CDOT contract C25575 bid tabulation
US 40 IN DEER TRAIL, PINE ST TO BURTON ST. Let by Colorado DOT on June 5, 2025, Arapahoe, Region 1. 5 bids received; low bid $672,753 by Myers & Sons Construction, LLC, +40% against the engineer's estimate of $480,000.
- Owner
- Colorado DOT
- Letting
- 05 JUN 2025
- Pay items
- 69
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Myers & Sons Construction, LLC | $672,753 | Low | +40% |
| 2 | Jalisco International, Inc. | $696,230 | +3.0% | +45% |
| 3 | Structures, Inc. | $720,968 | +7.0% | +50% |
| 4 | HCG Construction LLC | $749,999 | +11% | +56% |
| 5 | Abco Contracting, Inc. | $778,587 | +16% | +62% |
Engineer's estimate: $480,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Myers & Sons Construction, LLC | 2. Jalisco International, Inc. | 3. Structures, Inc. | 4. HCG Construction LLC | 5. Abco Contracting, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201-00000) | LS | 1 | $7,500.00 | $3,500.00 | $5,000.00 | $7,426.76 | $10,000 | $20,000 |
| 2 | Removal of structure (special) (202-00002) | EACH | 1 | $3,000.00 | $3,800.00 | $2,850.00 | $7,500.06 | $4,000.00 | $9,000.00 |
| 3 | Removal of sidewalk (202-00200) | SY | 26 | $60.00 | $20.00 | $17.00 | $26.61 | $50.00 | $55.00 |
| 4 | Removal of curb (202-00201) | LF | 20 | $33.12 | $20.00 | $20.00 | $22.65 | $20.00 | $49.00 |
| 5 | Removal of fence (202-01000) | LF | 431 | $7.69 | $2.00 | $3.00 | $5.94 | $6.00 | $3.00 |
| 6 | Unsuitable material (203-00050) | CY | 5 | $136.79 | $125.00 | $185.00 | $223.14 | $75.00 | $400.00 |
| 7 | Embankment material (complete in place) (203-00060) | CY | 81 | $100.00 | $35.00 | $150.00 | $130.95 | $100.00 | $250.00 |
| 8 | Proof rolling (203-01100) | HR | 10 | $144.35 | $150.00 | $140.00 | $162.21 | $200.00 | $300.00 |
| 9 | Blading (203-01500) | HR | 20 | $131.72 | $175.00 | $160.00 | $230.87 | $250.00 | $300.00 |
| 10 | Dozing (203-01550) | HR | 20 | $227.16 | $150.00 | $240.00 | $230.87 | $260.00 | $300.00 |
| 11 | Potholing (203-01597) | HR | 40 | $313.95 | $250.00 | $235.00 | $310.71 | $300.00 | $340.00 |
| 12 | Laborer (203-02330) | HR | 40 | $30.00 | $45.00 | $55.00 | $55.54 | $85.00 | $85.00 |
| 13 | Structure excavation (206-00000) | CY | 47 | $100.68 | $75.00 | $11.00 | $28.74 | $30.00 | $185.00 |
| 14 | Structure backfill (class 1) (206-00100) | CY | 55 | $165.06 | $75.00 | $100.00 | $182.49 | $135.00 | $250.00 |
| 15 | Structure backfill (class 2) (206-00200) | CY | 25 | $99.57 | $50.00 | $58.00 | $41.31 | $40.00 | $283.00 |
| 16 | Stockpile topsoil (207-00210) | CY | 18 | $57.95 | $10.00 | $22.00 | $19.34 | $15.00 | $140.00 |
| 17 | Topsoil (onsite) (207-00700) | CY | 18 | $85.00 | $12.00 | $35.00 | $19.34 | $15.00 | $140.00 |
| 18 | Erosion log type 1 (12 inch) (208-00002) | LF | 200 | $9.01 | $6.25 | $8.00 | $12.13 | $8.00 | $8.00 |
| 19 | Erosion log type 1 (20 inch) (208-00013) | LF | 100 | $10.86 | $8.33 | $10.00 | $15.06 | $12.00 | $3.00 |
