CDOT contract C25564 bid tabulation

Three timber structures throughout Region 5 will be rehabilitated by installing HSS members adjacent to existing timber stringers. The three timber structures are the following: 1. L-06-G, US 550 MP 98.3 2. K-11-F, US 50 MP 189.7 3. O-13-Q, SH 15 MP 30.0. Let by Colorado DOT on May 1, 2025, Conejos, Ouray, and Saguache, Region 5. 4 bids received; low bid $963,303 by Structures, Inc., -11% against the engineer's estimate of $1,083,765.

Owner
Colorado DOT
Letting
01 MAY 2025
Pay items
53
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Structures, Inc.$963,303Low-11%
2Abco Contracting, Inc.$1,046,632+9.0%-3.0%
3Myers & Sons Construction, LLC$1,103,655+15%+2.0%
4Meridian Engineering Co. dba Meridian Contracting, Inc.$1,194,089+24%+10%
CDOT contract C25564: bids by rank

Engineer's estimate: $1,083,765.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Structures, Inc.2. Abco Contracting, Inc.3. Myers & Sons Construction, LLC4. Meridian Engineering Co. dba Meridian Contracting, Inc.
1Removal of asphalt mat (202-00220)SY161$50.00$72.00$315.00$190.00$90.00
2Removal of portions of present structure (202-00500)EACH9$200.00$341.00$2,000.00$950.00$200.00
3Unclassified excavation (203-00000)CY144$100.00$111.00$190.00$95.00$90.00
4Combination loader (203-01594)HR30$200.00$267.00$300.00$145.00$110.00
5Potholing (203-01597)HR30$400.00$492.00$450.00$550.00$350.00
6Topsoil (onsite) (207-00700)CY650$30.00$34.00$50.00$32.00$45.00
7Topsoil (wetland) (207-00703)CY22.50$175.00$43.00$320.00$80.00$85.00
8Erosion log type 1 (12 inch) (208-00002)LF1,300$7.00$10.50$8.00$6.56$15.00
9Silt fence (208-00020)LF400$3.50$4.00$4.00$3.08$10.00
10Aggregate bag (208-00035)LF30$11.00$19.00$18.00$13.79$25.00
11Pre-fabricated vehicle tracking pad (208-00075)EACH1$5,000.00$8,864.00$9,000.00$5,000.00$30,000
12Construction mat (208-00082)SF64$50.00$86.00$170.00$145.00$40.00
13Removal and disposal of sediment (labor) (208-00103)HR15$70.00$60.00$55.00$85.00$100.00
14Removal and disposal of sediment (equipment) (208-00105)HR15$150.00$143.00$110.00$120.00$300.00
15Sweeping (sediment removal) (208-00106)HR15$150.00$154.00$305.00$200.00$120.00
16Water control (208-00400)LS1$150,000$22,602$29,500$50,000$159,056
17Reset fence (210-01000)LF150$5.00$14.50$18.00$18.00$22.00
18Seeding (wetlands) (212-00028)ACRE0.03$2,000.00$48,500$17,500$16,000$14,000
19Organic fertilizer (212-00700)LB235$2.00$3.20$4.00$3.00$4.25
20Biotic soil amendments (hydraulically applied) (212-00702)LB2,737$2.50$2.65$2.00$1.50$2.00
21Mycorrhizae (212-00704)LB47$25.00$11.00$28.00$23.00$32.00
22Seeding (native) hydraulic (212-00707)ACRE0.78$3,000.00$1,692.00$3,500.00$1,900.00$2,600.00
23Seeding (wetland) hydraulic (212-00710)ACRE0.03$2,000.00$51,940$20,000$14,500$13,000
24Mulching (weed free) (213-00003)ACRE0.78$3,500.00$2,756.00$4,500.00$5,000.00$3,800.00
25Mulch tackifier (213-00061)LB79$5.50$3.20$17.00$14.00$20.00
26Wildlife biologist (240-00000)HR40$200.00$265.00$230.00$250.00$200.00
27Removal of nests (240-00010)HR20$220.00$58.00$230.00$116.00$200.00
28Aggregate base course (class 2) (304-02000)TON96$90.00$103.00$145.00$180.00$90.00
29Aggregate base course (class 6) (304-06000)TON48$170.00$113.00$145.00$290.00$110.00
30Hot mix asphalt (patching) (asphalt) (403-00720)TON53$500.00$894.00$1,215.00$986.00$1,100.00
31Emulsified asphalt (slow-setting) (411-10255)GAL24$5.00$8.50$180.00$143.00$140.00
32Geogrid pavement reinforcement (420-00520)SY161$45.00$9.50$15.00$19.00$8.00
33Structural steel (galvanized) (509-00001)LB34,460$12.00$7.70$5.75$13.75$10.00
34Fence (temporary) (607-11580)LF150$5.00$9.00$12.00$12.00$14.00
35Barricade (type 3 M-A) (614-80321)EACH2$500.00$530.00$485.00$400.00$750.00
36Sanitary facility (620-00020)EACH1$4,000.00$2,358.00$1,300.00$6,000.00$8,000.00
37Mobilization (626-00000)LS1$130,000$303,950$282,000$110,000$130,000
38Public information services (tier IV) (626-01104)LS1$4,800.00$4,134.00$6,000.00$9,250.00$15,000
39Pavement marking paint (high build) (627-00013)GAL9$100.00$59.00$68.00$460.00$650.00
40Flagging (630-00000)HR600$45.00$37.00$34.00$25.00$40.00
41Traffic control inspection (630-00007)DAY20$500.00$212.00$610.00$500.00$800.00
42Traffic control management (630-00012)DAY48$1,500.00$742.00$1,465.00$1,500.00$2,300.00
43Construction traffic sign (panel size A) (630-80341)EACH2$100.00$53.00$61.00$50.00$120.00
44Construction traffic sign (panel size B) (630-80342)EACH41$110.00$212.00$49.00$40.00$150.00
45Vertical panel (630-80350)EACH50$40.00$37.00$49.00$40.00$50.00
46Portable message sign panel (630-80355)EACH2$12,000$4,505.00$7,325.00$6,000.00$10,000
47Drum channelizing device (630-80360)EACH50$75.00$53.00$18.00$15.00$60.00
48Drum channelizing device (with light) (steady burn) (630-80364)EACH8$70.00$80.00$25.00$20.00$70.00
49Barrier (temporary) (630-80370)LF150$100.00$96.00$185.00$300.00$175.00
50Traffic cone (630-80380)EACH25$15.00$5.50$18.00$15.00$15.00
51Portable rumble strips (temporary) (630-80440)EACH6$1,500.00$2,417.00$975.00$800.00$2,200.00
52Impact attenuator (temporary) (630-85010)EACH2$3,600.00$7,008.00$7,935.00$6,500.00$7,000.00
53Traffic signal (temporary) (630-86810)EACH1$35,000$28,463$30,500$26,000$45,000
CDOT contract C25564: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of May 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy