CDOT contract C25982 bid tabulation
Install fiber optic cable along SH-66 from I-25 to Lyons and Install cameras along US-36 from Lyons to Estes Park This project has an OPTIONAL pre-bid meeting on Thursday, June 5, 2025 beginning at 1030am via Google Meet. Let by Colorado DOT on June 26, 2025, Region HQ ITS in Boulder. 4 bids received; low bid $5,379,255 by Dillie and Kuhn, Inc, +19% against the engineer's estimate of $4,521,760.
- Owner
- Colorado DOT
- Letting
- 26 JUN 2025
- Pay items
- 67
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Dillie and Kuhn, Inc | $5,379,255 | Low | +19% |
| 2 | Morton Electric, Inc. | $5,573,359 | +4.0% | +23% |
| 3 | Goodland Construction, Inc. | $5,597,428 | +4.0% | +24% |
| 4 | Sturgeon Electric Company, Inc. | $6,079,059 | +13% | +34% |
Engineer's estimate: $4,521,760.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Dillie and Kuhn, Inc | 2. Morton Electric, Inc. | 3. Goodland Construction, Inc. | 4. Sturgeon Electric Company, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removal of fiber optic cable (202-00055) | LF | 415 | $2.21 | $2.00 | $1.38 | $2.23 | $1.50 |
| 2 | Removal of closed circuit camera (202-00720) | EACH | 1 | $315.02 | $900.00 | $2,340.00 | $650.00 | $255.00 |
| 3 | Removal of pull box (202-00827) | EACH | 1 | $257.04 | $500.00 | $1,170.00 | $555.00 | $825.00 |
| 4 | Potholing (203-01597) | HR | 300 | $310.00 | $210.00 | $350.00 | $277.00 | $425.00 |
| 5 | Erosion log type 1 (12 inch) (208-00002) | LF | 760 | $7.27 | $8.00 | $4.73 | $5.57 | $6.00 |
| 6 | Aggregate bag (208-00035) | LF | 1,400 | $10.86 | $8.50 | $5.28 | $7.78 | $7.00 |
| 7 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 4 | $1,367.92 | $1,100.00 | $2,005.00 | $2,223.00 | $2,400.00 |
| 8 | Storm drain inlet protection (type I) (208-00051) | LF | 100 | $16.52 | $8.50 | $6.38 | $28.90 | $10.00 |
| 9 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 2 | $4,642.52 | $5,000.00 | $14,080 | $6,434.00 | $2,500.00 |
| 10 | Removal and disposal of sediment (labor) (208-00103) | HR | 40 | $78.73 | $1.00 | $198.00 | $87.79 | $205.00 |
| 11 | Removal and disposal of sediment (equipment) (208-00105) | HR | 40 | $143.13 | $1.00 | $412.50 | $152.25 | $415.00 |
| 12 | Sweeping (sediment removal) (208-00106) | HR | 20 | $149.41 | $1.00 | $203.50 | $237.00 | $230.00 |
| 13 | Removal of trash (208-00107) | HR | 20 | $127.67 | $1.00 | $365.00 | $88.00 | $95.00 |
| 14 | Erosion control management (208-00207) | DAY | 100 | $536.62 | $1,100.00 | $350.35 | $433.00 | $375.00 |
| 15 | Reset dedicated short range communications(DSRC) (roadside unit) (210-00481) | EACH | 1 | $2,162.19 | $1,600.00 | $3,010.00 | $1,389.00 | $1,325.00 |
| 16 | Organic fertilizer (212-00700) | LB | 147 | $4.04 | $7.00 | $2.45 | $2.25 | $4.00 |
| 17 | Compost (mechanically applied) (212-00701) | CY | 32 | $111.90 | $85.00 | $68.23 | $87.00 | $73.00 |