| 20 | Silt fence (208-00020) | LF | 200 | $8.00 | $2.58 | $4.00 | $7.52 | $5.00 | $4.00 |
| 21 | Aggregate bag (208-00035) | LF | 40 | $16.72 | $8.39 | $12.00 | $15.70 | $15.00 | $10.00 |
| 22 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 1 | $2,281.31 | $1,000.00 | $920.00 | $2,380.52 | $3,500.00 | $2,000.00 |
| 23 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 3 | $3,200.00 | $1,500.00 | $6,700.00 | $6,934.72 | $6,000.00 | $2,500.00 |
| 24 | Removal and disposal of sediment (labor) (208-00103) | HR | 20 | $83.92 | $45.00 | $55.00 | $48.57 | $85.00 | $54.00 |
| 25 | Removal and disposal of sediment (equipment) (208-00105) | HR | 20 | $165.68 | $85.00 | $130.00 | $101.92 | $185.00 | $164.00 |
| 26 | Sweeping (sediment removal) (208-00106) | HR | 40 | $149.40 | $200.00 | $205.00 | $110.53 | $200.00 | $300.00 |
| 27 | Removal of trash (208-00107) | HR | 40 | $119.30 | $55.00 | $165.00 | $48.57 | $85.00 | $55.00 |
| 28 | Erosion control management (208-00207) | DAY | 12 | $485.93 | $100.00 | $485.00 | $670.36 | $400.00 | $710.00 |
| 29 | Reset pre-fabricated vehicle tracking pad (210-00075) | EACH | 3 | $500.00 | $500.00 | $500.00 | $775.18 | $250.00 | $690.00 |
| 30 | Soil conditioning (212-00032) | ACRE | 0.85 | $8,539.61 | $5,347.22 | $5,700.00 | $7,524.03 | $3,500.00 | $6,500.00 |
| 31 | Compost (mechanically applied) (212-00701) | CY | 56 | $121.65 | $70.63 | $76.00 | $99.38 | $140.00 | $85.00 |
| 32 | Mycorrhizae (212-00704) | LB | 7 | $23.86 | $43.11 | $47.00 | $60.66 | $40.00 | $52.00 |
| 33 | Seeding (native) hydraulic (212-00707) | ACRE | 0.85 | $2,743.89 | $2,188.66 | $2,400.00 | $3,079.65 | $3,480.00 | $2,700.00 |
| 34 | Mulching (weed free straw) (213-00004) | ACRE | 0.85 | $2,013.77 | $1,256.44 | $1,360.00 | $1,767.93 | $3,500.00 | $1,500.00 |
| 35 | Mulch tackifier (213-00061) | LB | 85 | $5.00 | $7.70 | $8.00 | $10.83 | $6.00 | $10.00 |
| 36 | Soil retention blanket (excelsior) (biodegradable class 1) (216-00211) | SY | 450 | $8.29 | $3.95 | $4.28 | $5.56 | $6.00 | $5.00 |
| 37 | Herbicide treatment (217-00020) | HR | 20 | $193.58 | $165.00 | $270.00 | $267.12 | $185.00 | $300.00 |
| 38 | Wildlife biologist (240-00000) | HR | 8 | $421.67 | $230.00 | $220.00 | $233.20 | $150.00 | $275.00 |
| 39 | Hot mix asphalt (patching) (asphalt) (403-00721) | SY | 3 | $150.26 | $950.00 | $400.00 | $795.00 | $400.00 | $655.00 |
| 40 | Pile tip (502-00460) | EACH | 4 | $254.10 | $776.00 | $825.00 | $536.75 | $500.00 | $1,075.00 |
| 41 | Complete joint penetration (CJP) splice (502-00500) | EACH | 4 | $1,004.36 | $1,695.00 | $1,710.00 | $1,708.45 | $3,000.00 | $2,170.00 |
| 42 | Dynamic pile test (502-02010) | EACH | 2 | $3,870.81 | $5,000.00 | $2,300.00 | $4,639.51 | $5,500.00 | $5,300.00 |
| 43 | Steel piling (HP 14X89) (502-11489) | LF | 181 | $80.00 | $204.87 | $215.00 | $161.64 | $195.00 | $255.00 |
| 44 | Pipe railing (514-00000) | LF | 30 | $139.55 | $600.00 | $460.00 | $422.40 | $400.00 | $445.00 |
