CDOT contract C26196 bid tabulation
WADSWORTH BLVD & EVANS AVE Installation of new traffic signal and curb ramps at the intersection of Wadsworth Blvd & Evans Ave. One dual mast arm, and two single mast arms. New pedestrian crossing infrastructure for the north and east legs of the intersection. Median work on Wadsworth Blvd to channe. Let by Colorado DOT on July 17, 2025, Jefferson, Region 1. 4 bids received; low bid $655,850 by Lighthouse Transportation Group, LLC, -8.3% against the engineer's estimate of $715,000.
- Owner
- Colorado DOT
- Letting
- 17 JUL 2025
- Pay items
- 75
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lighthouse Transportation Group, LLC | $655,850 | Low | -8.0% |
| 2 | Sturgeon Electric Company, Inc. | $667,631 | +2.0% | -7.0% |
| 3 | Morton Electric, Inc. | $708,679 | +8.0% | -1.0% |
| 4 | Adiona Transportation Solutions LLC | $789,494 | +20% | +10% |
Engineer's estimate: $715,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Lighthouse Transportation Group, LLC | 2. Sturgeon Electric Company, Inc. | 3. Morton Electric, Inc. | 4. Adiona Transportation Solutions LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201-00000) | LS | 1 | $19,278 | $3,955.00 | $1,650.00 | $8,040.00 | $3,992.00 |
| 2 | Removal of concrete median cover material (202-00190) | SY | 7 | $50.00 | $45.00 | $73.00 | $44.00 | $56.00 |
| 3 | Removal of sidewalk (202-00200) | SY | 69 | $51.53 | $35.00 | $44.00 | $32.00 | $45.00 |
| 4 | Removal of curb and gutter (202-00203) | LF | 130 | $32.40 | $15.00 | $18.00 | $15.00 | $17.00 |
| 5 | Removal of concrete curb ramp (202-00206) | SY | 27 | $58.66 | $36.00 | $44.00 | $35.50 | $45.00 |
| 6 | Removal of asphalt mat (202-00220) | SY | 104 | $62.70 | $50.00 | $44.00 | $50.00 | $45.00 |
| 7 | Removal of pavement marking (202-00250) | SF | 92 | $7.29 | $6.00 | $9.00 | $5.50 | $6.00 |
| 8 | Removal of light standard (202-00700) | EACH | 1 | $1,041.13 | $1,525.00 | $1,850.00 | $856.00 | $2,188.00 |
| 9 | Potholing (203-01597) | HR | 40 | $317.03 | $335.00 | $575.00 | $328.00 | $405.00 |
| 10 | Concrete washout structure (208-00045) | EACH | 1 | $2,202.98 | $1,700.00 | $3,500.00 | $5,140.00 | $3,360.00 |
| 11 | Storm drain inlet protection (type II) (208-00054) | EACH | 3 | $288.06 | $200.00 | $150.00 | $200.00 | $651.00 |
| 12 | Removal and disposal of sediment (labor) (208-00103) | HR | 8 | $86.31 | $85.00 | $130.00 | $136.00 | $179.00 |
| 13 | Removal and disposal of sediment (equipment) (208-00105) | HR | 8 | $165.73 | $145.00 | $175.00 | $152.00 | $295.00 |
| 14 | Sweeping (sediment removal) (208-00106) | HR | 8 | $149.43 | $170.00 | $220.00 | $152.00 | $295.00 |
| 15 | Erosion control management (208-00207) | DAY | 8 | $620.98 | $540.00 | $260.00 | $1,011.00 | $730.00 |
| 16 | Seeding (native) broadcast (212-00708) | ACRE | 0.10 | $7,438.35 | $5,480.00 | $11,200 | $7,700.00 | $10,756 |
| 17 | Landscape restoration (212-01200) | LS | 1 | $5,000.00 | $6,950.00 | $9,900.00 | $7,040.00 | $10,080 |
| 18 | Reconditioning (306-01000) | SY | 277 | $11.39 | $20.00 | $28.00 | $4.00 | $28.00 |
| 19 | Hot mix asphalt (patching) (asphalt) (403-00721) | SY | 54 | $235.00 | $215.00 | $325.00 | $204.00 | $336.00 |
| 20 | Concrete pavement (10 inch) (412-01000) | SY | 57 | $172.66 | $235.00 | $120.00 | $218.00 | $123.00 |
| 21 | Drilled shaft (36 inch) (503-00036) | LF | 13 | $1,000.00 | $825.00 | $800.00 | $807.00 | $939.00 |
| 22 | Drilled shaft (42 inch) (503-00042) | LF | 17 | $1,200.00 | $835.00 | $915.00 | $927.00 | $1,018.00 |
| 23 | Drilled shaft (54 inch) (503-00054) | LF | 21 | $1,400.00 | $875.00 | $1,200.00 | $1,090.00 | $1,288.00 |
| 24 | Concrete sidewalk (6 inch) (608-00006) | SY | 102 | $120.00 | $140.00 | $100.00 | $139.00 | $98.00 |
| 25 | Concrete curb ramp (608-00010) | SY | 14 | $291.81 | $375.00 | $180.00 | $369.00 | $180.00 |
| 26 | Curb and gutter type 2 (section I-B) (609-21010) | LF | 30 | $68.16 | $55.00 | $68.00 | $52.00 | $64.00 |
| 27 | Curb and gutter type 2 (section II-B) (609-21020) | LF | 99 | $62.19 | $55.00 | $66.00 | $52.00 | $67.00 |
| 28 | Median cover material (patterned concrete) (610-00020) | SF | 35 | $45.84 | $95.00 | $39.00 | $94.00 | $34.00 |
| 29 | 2 inch electrical conduit (613-00200) | LF | 222 | $36.49 | $25.00 | $23.00 | $24.50 | $27.00 |
| 30 | 2 inch electrical conduit (bored) (613-00206) | LF | 586 | $37.28 | $25.00 | $28.00 | $24.50 | $28.00 |
| 31 | 3 inch electrical conduit (613-00300) | LF | 175 | $32.80 | $25.00 | $24.00 | $27.60 | $37.00 |
| 32 | 3 inch electrical conduit (bored) (613-00306) | LF | 415 | $39.56 | $25.00 | $32.00 | $27.90 | $36.00 |
| 33 | Type three pull box (613-07003) | EACH | 2 | $1,347.67 | $1,820.00 | $1,900.00 | $1,418.00 | $1,931.00 |
| 34 | Type four pull box (613-07004) | EACH | 1 | $2,024.81 | $2,525.00 | $2,600.00 | $2,100.00 | $3,229.00 |
| 35 | Wiring (613-10000) | LS | 1 | $20,000 | $26,825 | $16,000 | $23,660 | $30,665 |
| 36 | Luminaire (LED) (special) (613-13000) | EACH | 4 | $1,096.71 | $800.00 | $930.00 | $1,150.00 | $1,402.00 |
| 37 | Sign panel (class I) (614-00011) | SF | 41 | $33.75 | $35.00 | $68.00 | $27.50 | $41.00 |
| 38 | Sign panel (class II) (614-00012) | SF | 36 | $42.62 | $42.00 | $90.00 | $40.70 | $61.00 |
| 39 | Sign panel (class I) (install only) (614-00025) | SF | 9 | $24.20 | $25.00 | $57.00 | $16.50 | $31.00 |
| 40 | Steel sign support (2-inch round)(post) (614-01512) | LF | 20 | $26.35 | $50.00 | $45.00 | $38.50 | $70.00 |
| 41 | Steel sign support (2-inch round)(socket) (614-01522) | EACH | 2 | $233.76 | $185.00 | $170.00 | $203.50 | $172.00 |
| 42 | Steel sign support (2-1/2 inch round SCH 80) (post) (614-01585) | LF | 12 | $30.55 | $120.00 | $50.00 | $55.00 | $58.00 |
| 43 | Steel sign support (2-1/2 inch round SCH 80)(slipbase) (614-01588) | EACH | 1 | $534.74 | $400.00 | $350.00 | $242.00 | $349.00 |
| 44 | Pedestrian signal face (16) (countdown) (614-70150) | EACH | 4 | $691.77 | $775.00 | $1,020.00 | $690.00 | $926.00 |
| 45 | Accessible pedestrian signal (614-70200) | EACH | 1 | $2,376.82 | $8,050.00 | $8,000.00 | $8,217.00 | $10,245 |
| 46 | Traffic signal face (12-12-12) (614-70336) | EACH | 15 | $1,300.00 | $1,315.00 | $1,800.00 | $982.00 | $1,645.00 |
| 47 | Traffic signal controller cabinet (614-72855) | EACH | 1 | $35,000 | $31,695 | $43,000 | $33,978 | $38,575 |
| 48 | Fire preemption unit and timer (614-72866) | EACH | 1 | $4,800.00 | $9,850.00 | $9,500.00 | $9,652.00 | $13,065 |
