CDOT contract C26757 bid tabulation
This project will remove and replace ground mounted signs on US-36 from Estes Park to Boulder. Let by Colorado DOT on June 5, 2025, Boulder and Larimer, Region 4. 4 bids received; low bid $928,778 by Workzone Traffic Control, LLC, +6.0% against the engineer's estimate of $876,184.
- Owner
- Colorado DOT
- Letting
- 05 JUN 2025
- Pay items
- 24
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Workzone Traffic Control, LLC | $928,778 | Low | +6.0% |
| 2 | Roadsafe Traffic Systems, Inc | $1,093,529 | +18% | +25% |
| 3 | Barricade Holdings LLC | $1,217,000 | +31% | +39% |
| 4 | Lighthouse Transportation Group, LLC | $1,781,703 | +92% | +103% |
Engineer's estimate: $876,184.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Workzone Traffic Control, LLC | 2. Roadsafe Traffic Systems, Inc | 3. Barricade Holdings LLC | 4. Lighthouse Transportation Group, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Removal of ground sign (202-00810) | EACH | 665 | $95.00 | $40.00 | $140.00 | $150.00 | $250.00 |
| 2 | Removal of sign panel (202-00821) | EACH | 70 | $83.00 | $45.00 | $115.00 | $36.00 | $125.00 |
| 3 | Aggregate bag (208-00035) | LF | 160 | $9.00 | $15.00 | $3.50 | $11.00 | $20.00 |
| 4 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 1 | $2,763.00 | $1,200.00 | $2,500.00 | $1,000.00 | $2,792.00 |
| 5 | Reset sign panel (210-00815) | EACH | 17 | $257.00 | $215.00 | $200.00 | $77.00 | $225.00 |
| 6 | Sign panel (class I) (614-00011) | SF | 2,793 | $27.55 | $33.50 | $33.00 | $21.00 | $40.00 |
| 7 | Sign panel (class II) (614-00012) | SF | 3,773 | $28.30 | $38.25 | $40.00 | $45.00 | $48.00 |
| 8 | Sign panel (class III) (614-00013) | SF | 196 | $37.76 | $48.00 | $65.00 | $55.00 | $55.00 |
| 9 | Steel sign support (2-inch round)(post and socket) (614-01503) | EACH | 282 | $350.00 | $310.00 | $375.00 | $550.00 | $661.00 |
| 10 | Steel sign support (2-1/2 inch round NP- 40)(post & slipbase) (614-01573) | EACH | 421 | $538.91 | $485.00 | $575.00 | $800.00 | $1,281.00 |
| 11 | Steel sign support (2-1/2 in round SCH 80) (post & slipbase) (614-01583) | EACH | 7 | $655.00 | $585.00 | $660.00 | $1,365.00 | $1,376.00 |
| 12 | Paint ground sign (614-10035) | EACH | 3 | $320.01 | $315.00 | $275.00 | $3,000.00 | $350.00 |
| 13 | Mobilization (626-00000) | LS | 1 | $64,000 | $47,750 | $100,000 | $150,000 | $286,826 |
| 14 | Public information services (tier IV) (626-01104) | LS | 1 | $18,000 | $8,300.00 | $10,000 | $13,446 | $6,769.00 |
| 15 | Flagging (630-00000) | HR | 500 | $38.08 | $51.50 | $36.50 | $49.00 | $44.00 |
| 16 | Traffic control inspection (630-00007) | DAY | 8 | $121.09 | $415.90 | $250.00 | $350.00 | $250.00 |
| 17 | Traffic control management (630-00012) | DAY | 70 | $573.47 | $1,525.00 | $1,725.00 | $1,400.00 | $875.00 |
| 18 | Construction traffic sign (panel size A) (630-80341) | EACH | 16 | $47.55 | $85.00 | $20.00 | $12.00 | $75.00 |
| 19 | Construction traffic sign (panel size B) (630-80342) | EACH | 50 | $62.55 | $85.00 | $20.00 | $22.00 | $88.00 |
| 20 | Vertical panel (630-80350) | EACH | 50 | $33.15 | $85.00 | $20.00 | $5.00 | $44.00 |
| 21 | Portable message sign panel (630-80355) | EACH | 2 | $5,116.03 | $3,800.00 | $2,500.00 | $2,000.00 | $3,750.00 |
| 22 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 4 | $1,154.04 | $1,500.00 | $500.00 | $1,300.00 | $1,563.00 |
| 23 | Traffic cone (630-80380) | EACH | 500 | $7.00 | $25.00 | $5.00 | $3.00 | $13.00 |
| 24 | Mobile attenuator (630-85041) | DAY | 120 | $919.44 | $1,000.00 | $950.00 | $500.00 | $1,250.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of June 5, 2025. Compiled by Mirage Metrics.