| 45 | Pedestrian railing (steel) (514-00200) | LF | 114 | $200.00 | $600.00 | $425.00 | $481.71 | $400.00 | $450.00 |
| 46 | Bridge compression joint sealer (518-00000) | LF | 25 | $217.92 | $300.00 | $625.00 | $334.95 | $350.00 | $275.00 |
| 47 | Concrete class D (bridge) (601-03040) | CY | 43 | $850.00 | $1,100.00 | $1,335.00 | $1,561.54 | $1,700.00 | $1,475.00 |
| 48 | Structural concrete coating (anti-graffiti) (601-40302) | SF | 315 | $4.13 | $5.00 | $4.00 | $9.24 | $12.00 | $6.00 |
| 49 | Reinforcing steel (epoxy coated) (602-00020) | LB | 4,180 | $2.83 | $1.50 | $2.25 | $2.98 | $2.50 | $5.00 |
| 50 | Fence combination wire with metal posts (607-11200) | LF | 415 | $11.04 | $10.00 | $6.00 | $7.57 | $10.00 | $6.00 |
| 51 | Fence (plastic) (607-11525) | LF | 2,250 | $4.26 | $1.50 | $4.00 | $5.09 | $5.00 | $4.00 |
| 52 | Concrete sidewalk (6 inch) (608-00006) | SY | 95 | $128.89 | $84.13 | $90.00 | $133.16 | $100.00 | $140.00 |
| 53 | Concrete curb ramp (608-00010) | SY | 14 | $323.59 | $156.33 | $165.00 | $377.17 | $250.00 | $550.00 |
| 54 | Detectable warnings (608-00015) | SF | 15 | $145.68 | $67.81 | $70.00 | $63.32 | $60.00 | $65.00 |
| 55 | Curb and gutter type 2 (section II-M) (609-21021) | LF | 33 | $66.07 | $32.41 | $35.00 | $98.26 | $50.00 | $155.00 |
| 56 | Sign panel (class I) (614-00011) | SF | 4 | $46.33 | $40.00 | $70.00 | $76.20 | $50.00 | $30.00 |
| 57 | Steel signpost (U-2) (614-00200) | LF | 10 | $16.96 | $30.00 | $33.00 | $88.05 | $80.00 | $120.00 |
| 58 | Bollard (622-00270) | EACH | 2 | $2,000.00 | $500.00 | $1,900.00 | $622.21 | $1,000.00 | $1,740.00 |
| 59 | Detour drainage pipe (class 0) (624-20301) | LS | 1 | $10,000 | $2,500.00 | $12,600 | $4,025.06 | $23,500 | $15,500 |
| 60 | Construction surveying (625-00000) | LS | 1 | $5,000.00 | $8,000.00 | $12,500 | $29,700 | $30,000 | $18,000 |
| 61 | Mobilization (626-00000) | LS | 1 | $46,091 | $67,000 | $95,000 | $59,951 | $60,000 | $115,000 |
| 62 | Bridge girder and deck unit (100 feet to 105 feet) (628-00100) | EACH | 1 | $128,000 | $272,500 | $210,000 | $226,432 | $240,000 | $159,000 |
| 63 | Flagging (630-00000) | HR | 20 | $44.31 | $42.00 | $45.00 | $44.52 | $40.00 | $50.00 |
| 64 | Traffic control management (630-00012) | DAY | 5 | $538.12 | $1,250.00 | $1,480.00 | $1,325.00 | $1,000.00 | $1,525.00 |
| 65 | Barricade (type 3 M-A) (temporary) (630-80335) | EACH | 3 | $85.00 | $15.00 | $100.00 | $15.90 | $300.00 | $20.00 |
| 66 | Construction traffic sign (panel size A) (630-80341) | EACH | 14 | $47.47 | $20.00 | $105.00 | $21.20 | $125.00 | $25.00 |
| 67 | Vertical panel (plastic) (630-80351) | EACH | 5 | $27.99 | $15.00 | $30.00 | $15.90 | $50.00 | $20.00 |
| 68 | Drum channelizing device (630-80360) | EACH | 7 | $100.00 | $25.00 | $40.00 | $26.50 | $50.00 | $30.00 |
| 69 | Traffic cone (630-80380) | EACH | 20 | $10.40 | $5.00 | $10.00 | $5.30 | $10.00 | $7.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of June 5, 2025. Compiled by Mirage Metrics.