CDOT contract C25012 bid tabulation
This project will replace the traffic signal at the CO-13 (Yampa Ave.) & 9th St in Craig, CO as well as replace the conduit and signal cabinet at the US-40 (4th St.) & Ranney St. signal in Craig, CO. CO13 MM 90.2, US40Z MM 0.65, MOFFAT COUNTY. Let by Colorado DOT on January 30, 2025, Moffat, Region 3. 3 bids received; low bid $1,280,705 by Sturgeon Electric Company, Inc., -17% against the engineer's estimate of $1,541,792.
- Owner
- Colorado DOT
- Letting
- 30 JAN 2025
- Pay items
- 81
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sturgeon Electric Company, Inc. | $1,280,705 | Low | -17% |
| 2 | Morton Electric, Inc. | $1,385,962 | +8.0% | -10% |
| 3 | Advanced Electrical Contracting, Inc. | $1,471,426 | +15% | -5.0% |
Engineer's estimate: $1,541,792.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Sturgeon Electric Company, Inc. | 2. Morton Electric, Inc. | 3. Advanced Electrical Contracting, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201-00000) | LS | 1 | $25,000 | $4,300.00 | $4,015.00 | $13,500 |
| 2 | Removal of sidewalk (202-00200) | SY | 22 | $50.00 | $110.00 | $121.00 | $47.25 |
| 3 | Removal of curb (202-00201) | LF | 2 | $8.00 | $140.00 | $128.00 | $81.00 |
| 4 | Removal of curb and gutter (202-00203) | LF | 18 | $25.00 | $150.00 | $149.00 | $20.25 |
| 5 | Removal of concrete curb ramp (202-00206) | SY | 15 | $50.00 | $130.00 | $116.00 | $47.25 |
| 6 | Removal of asphalt mat (202-00220) | SY | 45 | $80.00 | $65.00 | $61.00 | $10.13 |
| 7 | Removal of pavement marking (202-00250) | SF | 2,400 | $2.50 | $4.00 | $4.00 | $4.73 |
| 8 | Removal of luminaire (202-00750) | EACH | 1 | $250.00 | $325.00 | $425.00 | $202.50 |
| 9 | Removal of pull box (202-00827) | EACH | 10 | $1,000.00 | $350.00 | $790.00 | $202.50 |
| 10 | Removal of traffic signal equipment (202-00828) | LS | 1 | $30,000 | $29,000 | $13,900 | $29,700 |
| 11 | Blading (203-01500) | HR | 20 | $270.00 | $250.00 | $275.00 | $168.75 |
| 12 | Potholing (203-01597) | HR | 20 | $400.00 | $700.00 | $396.00 | $337.50 |
| 13 | Topsoil (onsite) (207-00700) | CY | 34 | $120.00 | $120.00 | $102.00 | $47.25 |
| 14 | Aggregate bag (208-00035) | LF | 160 | $25.00 | $9.00 | $20.00 | $8.22 |
| 15 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 1 | $5,000.00 | $3,000.00 | $3,300.00 | $2,205.23 |
| 16 | Storm drain inlet protection (type I) (84 inch) (208-00053) | EACH | 1 | $300.00 | $500.00 | $479.00 | $123.04 |
| 17 | Storm drain inlet protection (type II) (208-00054) | EACH | 2 | $310.00 | $450.00 | $446.00 | $98.78 |
| 18 | Storm drain inlet protection (type III) (208-00056) | EACH | 1 | $320.00 | $600.00 | $595.00 | $143.81 |
| 19 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 1 | $4,000.00 | $800.00 | $22,000 | $16,663 |
| 20 | Removal and disposal of sediment (labor) (208-00103) | HR | 8 | $80.00 | $350.00 | $391.00 | $67.50 |
| 21 | Sweeping (sediment removal) (208-00106) | HR | 10 | $250.00 | $300.00 | $275.00 | $168.75 |
| 22 | Removal of trash (208-00107) | HR | 4 | $90.00 | $200.00 | $182.00 | $67.50 |
| 23 | Reset radio communication antenna (210-00479) | EACH | 1 | $2,000.00 | $1,900.00 | $1,975.00 | $607.50 |
| 24 | Sod (212-00050) | SF | 825 | $3.00 | $18.00 | $20.00 | $2.57 |
| 25 | Organic fertilizer (212-00700) | LB | 12 | $8.00 | $80.00 | $83.00 | $14.70 |
| 26 | Biotic soil amendments (hydraulically applied) (212-00702) | LB | 140 | $4.00 | $7.00 | $7.00 | $49.71 |
| 27 | Humate (212-00703) | LB | 6 | $15.00 | $95.00 | $86.00 | $24.99 |
| 28 | Mycorrhizae (212-00704) | LB | 1.60 | $50.00 | $500.00 | $523.00 | $16.17 |
| 29 | Seeding (native) broadcast (212-00708) | ACRE | 0.02 | $15,000 | $73,000 | $70,400 | $615.95 |
| 30 | Spray-on mulch blanket (213-00012) | ACRE | 0.02 | $15,000 | $700,000 | $830,500 | $49.32 |
| 31 | Herbicide treatment (217-00020) | HR | 8 | $300.00 | $200.00 | $209.00 | $147.02 |
| 32 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 9 | $800.00 | $900.00 | $879.00 | $646.87 |
| 33 | Drilled shaft (18 inch) (503-00018) | LF | 45 | $500.00 | $400.00 | $400.00 | $675.00 |
| 34 | Drilled shaft (36 inch) (503-00036) | LF | 38 | $900.00 | $900.00 | $850.00 | $945.00 |
| 35 | Drilled shaft (42 inch) (503-00042) | LF | 19 | $1,000.00 | $900.00 | $975.00 | $1,147.50 |
| 36 | Fence (plastic) (607-11525) | LF | 180 | $15.00 | $10.00 | $11.00 | $5.93 |
| 37 | Concrete sidewalk (6 inch) (608-00006) | SY | 20 | $200.00 | $350.00 | $396.00 | $220.52 |
| 38 | Concrete curb ramp (608-00010) | SY | 34 | $350.00 | $450.00 | $512.00 | $271.98 |
| 39 | Curb and gutter type 2 (section II-B) (609-21020) | LF | 37 | $45.00 | $180.00 | $182.00 | $190.64 |
| 40 | Median cover material (patterned concrete) (610-00020) | SF | 91 | $20.00 | $53.00 | $50.00 | $51.46 |
| 41 | 3 inch electrical conduit (bored) (613-00306) | LF | 2,450 | $40.00 | $36.00 | $26.00 | $69.92 |
| 42 | 2 inch electrical conduit (plastic) (613-01200) | LF | 300 | $30.00 | $27.00 | $25.00 | $20.44 |
| 43 | 3 inch electrical conduit (plastic) (613-01300) | LF | 310 | $40.00 | $28.00 | $26.00 | $28.86 |
| 44 | Type four pull box (613-07004) | EACH | 6 | $3,500.00 | $3,000.00 | $1,720.00 | $2,115.55 |
| 45 | Type five pull box (613-07005) | EACH | 2 | $4,500.00 | $3,800.00 | $1,950.00 | $3,695.96 |
| 46 | Wiring (613-10000) | LS | 1 | $50,000 | $76,600 | $24,500 | $67,953 |
| 47 | Luminaire (LED) (special) (613-13000) | EACH | 3 | $1,500.00 | $960.00 | $1,450.00 | $700.63 |
| 48 | Secondary service pedestal (613-50150) | EACH | 2 | $15,000 | $13,200 | $10,500 | $14,506 |
| 49 | Sign panel (class I) (614-00011) | SF | 30 | $30.00 | $82.00 | $37.00 | $53.68 |
| 50 | Sign panel (class II) (614-00012) | SF | 12 | $45.00 | $90.00 | $50.00 | $86.79 |
| 51 | Sign panel (class I) (install only) (614-00026) | EACH | 7 | $500.00 | $280.00 | $170.00 | $97.20 |
| 52 | Pedestrian signal face (16) (countdown) (614-70150) | EACH | 14 | $900.00 | $1,100.00 | $680.00 | $731.78 |
| 53 | Traffic signal face (12-12-12) (614-70336) | EACH | 15 | $1,300.00 | $1,600.00 | $850.00 | $1,010.70 |