| 18 | Mycorrhizae (212-00704) | LB | 29 | $26.51 | $70.00 | $22.80 | $17.00 | $29.00 |
| 19 | Seeding (native) drill (212-00706) | ACRE | 0.49 | $2,886.39 | $2,000.00 | $2,244.90 | $6,437.00 | $2,450.00 |
| 20 | Soil retention blanket (straw-coconut) (photodegradable class 1) (216-00101) | SY | 5,000 | $3.01 | $3.20 | $4.24 | $5.57 | $4.25 |
| 21 | Drilled shaft (24 inch) (503-00024) | LF | 24 | $582.61 | $1,200.00 | $750.00 | $500.00 | $740.00 |
| 22 | Fence (plastic) (607-11525) | LF | 100 | $6.19 | $8.00 | $4.13 | $8.90 | $9.25 |
| 23 | Location marker (fiber optic)(dome) (612-00260) | EACH | 70 | $154.14 | $150.00 | $172.34 | $356.00 | $165.00 |
| 24 | 2 inch electrical conduit (bored) (613-00206) | LF | 153,825 | $12.50 | $11.92 | $12.04 | $15.56 | $15.25 |
| 25 | 6 inch electrical conduit (613-00600) | LF | 2,495 | $25.49 | $96.41 | $25.00 | $105.56 | $115.00 |
| 26 | 2 inch electrical conduit (plastic) (613-01200) | LF | 120 | $29.87 | $30.00 | $100.00 | $30.00 | $24.00 |
| 27 | Type one pull box (613-07001) | EACH | 2 | $1,004.66 | $1,600.00 | $1,841.00 | $1,392.00 | $1,650.00 |
| 28 | Type three pull box (613-07003) | EACH | 1 | $1,444.85 | $1,750.00 | $2,347.00 | $1,832.00 | $2,050.00 |
| 29 | Type four pull box (613-07004) | EACH | 68 | $2,024.81 | $1,890.00 | $2,390.00 | $2,219.00 | $3,150.00 |
| 30 | Type five pull box (613-07005) | EACH | 2 | $2,479.12 | $3,200.00 | $3,162.00 | $3,500.00 | $4,750.00 |
| 31 | Proof conduit (613-07195) | LF | 200 | $5.84 | $2.00 | $5.00 | $5.56 | $4.00 |
| 32 | Troubleshooting (613-60700) | HR | 100 | $286.94 | $170.00 | $209.00 | $206.00 | $200.00 |
| 33 | Service meter cabinet (613-80130) | EACH | 1 | $5,441.89 | $15,000 | $13,660 | $13,612 | $8,800.00 |
| 34 | 1310NM SFP optic module (614-70024) | EACH | 95 | $615.78 | $290.00 | $714.63 | $268.00 | $2,100.00 |
| 35 | Optical attenuator (614-70030) | EACH | 95 | $187.05 | $120.00 | $16.50 | $34.50 | $75.00 |
| 36 | Communications cabinet (614-72830) | EACH | 1 | $13,359 | $28,000 | $25,000 | $23,054 | $20,000 |
| 37 | Communications cabinet (type 1) (614-72831) | EACH | 27 | $7,000.00 | $24,000 | $21,457 | $10,312 | $20,500 |
| 38 | Uninterrupted power supply (614-86800) | EACH | 1 | $7,259.40 | $21,000 | $19,066 | $19,843 | $18,500 |
| 39 | Fiber optic termination panel (6 fiber) (614-87006) | EACH | 27 | $802.02 | $1,000.00 | $429.62 | $706.00 | $575.00 |
| 40 | Fiber optic cable (single mode) (12 fiber) (614-87010) | LF | 6,910 | $5.09 | $3.80 | $3.73 | $11.15 | $3.50 |
| 41 | Fiber optic termination panel (12 fiber) (614-87012) | EACH | 7 | $1,077.04 | $1,070.00 | $2,386.00 | $1,320.00 | $1,050.00 |
| 42 | Fiber optic termination panel (96 fiber) (614-87096) | EACH | 1 | $5,615.57 | $3,800.00 | $5,080.00 | $6,859.00 | $4,075.00 |
