CDOT contract C26934combo bid tabulation
Bridge Repairs on east I-70 in Arapahoe County, near Deer Trail. Work includes repairs of bridge decks at four structures, including hydrodemolition, concrete shoulder repairs, approach slab repairs, polyester concrete overlay, and substructure repairs. A mandatory pre-bid meeting will be held virtu. Let by Colorado DOT on July 24, 2025, Arapahoe, Region 1. 4 bids received; low bid $7,235,023 by Structures, Inc., -0.8% against the engineer's estimate of $7,292,629.
- Owner
- Colorado DOT
- Letting
- 24 JUL 2025
- Pay items
- 67
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Structures, Inc. | $7,235,023 | Low | -1.0% |
| 2 | Abco Contracting, Inc. | $7,545,928 | +4.0% | +3.0% |
| 3 | Myers & Sons Construction, LLC | $8,474,743 | +17% | +16% |
| 4 | Lobato Construction, LLC | $12,000,000 | +66% | +65% |
Engineer's estimate: $7,292,629.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Structures, Inc. | 2. Abco Contracting, Inc. | 3. Myers & Sons Construction, LLC | 4. Lobato Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Removal of concrete pavement (202-00210) | SY | 6,494 | $38.83 | $33.92 | $40.00 | $27.00 | $38.00 |
| 2 | Removal of asphalt mat (planing) (special) (202-00246) | SY | 1,172 | $31.01 | $46.07 | $48.00 | $52.00 | $38.00 |
| 3 | Removal of pavement marking (202-00250) | SF | 16,914 | $1.86 | $1.05 | $1.15 | $3.00 | $1.00 |
| 4 | Removal of portions of present structure (class 1) (202-00450) | SY | 42 | $367.07 | $194.71 | $140.00 | $250.00 | $300.00 |
| 5 | Removal of portions of present structure (class 2) (202-00453) | SY | 102 | $566.92 | $461.00 | $275.00 | $375.00 | $500.00 |
| 6 | Removal of portions of present structure (hydrodemolition)(fast-track) 00 76 00 (202-00458) | SY | 4,438 | $265.00 | $273.02 | $300.00 | $252.00 | $500.00 |
| 7 | Removal of portions of present structure (class 3) (202-00460) | SY | 130 | $684.39 | $515.21 | $690.00 | $550.00 | $750.00 |
| 8 | Removal of expansion device (202-00504) | LF | 76 | $509.21 | $333.41 | $170.00 | $300.00 | $300.00 |
| 9 | Removal of portions of present structure (202-00505) | SF | 1,025 | $94.88 | $124.09 | $115.00 | $260.00 | $75.00 |
| 10 | Clean expansion joint (202-04050) | LF | 108 | $47.43 | $18.28 | $40.00 | $25.00 | $20.00 |
| 11 | Unclassified excavation (complete in place) (203-00010) | CY | 802 | $62.91 | $82.50 | $85.00 | $85.00 | $80.00 |
| 12 | Potholing (203-01597) | HR | 5 | $331.48 | $544.86 | $300.00 | $500.00 | $390.00 |
| 13 | Subgrade soil preparation (207-00704) | SY | 7,500 | $2.26 | $8.09 | $8.50 | $3.00 | $8.00 |
| 14 | Erosion log type 1 (20 inch) (208-00013) | LF | 2,444 | $13.95 | $9.36 | $9.00 | $13.00 | $8.00 |
| 15 | Silt fence (208-00020) | LF | 6,658 | $2.11 | $5.70 | $2.00 | $3.00 | $2.00 |
| 16 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 6 | $1,501.42 | $2,988.10 | $2,000.00 | $5,000.00 | $4,000.00 |
| 17 | Storm drain inlet protection (type I) (208-00051) | LF | 1 | $39.94 | $334.40 | $15.00 | $15.00 | $100.00 |
| 18 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 4 | $4,752.74 | $5,949.24 | $1,300.00 | $7,500.00 | $7,500.00 |
| 19 | Construction mat (208-00082) | SF | 29,957 | $9.41 | $2.09 | $10.00 | $7.50 | $25.00 |
| 20 | Sweeping (sediment removal) (208-00106) | HR | 240 | $198.20 | $114.70 | $180.00 | $200.00 | $200.00 |
| 21 | Erosion control management (208-00207) | DAY | 120 | $299.90 | $233.38 | $560.00 | $300.00 | $250.00 |
| 22 | Organic fertilizer (212-00700) | LB | 761 | $2.12 | $1.57 | $2.00 | $25.00 | $2.00 |
| 23 | Compost (mechanically applied) (212-00701) | CY | 175 | $52.83 | $68.91 | $122.00 | $200.00 | $110.00 |
| 24 | Mycorrhizae (212-00704) | LB | 23 | $24.05 | $24.76 | $22.00 | $50.00 | $20.00 |
| 25 | Seeding (native) drill (212-00706) | ACRE | 0.61 | $3,038.73 | $2,458.32 | $1,400.00 | $2,900.00 | $1,200.00 |
| 26 | Seeding (native) broadcast (212-00708) | ACRE | 0.89 | $2,822.86 | $2,465.73 | $1,800.00 | $2,900.00 | $1,500.00 |
| 27 | Seeding (wetland) broadcast (212-00711) | ACRE | 0.14 | $6,036.97 | $4,836.86 | $8,400.00 | $10,000 | $7,500.00 |
| 28 | Mulching (weed free) (213-00003) | ACRE | 1.64 | $2,200.58 | $2,500.67 | $1,200.00 | $8,000.00 | $1,000.00 |
| 29 | Mulch tackifier (213-00061) | LB | 163.50 | $7.19 | $3.23 | $8.00 | $15.00 | $7.00 |
| 30 | Wildlife biologist (240-00000) | HR | 120 | $165.66 | $167.20 | $180.00 | $160.00 | $160.00 |
| 31 | Removal of nests (240-00010) | HR | 120 | $181.52 | $248.03 | $250.00 | $145.00 | $150.00 |
| 32 | Emergency pothole repair (403-00800) | TON | 3 | $1,385.96 | $1,741.44 | $5,400.00 | $7,500.00 | $10,000 |
| 33 | Concrete pavement (11 inch) (412-01100) | SY | 7,500 | $105.04 | $112.75 | $133.00 | $125.00 | $145.00 |
| 34 | Bearing repair corbel (512-00120) | EACH | 40 | $5,622.58 | $6,125.70 | $8,800.00 | $9,500.00 | $7,500.00 |
| 35 | Bridge drain (special) (513-00690) | EACH | 24 | $3,849.32 | $535.84 | $340.00 | $750.00 | $1,000.00 |
| 36 | Bridge compression joint sealer (518-00000) | LF | 158 | $234.83 | $152.27 | $140.00 | $150.00 | $150.00 |
| 37 | Bridge expansion device (0-4 inch) (518-01004) | LF | 76 | $477.30 | $489.93 | $650.00 | $500.00 | $500.00 |
| 38 | Sawing and sealing bridge joint (518-03000) | LF | 342 | $37.50 | $37.04 | $29.00 | $43.19 | $30.00 |
| 39 | Place thin bonded overlay (polyester concrete) (519-03035) | SY | 5,594 | $77.49 | $59.60 | $65.00 | $50.00 | $55.00 |
| 40 | Furnish thin bonded overlay (polyester concrete) (519-03055) | CF | 3,965 | $168.32 | $168.11 | $112.00 | $150.00 | $120.00 |
| 41 | Concrete class D (bridge) (601-03040) | CY | 673 | $1,269.65 | $495.08 | $555.00 | $650.00 | $2,500.00 |
| 42 | Concrete (patching) (601-06102) | CF | 300 | $180.36 | $415.91 | $505.00 | $650.00 | $750.00 |
| 43 | Reinforcing steel (602-00000) | LB | 1,420 | $2.91 | $3.22 | $2.50 | $2.50 | $3.00 |
| 44 | Reinforcing steel (epoxy coated) (602-00020) | LB | 23,030 | $2.27 | $1.97 | $2.75 | $3.00 | $4.00 |
| 45 | Galvanic anodes, please reference previous code 601-51010 for historical pricing (602-51010) | EACH | 23,501 | $5.00 | $21.41 | $19.65 | $35.00 | $15.00 |
| 46 | Fence (plastic) (607-11525) | LF | 672 | $4.81 | $3.71 | $5.00 | $3.00 | $5.00 |
| 47 | Field office (class 2) (620-00002) | EACH | 1 | $22,366 | $87,935 | $90,000 | $150,000 | $100,000 |
| 48 | Sanitary facility (620-00020) | EACH | 2 | $2,314.66 | $5,203.00 | $4,500.00 | $10,000 | $25,000 |
| 49 | Mobilization (626-00000) | LS | 1 | $508,884 | $859,670 | $610,000 | $840,000 | $2,278,401 |
| 50 | Public information management (tier III) (626-01113) | DAY | 180 | $88.91 | $156.36 | $75.00 | $85.00 | $125.00 |
| 51 | Modified epoxy pavement marking (627-00008) | GAL | 549 | $236.95 | $161.98 | $175.00 | $325.00 | $175.00 |
| 52 | Preformed plastic pavement marking (type I)(inlaid) (627-01010) | SF | 1,410 | $28.43 | $26.65 | $29.00 | $28.00 | $26.00 |
| 53 | Preformed plastic pavement marking (contrast)(inlaid) (627-01011) | SF | 1,410 | $24.42 | $26.65 | $29.00 | $28.00 | $26.00 |
| 54 | Flagging (630-00000) | HR | 1,920 | $37.75 | $62.18 | $47.00 | $59.50 | $45.00 |
| 55 | Traffic control inspection (630-00007) | DAY | 70 | $165.58 | $313.50 | $198.00 | $500.00 | $325.00 |
| 56 | Traffic control management (630-00012) | DAY | 160 | $720.11 | $940.50 | $1,667.00 | $1,500.00 | $950.00 |
| 57 | Uniformed traffic control (special) (630-00019) | HR | 100 | $400.00 | $308.28 | $170.00 | $295.00 | $300.00 |
| 58 | Flashing beacon (portable) (630-80001) | EACH | 295 | $887.32 | $52.25 | $38.00 | $50.00 | $55.00 |
| 59 | Barricade (type 3 M-A) (temporary) (630-80335) | EACH | 12 | $128.60 | $308.28 | $85.00 | $295.00 | $300.00 |
| 60 | Construction traffic sign (panel size A) (630-80341) | EACH | 36 | $51.16 | $47.03 | $62.00 | $45.00 | $50.00 |
| 61 | Construction traffic sign (panel size B) (630-80342) | EACH | 64 | $74.27 | $156.75 | $74.00 | $150.00 | $150.00 |
| 62 | Portable message sign panel (630-80355) | EACH | 4 | $5,268.28 | $15,153 | $8,500.00 | $19,500 | $20,000 |
| 63 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 2 | $1,156.48 | $4,174.78 | $3,050.00 | $2,995.00 | $3,000.00 |
| 64 | Drum channelizing device (630-80360) | EACH | 320 | $35.26 | $47.03 | $50.00 | $45.00 | $45.00 |
| 65 | Barrier (temporary) (630-80370) | LF | 2,750 | $67.70 | $68.47 | $60.00 | $90.00 | $105.00 |
| 66 | Impact attenuator (temporary) (630-85010) | EACH | 4 | $4,938.02 | $5,650.50 | $11,000 | $10,000 | $10,500 |
| 67 | Mobile attenuator (630-85020) | EACH | 1 | $31,319 | $36,575 | $50,000 | $75,000 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of July 24, 2025. Compiled by Mirage Metrics.