| 54 | Traffic signal controller cabinet (614-72855) | EACH | 2 | $62,000 | $50,500 | $43,739 | $43,889 |
| 55 | Pedestrian push button (614-72860) | EACH | 14 | $800.00 | $950.00 | $650.00 | $622.84 |
| 56 | Pedestrian push button post assembly (614-72863) | EACH | 4 | $2,000.00 | $3,200.00 | $976.00 | $2,308.14 |
| 57 | Intersection detection system (camera) (614-72886) | EACH | 2 | $25,000 | $25,000 | $35,350 | $40,392 |
| 58 | Traffic signal-light pole steel (2 mast arm) (614-81020) | EACH | 1 | $65,000 | $38,500 | $36,850 | $45,795 |
| 59 | Traffic signal-light pole steel (1-30 foot mast arm) (614-81130) | EACH | 1 | $28,000 | $21,500 | $20,975 | $24,515 |
| 60 | Traffic signal-light pole steel (1-50 foot mast arm) (614-81150) | EACH | 1 | $35,000 | $25,000 | $23,769 | $27,492 |
| 61 | Traffic signal pedestal pole steel (614-84000) | EACH | 9 | $4,500.00 | $3,700.00 | $3,500.00 | $2,916.02 |
| 62 | Sanitary facility (620-00020) | EACH | 1 | $4,000.00 | $1,500.00 | $2,700.00 | $5,145.53 |
| 63 | Construction surveying (625-00000) | LS | 1 | $150,000 | $46,000 | $19,206 | $33,680 |
| 64 | Mobilization (626-00000) | LS | 1 | $225,000 | $123,000 | $318,100 | $348,608 |
| 65 | Public information services (tier III) (626-01103) | LS | 1 | $90.00 | $4,500.00 | $4,800.00 | $114.75 |
| 66 | Modified epoxy pavement marking (627-00008) | GAL | 5 | $1,000.00 | $320.00 | $275.00 | $1,837.69 |
| 67 | Preformed thermoplastic pavement marking (word-symbol) (special) (627-30407) | SF | 65 | $30.00 | $26.00 | $21.50 | $28.67 |
| 68 | Preformed thermoplastic pavement marking (xwalk-stop line) (special) (627-30411) | SF | 1,864 | $15.00 | $19.00 | $19.50 | $25.73 |
| 69 | Flagging (630-00000) | HR | 2,000 | $50.00 | $50.00 | $58.00 | $21.00 |
| 70 | Traffic control inspection (630-00007) | DAY | 24 | $150.00 | $750.00 | $385.00 | $351.98 |
| 71 | Traffic control management (630-00012) | DAY | 60 | $2,000.00 | $1,400.00 | $1,870.00 | $1,296.75 |
| 72 | Flashing beacon (portable) (630-80001) | EACH | 4 | $1,600.00 | $1,650.00 | $715.00 | $550.00 |
| 73 | Barricade (type 3 M-B) (temporary) (630-80336) | EACH | 4 | $500.00 | $12.00 | $165.00 | $80.00 |
| 74 | Pedestrian barricade (ADA) (630-80340) | LF | 100 | $100.00 | $37.00 | $33.00 | $15.00 |
| 75 | Construction traffic sign (panel size A) (630-80341) | EACH | 87 | $140.00 | $2.00 | $77.00 | $22.23 |
| 76 | Construction traffic sign (panel size B) (630-80342) | EACH | 22 | $150.00 | $2.00 | $77.00 | $22.23 |
| 77 | Vertical panel (630-80350) | EACH | 50 | $70.00 | $22.00 | $44.00 | $14.82 |
| 78 | Portable message sign panel (630-80355) | EACH | 4 | $150.00 | $6,500.00 | $6,600.00 | $3,630.00 |
| 79 | Advance warning flashing or sequencing arrow panel (B type) (630-80357) | EACH | 2 | $1,700.00 | $2,600.00 | $3,300.00 | $1,624.00 |
| 80 | Drum channelizing device (630-80360) | EACH | 50 | $50.00 | $23.00 | $44.00 | $14.82 |
| 81 | Traffic cone (630-80380) | EACH | 100 | $20.00 | $2.00 | $25.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of January 30, 2025. Compiled by Mirage Metrics.