CDOT letting results, October 24, 2024
9 contracts let by Colorado DOT on October 24, 2024, $52,332,557 in low bids, a median of 3 bidders per contract. On the 9 with an engineer's estimate, the low bid came in under it 7 times; median low bid -12% against the estimate.
- Owner
- Colorado DOT
- Contracts
- 9
- Low bids, total
- $52,332,557
- Data through
- 10 SEP 2026
Contracts let that day
| Contract | Project | Region | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| C24809 | I25 AT MP 165.4 - NEW BRIDGE CONSTRUCTION OF WILDLIFE OVERPASS INCLUDING BRIDGE CONSTRUCTION, RETAINING WALLS, TEMPORARY EROSION CONTROL, SEEDING AND MULCHING, | Region 1 | 8 | Kraemer North America, LLC | $14,831,421 | $15,307,895 | +3.0% | -37% | CDOT |
| C24971 | US 160 TREASURE FALLS TO WC SURFACE TREATMENT PROJECT INCLUDES: ASPHALT LEVELING AND OVERLAY GUARDRAIL REPLACEMENT SIGN PANEL REPLACEMENT REPAIR TO INLET OF ONE | Region 5 | 2 | Kilgore Companies, LLC dba Elam Construction | $12,661,160 | $14,304,074 | +13% | -5.0% | CDOT |
| C22992 | SH 92 Mill and fill existing lanes, shoulder widening, waterline relocation, and pipe ramming two culverts. A mandatory pre bid conference will be held in perso | Region 3 | 1 | Oldcastle SW Group, Inc. | $12,263,411 | +8.0% | CDOT | ||
| C25942 | This is an HMA overlay project North and South of Akron along SH 63 MM 25.1 to 34.3 with 3.5 " of HMA. Within the town of Akron a 2.5" HMA mill and fill will be | Region 4 | 3 | McAtee Construction Co. | $7,902,793 | $8,123,625 | +3.0% | -12% | CDOT |
| C26270R | This project is located in Region 2 in various counties. Project work consists of removal and replacement of signs along US 24 between Divide and Chipita Park a | Region 2 | 5 | Roadsafe Traffic Systems, Inc | $1,848,479 | $1,903,212 | +3.0% | -3.0% | CDOT |
| C23021 | This project is located on State Highway 53 between 58th Ave and 70th Ave. The work involves the replacement of traffic signals at 62nd and 70th, the modificati | Region 1 | 5 | Adiona Transportation Solutions LLC | $1,259,445 | $1,305,392 | +4.0% | -37% | CDOT |
| C26617 | The project is located in Region 2 in Pueblo and El Paso counties. Project work consists of removal and replacing of overhead sign structures on I-25 at mile ma | Region 2 | 2 | Workzone Traffic Control, LLC | $637,923 | $643,227 | +1.0% | +5.0% | CDOT |
| C26357 | R2 VARIOUS HIGHWAYS AND COUNTIES | Region 2 | 3 | Roadsafe Traffic Systems, Inc | $497,230 | $545,081 | +10% | -29% | CDOT |
| C25613 | CO 402 & S CR 5 (MM 140.0-141.1) | Region 4 | 5 | Adiona Transportation Solutions LLC | $430,696 | $470,445 | +9.0% | -14% | CDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than CDOT received, the others did not match their published totals and are left out.