| 49 | Intersection detection system (camera) (614-72886) | EACH | 1 | $25,000 | $25,995 | $27,750 | $27,378 | $33,885 |
| 50 | Traffic signal-light pole steel (2 mast arm) (614-81020) | EACH | 1 | $40,000 | $59,860 | $62,000 | $63,010 | $64,016 |
| 51 | Traffic signal-light pole steel (1-30 foot mast arm) (614-81130) | EACH | 1 | $25,000 | $22,485 | $21,000 | $21,798 | $24,003 |
| 52 | Traffic signal-light pole steel (1-50 foot mast arm) (614-81150) | EACH | 1 | $30,000 | $26,960 | $25,000 | $25,439 | $28,785 |
| 53 | Traffic signal pedestal pole steel (614-84000) | EACH | 3 | $5,000.00 | $5,500.00 | $4,350.00 | $2,704.00 | $3,846.00 |
| 54 | Uninterrupted power supply (614-86800) | EACH | 1 | $9,119.13 | $18,100 | $14,000 | $11,300 | $13,258 |
| 55 | Closed circuit television camera (traffic surveillance) (614-87333) | EACH | 1 | $7,581.88 | $5,650.00 | $6,400.00 | $6,139.00 | $7,204.00 |
| 56 | Ethernet switch (614-87690) | EACH | 1 | $5,464.11 | $7,260.00 | $4,500.00 | $8,990.00 | $10,976 |
| 57 | Sanitary facility (620-00020) | EACH | 2 | $2,285.61 | $1,000.00 | $1,220.00 | $1,250.00 | $2,293.00 |
| 58 | Construction surveying (625-00000) | LS | 1 | $12,000 | $6,000.00 | $5,800.00 | $5,698.00 | $19,600 |
| 59 | Mobilization (626-00000) | LS | 1 | $48,499 | $52,322 | $34,600 | $106,715 | $82,857 |
| 60 | Public information services (tier IV) (626-01104) | LS | 1 | $5,000.00 | $4,550.00 | $5,400.00 | $4,950.00 | $6,036.00 |
| 61 | Modified epoxy pavement marking (627-00008) | GAL | 4 | $1,040.54 | $615.00 | $820.00 | $600.00 | $605.00 |
| 62 | Thermoplastic pavement marking (word- symbol) (627-30205) | SF | 138 | $27.45 | $35.00 | $20.00 | $32.00 | $32.00 |
| 63 | Thermoplastic pavement marking (xwalk- stopline) (627-30210) | SF | 689 | $20.73 | $18.00 | $16.50 | $17.00 | $17.00 |
| 64 | Flagging (630-00000) | HR | 60 | $30.00 | $39.00 | $38.00 | $38.50 | $40.00 |
| 65 | Uniformed traffic control (630-00003) | HR | 40 | $164.55 | $227.00 | $220.00 | $242.00 | $224.00 |
| 66 | Traffic control inspection (630-00007) | DAY | 8 | $350.00 | $247.00 | $250.00 | $253.00 | $247.00 |
| 67 | Traffic control management (630-00012) | DAY | 30 | $1,200.00 | $1,226.00 | $1,500.00 | $1,220.00 | $1,232.00 |
| 68 | Construction traffic sign (panel size A) (630-80341) | EACH | 8 | $28.00 | $50.00 | $49.00 | $50.00 | $51.00 |
| 69 | Construction traffic sign (panel size C) (630-80343) | EACH | 4 | $45.00 | $51.00 | $49.00 | $49.50 | $51.00 |
| 70 | Vertical panel (630-80350) | EACH | 50 | $35.55 | $40.00 | $38.00 | $38.50 | $40.00 |
| 71 | Portable message sign panel (630-80355) | EACH | 2 | $20,000 | $3,336.00 | $3,250.00 | $3,300.00 | $3,360.00 |
| 72 | Drum channelizing device (630-80360) | EACH | 100 | $35.54 | $42.00 | $38.00 | $38.50 | $40.00 |
| 73 | Traffic cone (630-80380) | EACH | 100 | $10.35 | $11.00 | $11.00 | $11.00 | $12.00 |
| 74 | Mobile attenuator (630-85041) | DAY | 30 | $912.91 | $548.00 | $560.00 | $550.00 | $583.00 |
| 75 | Night work lighting (632-00000) | LS | 1 | $12,000 | $5,950.00 | $7,900.00 | $12,040 | $22,767 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of July 17, 2025. Compiled by Mirage Metrics.