-00005)LS1$15,000$5,020.00$20,000$2,175.00$45,000$5,000.00
3Clean culvert (202-04002)EACH34$1,000.00$2,725.00$5,700.00$3,615.00$3,500.00$2,500.00
4Aggregate bag (208-00035)LF40$14.93$17.00$18.00$14.00$14.00$25.00
5Construction mat (208-00082)SF100$45.41$25.00$46.00$1.00$200.00$100.00
6Removal and disposal of sediment (labor) (208-00103)HR4$72.76$235.00$92.00$216.00$88.00$90.00
7Sweeping (sediment removal) (208-00106)HR4$201.29$410.00$200.00$216.00$117.00$200.00
8Seeding (native) broadcast (212-00708)ACRE0.10$5,917.14$3,715.00$3,400.00$43,300$2,700.00$12,000
9Mulching (weed free hay) (213-00002)ACRE0.10$4,164.24$3,905.00$3,500.00$43,300$2,800.00$8,000.00
10Wildlife biologist (240-00000)HR8$135.09$140.00$240.00$289.00$325.00$250.00
11Culvert lining (18 inch) (603-00018)LF167$210.00$112.00$165.00$135.00$240.00$165.00
12Culvert lining (24 inch) (603-00026)LF4,321$183.69$175.00$164.00$175.00$175.00$231.00
13Culvert lining (30 inch) (603-00030)LF226$190.57$245.00$190.00$233.00$260.00$250.00
14Fence (plastic) (607-11525)LF200$4.64$4.00$6.00$14.00$5.00$15.00
15Field office (class 2) (620-00002)EACH1$22,258$9,230.00$34,000$20,000$50,000$18,000
16Sanitary facility (620-00020)EACH1$3,763.97$1,440.00$2,400.00$1,000.00$15,000$3,000.00
17Mobilization (626-00000)LS1$134,771$137,600$136,000$91,750$160,000$252,000
18Public information services (tier IV) (626-01104)LS1$4,500.00$7,665.00$6,200.00$2,175.00$5,500.00$6,000.00
19Flagging (630-00000)HR2,500$40.00$49.00$50.00$48.00$35.00$20.00
20Traffic control inspection (630-00007)DAY34$200.00$275.00$265.00$310.00$450.00$200.00
21Traffic control management (630-00012)DAY68$2,000.00$975.00$1,600.00$1,985.00$1,375.00$500.00
22Flashing beacon (solar) (630-80002)EACH4$1,631.28$2,785.00$430.00$505.00$1,000.00$1,575.00
23Barricade (type 3 M-A) (temporary) (630-80335)EACH4$194.35$210.00$215.00$253.00$400.00$299.25
24Construction traffic sign (panel size A) (630-80341)EACH23$51.00$85.00$45.00$50.00$60.00$48.30
25Construction traffic sign (panel size B) (630-80342)EACH12$60.33$95.00$55.00$65.00$72.00$51.45
26Construction traffic sign (panel size C) (630-80343)EACH18$78.05$140.00$70.00$80.00$78.00$54.60
27Construction information sign (630-80348)EACH8$120.32$560.00$70.00$80.00$85.00$204.75
28Vertical panel (630-80350)EACH36$52.43$49.00$37.00$43.00$40.00$48.30
29Portable message sign panel (630-80355)EACH2$5,103.09$8,225.00$7,000.00$8,300.00$6,000.00$7,875.00
30Traffic cone (630-80380)EACH50$10.30$15.00$16.00$18.00$11.00$46.20
31Mobile attenuator (630-85020)EACH4$30,657$25,095$3,000.00$34,750$22,000$7,035.00
CDOT contract C26564: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of September 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy