CDOT contract C26425 bid tabulation
I-70 DILLON TO EJMT MM 204 TO MM 214 A mandatory pre bid conference will be held on April 28th, beginning at 10:00 AM at the Mountain Residency, East Blue River Conference Room. Bids will be accepted only from pre- qualified bidders who attend the mandatory pre-bid conference. This will be a 2 seaso. Let by Colorado DOT on May 8, 2025, Summit, Region 3. 1 bid received; low bid $3,373,121 by American West Construction, LLC, -24% against the engineer's estimate of $4,414,920.
- Owner
- Colorado DOT
- Letting
- 08 MAY 2025
- Pay items
- 67
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | American West Construction, LLC | $3,373,121 | Low | -24% |
Engineer's estimate: $4,414,920.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. American West Construction, LLC |
|---|---|---|---|---|---|
| 1 | Removal of inlet (202-00019) | EACH | 4 | $3,000.00 | $1,900.00 |
| 2 | Removal of pipe (202-00035) | LF | 190 | $400.00 | $40.00 |
| 3 | Removal of curb (202-00201) | LF | 30 | $30.00 | $95.00 |
| 4 | Removal of gutter (202-00202) | LF | 140 | $120.00 | $43.00 |
| 5 | Removal of guardrail type 7 (202-01170) | LF | 85 | $150.00 | $120.00 |
| 6 | Clean culvert (202-04002) | EACH | 6 | $10,000 | $12,000 |
| 7 | Blading (203-01500) | HR | 40 | $150.00 | $235.00 |
| 8 | Dozing (203-01550) | HR | 40 | $200.00 | $285.00 |
| 9 | Hydraulic excavator (203-01565) | HR | 80 | $200.00 | $300.00 |
| 10 | Truck (203-01580) | HR | 40 | $150.00 | $110.00 |
| 11 | Combination loader (203-01594) | HR | 40 | $150.00 | $165.00 |
| 12 | Potholing (203-01597) | HR | 10 | $600.00 | $280.00 |
| 13 | Laborer (203-02330) | HR | 40 | $75.00 | $55.00 |
| 14 | Structure backfill (special) (206-00050) | CY | 86 | $300.00 | $1,500.00 |
| 15 | Erosion log type 1 (12 inch) (208-00002) | LF | 500 | $10.00 | $7.00 |
| 16 | Aggregate bag (208-00035) | LF | 500 | $15.00 | $11.00 |
| 17 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 1 | $2,000.00 | $4,500.00 |
| 18 | Removal and disposal of sediment (labor) (208-00103) | HR | 40 | $100.00 | $55.00 |
| 19 | Removal and disposal of sediment (equipment) (208-00105) | HR | 40 | $150.00 | $145.00 |
| 20 | Sweeping (sediment removal) (208-00106) | HR | 40 | $200.00 | $165.00 |
| 21 | Removal of trash (208-00107) | HR | 40 | $150.00 | $55.00 |
| 22 | Reset guardrail type 3 (210-01130) | LF | 225 | $150.00 | $340.00 |
| 23 | Reset guardrail type 7 (210-01170) | LF | 20 | $300.00 | $640.00 |
| 24 | Modify inlet (210-04020) | EACH | 16 | $12,000 | $11,000 |
| 25 | Biotic soil amendments (hydraulically applied) (212-00702) | LB | 33 | $20.00 | $2.00 |
| 26 | Seeding (native) hydraulic (212-00707) | ACRE | 0.50 | $1,000.00 | $4,500.00 |
| 27 | Spray-on mulch blanket (213-00012) | ACRE | 0.50 | $20,000 | $6,300.00 |
| 28 | Aggregate base course (class 6) (304-06007) | CY | 23 | $250.00 | $340.00 |
| 29 | Hot mix asphalt (patching) (asphalt) (403-00721) | SY | 29 | $150.00 | $880.00 |
| 30 | Riprap (18 inch) (506-00218) | CY | 162 | $500.00 | $350.00 |
| 31 | Cement grout (601-06300) | CF | 109 | $300.00 | $315.00 |
| 32 | Prepare culvert pipe (24 inch) (603-00024) | LF | 3,823 | $150.00 | $100.00 |
| 33 | Culvert lining (24 inch)(special) (603-00025) | LF | 3,823 | $400.00 | $225.00 |
| 34 | 24 inch corrugated steel pipe (603-10240) | LF | 125 | $300.00 | $310.00 |
| 35 | 24 inch steel end section (603-30024) | EACH | 1 | $2,000.00 | $1,600.00 |
| 36 | 24 inch plastic pipe (603-50024) | LF | 5 | $1,500.00 | $900.00 |
| 37 | Inlet type C (5 foot) (604-00305) | EACH | 3 | $10,000 | $10,000 |
| 38 | Inlet special (20 foot) (604-19020) | EACH | 3 | $30,000 | $18,500 |
| 39 | Manhole slab base (10 foot) (604-30010) | EACH | 4 | $15,000 | $10,000 |
| 40 | Manhole slab base (15 foot) (604-30015) | EACH | 2 | $20,000 | $29,000 |
| 41 | Guardrail type 7 (style CA) (606-00710) | LF | 60 | $450.00 | $700.00 |
| 42 | Guardrail type 9 (style CA) (606-00910) | LF | 200 | $450.00 | $675.00 |
| 43 | Gutter type 2 (10 foot) (609-24010) | LF | 140 | $200.00 | $175.00 |
| 44 | Curb type 6 (section M) (609-60011) | LF | 30 | $30.00 | $195.00 |
| 45 | Delineator (type III) (extra height) (612-00033) | EACH | 20 | $150.00 | $250.00 |
| 46 | Construction surveying (625-00000) | LS | 1 | $8,000.00 | $48,000 |
| 47 | Construction surveying (hourly) (625-00001) | HR | 40 | $200.00 | $700.00 |
| 48 | Mobilization (626-00000) | LS | 1 | $500,000 | $330,000 |
| 49 | Public information services (tier III) (626-01103) | LS | 1 | $15,000 | $11,500 |
| 50 | Traffic control inspection (630-00007) | DAY | 64 | $500.00 | $615.00 |
| 51 | Traffic control management (630-00012) | DAY | 151 | $2,500.00 | $1,700.00 |
| 52 | Flashing beacon (portable) (630-80001) | EACH | 4 | $2,000.00 | $1,800.00 |
| 53 | Barricade (type 3 M-A) (temporary) (630-80335) | EACH | 4 | $500.00 | $370.00 |
| 54 | Construction traffic sign (panel size A) (630-80341) | EACH | 22 | $130.00 | $25.00 |
| 55 | Construction traffic sign (panel size B) (630-80342) | EACH | 53 | $150.00 | $25.00 |
| 56 | Construction traffic sign (panel size C) (630-80343) | EACH | 40 | $180.00 | $25.00 |
| 57 | Construction traffic sign (special) (630-80344) | SF | 192 | $100.00 | $25.00 |
| 58 | Portable message sign panel (630-80355) | EACH | 2 | $15,000 | $15,000 |
| 59 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 2 | $6,000.00 | $4,900.00 |
| 60 | Drum channelizing device (630-80360) | EACH | 200 | $60.00 | $37.00 |
| 61 | Drum channelizing device (with light) (flashing) (630-80363) | EACH | 10 | $60.00 | $61.00 |
| 62 | Drum channelizing device (with light) (steady burn) (630-80364) | EACH | 10 | $60.00 | $61.00 |
| 63 | Portable traffic speed monitor (630-80367) | EACH | 2 | $12,000 | $4,900.00 |
| 64 | Barrier (temporary) (630-80370) | LF | 200 | $100.00 | $410.00 |
| 65 | Traffic cone (630-80380) | EACH | 200 | $20.00 | $1.50 |
| 66 | Impact attenuator (temporary) (630-85010) | EACH | 2 | $15,000 | $12,000 |
| 67 | Mobile attenuator (630-85020) | EACH | 1 | $115,000 | $74,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of May 8, 2025. Compiled by Mirage Metrics.