| 43 | Closed circuit television (614-87320) | EACH | 29 | $5,646.57 | $6,000.00 | $8,048.00 | $5,939.00 | $5,700.00 |
| 44 | Closed circuit television camera (traffic surveillance) (614-87333) | EACH | 6 | $7,674.68 | $6,100.00 | $6,442.00 | $5,719.00 | $5,300.00 |
| 45 | Test fiber optic cable (614-87350) | LS | 1 | $15,000 | $10,000 | $25,350 | $13,889 | $15,150 |
| 46 | Breakaway tapered ITS pole steel (40 feet) (614-87402) | EACH | 2 | $11,224 | $8,300.00 | $7,042.00 | $7,072.00 | $5,500.00 |
| 47 | Fiber optic cable (single mode) (96 strands) (614-87496) | LF | 80,090 | $2.75 | $2.17 | $4.85 | $3.35 | $4.00 |
| 48 | Ethernet switch type I (614-87691) | EACH | 27 | $6,092.38 | $6,650.00 | $8,519.00 | $5,842.00 | $8,125.00 |
| 49 | Ethernet switch type II (614-87692) | EACH | 6 | $5,082.43 | $5,050.00 | $6,221.00 | $6,259.00 | $11,855 |
| 50 | Ethernet switch type III (614-87693) | EACH | 1 | $6,846.56 | $5,050.00 | $7,480.00 | $7,042.00 | $11,855 |
| 51 | Ethernet aggregation switch type II (614-87698) | EACH | 1 | $36,141 | $10,600 | $12,870 | $7,042.00 | $11,855 |
| 52 | Sanitary facility (620-00020) | EACH | 1 | $2,507.26 | $5,000.00 | $12,500 | $9,413.00 | $12,600 |
| 53 | Construction surveying (625-00000) | LS | 1 | $60,000 | $340,000 | $66,000 | $92,594 | $110,000 |
| 54 | Mobilization (626-00000) | LS | 1 | $450,000 | $361,200 | $852,000 | $350,922 | $305,000 |
| 55 | Public information management (tier III) (626-01113) | DAY | 300 | $75.84 | $92.00 | $88.00 | $98.00 | $100.00 |
| 56 | Flagging (630-00000) | HR | 400 | $35.03 | $50.50 | $46.20 | $52.25 | $40.00 |
| 57 | Traffic control inspection (630-00007) | DAY | 10 | $126.56 | $270.00 | $247.50 | $276.00 | $320.00 |
| 58 | Traffic control management (630-00012) | DAY | 365 | $900.00 | $1,500.00 | $835.62 | $1,587.00 | $1,300.00 |
| 59 | Barricade (type 3 M-A) (temporary) (630-80335) | EACH | 6 | $187.76 | $60.00 | $55.00 | $61.15 | $215.00 |
| 60 | Construction traffic sign (panel size A) (630-80341) | EACH | 24 | $50.74 | $54.00 | $49.00 | $56.00 | $110.00 |
| 61 | Construction traffic sign (panel size B) (630-80342) | EACH | 80 | $73.91 | $102.00 | $93.00 | $105.00 | $110.00 |
| 62 | Portable message sign panel (630-80355) | EACH | 2 | $5,118.41 | $9,500.00 | $9,350.00 | $10,379 | $10,425 |
| 63 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 2 | $1,154.04 | $3,000.00 | $2,750.00 | $3,054.00 | $6,385.00 |
| 64 | Traffic cone (630-80380) | EACH | 300 | $8.61 | $18.00 | $16.50 | $18.90 | $10.00 |
| 65 | Stackable vertical panels (630-80393) | EACH | 200 | $29.14 | $54.00 | $49.50 | $56.00 | $54.00 |
| 66 | Mobile attenuator (630-85020) | EACH | 2 | $31,046 | $31,000 | $30,800 | $34,189 | $75,000 |
| 67 | Night work lighting (632-00000) | LS | 1 | $70,000 | $2,000.00 | $17,720 | $98,902 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of June 26, 2025. Compiled by Mirage Metrics.