CDOT contract C27031 bid tabulation
I-70 EISENHOWER-JOHNSON MEMORIAL TUNNEL, RIGHT LANE OVERLAY AND STRIPING, MM 213.5 TO MM 215.7. Let by Colorado DOT on July 24, 2025, Clear Creek and Summit, Region 1. 1 bid received; low bid $2,769,130 by Brannan Sand and Gravel, LLC, +73% against the engineer's estimate of $1,600,000.
- Owner
- Colorado DOT
- Letting
- 24 JUL 2025
- Pay items
- 35
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Brannan Sand and Gravel, LLC | $2,769,130 | Low | +73% |
Engineer's estimate: $1,600,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Brannan Sand and Gravel, LLC |
|---|---|---|---|---|---|
| 1 | Removal of asphalt mat (planing) (202-00240) | SY | 39,877 | $3.50 | $8.75 |
| 2 | Removal of pavement marking (202-00250) | SF | 9,858 | $3.50 | $1.55 |
| 3 | Potholing (203-01597) | HR | 40 | $275.00 | $475.00 |
| 4 | Laborer (203-02330) | HR | 40 | $71.70 | $100.00 |
| 5 | Aggregate bag (208-00035) | LF | 476 | $13.10 | $2.00 |
| 6 | Rigid inlet protection device (208-00055) | EACH | 110 | $408.52 | $450.00 |
| 7 | Removal and disposal of sediment (labor) (208-00103) | HR | 20 | $67.00 | $100.00 |
| 8 | Removal and disposal of sediment (equipment) (208-00105) | HR | 20 | $130.00 | $200.00 |
| 9 | Sweeping (sediment removal) (208-00106) | HR | 20 | $160.00 | $400.00 |
| 10 | Removal of trash (208-00107) | HR | 10 | $92.00 | $100.00 |
| 11 | Erosion control management (208-00207) | DAY | 10 | $500.00 | $950.00 |
| 12 | Adjust manhole (210-04010) | EACH | 70 | $1,000.00 | $1,275.00 |
| 13 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 44 | $380.00 | $650.00 |
| 14 | Stone matrix asphalt (fibers)(asphalt) (403-09221) | TON | 5,379 | $150.00 | $212.00 |
| 15 | Emulsified asphalt (slow-setting) (411-10255) | GAL | 4,202 | $7.30 | $4.50 |
| 16 | Loop detector wire (614-72875) | LF | 1,456 | $13.00 | $42.00 |
| 17 | Sanitary facility (620-00020) | EACH | 2 | $3,800.00 | $3,000.00 |
| 18 | Construction surveying (625-00000) | LS | 1 | $10,000 | $75,000 |
| 19 | Mobilization (626-00000) | LS | 1 | $142,285 | $565,000 |
| 20 | Public information management (tier III) (626-01113) | DAY | 45 | $120.00 | $135.00 |
| 21 | Modified epoxy pavement marking (627-00008) | GAL | 240 | $230.00 | $250.00 |
| 22 | Preformed plastic pavement marking (type I)(inlaid) (627-01010) | SF | 3,129 | $21.00 | $42.00 |
| 23 | Flagging (630-00000) | HR | 150 | $33.00 | $52.50 |
| 24 | Traffic control inspection (630-00007) | DAY | 20 | $290.00 | $375.00 |
| 25 | Traffic control management (630-00012) | DAY | 25 | $1,200.00 | $1,450.00 |
| 26 | Flashing beacon (portable) (630-80001) | EACH | 6 | $1,800.00 | $12.00 |
| 27 | Barricade (type 3 M-C) (temporary) (630-80337) | EACH | 3 | $315.00 | $40.00 |
| 28 | Construction traffic sign (panel size A) (630-80341) | EACH | 8 | $62.00 | $45.00 |
| 29 | Construction traffic sign (panel size B) (630-80342) | EACH | 22 | $84.00 | $60.00 |
| 30 | Portable message sign panel (630-80355) | EACH | 2 | $6,600.00 | $7,500.00 |
| 31 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 1 | $1,900.00 | $3,000.00 |
| 32 | Drum channelizing device (630-80360) | EACH | 165 | $38.00 | $25.00 |
| 33 | Traffic cone (630-80380) | EACH | 50 | $25.00 | $12.00 |
| 34 | Mobile attenuator (630-85041) | DAY | 20 | $800.00 | $1,200.00 |
| 35 | Night work lighting (632-00000) | LS | 1 | $25,000 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of July 24, 2025. Compiled by Mirage Metrics.