FDOT contract T7571 bid tabulation

SR 93 (I-275) NB/SB SKYWAY REST AREA. Let by Florida DOT on January 29, 2025, Pinellas, District 7. 3 bids received; low bid $714,390 by American Lighting and Signalization, LLC..

Owner
Florida DOT
Letting
29 JAN 2025
Pay items
33
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1American Lighting and Signalization, LLC.$714,390Low
2Highway Safety Devices, Inc.$716,4880.0%
3New Era Electric Inc$858,246+20%
FDOT contract T7571: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. American Lighting and Signalization, LLC.2. Highway Safety Devices, Inc.3. New Era Electric Inc
0005Mobilization (0101-1)LS1$101,678$68,150$80,000
0010Maintenance of traffic (0102-1)DA1$81,830$25,500$110,000
0015Clearing & grubbing (0110-1-1)ACRE1$19,867$5,750.00$87,803
0020Fencing, type B, 0.0-5.0', standard features (0550-10210)LF92$166.00$250.00$54.65
0025Initial contingency amount, DO not bid (0999-25)LS1$35,000$35,000$35,000
0030Multi-column ground sign assembly, F&I ground mount, 1-200.0 SF (0700-2116)EACH2$29,308$17,700$18,338
0035Embedded dynamic message furnish & install- with UPS, full color, 12-20 SF (0700-7132)EACH2$29,113$28,500$46,139
0040Itsfm subsurface documentation- project length (0611-1-1)MI0.28$3,863.00$6,800.00$4,500.00
0045Itsfm location documentation- ITS site (0611-2-2)EACH7$1,749.00$3,100.00$2,263.95
0050Conduit, furnish & install, open trench (0630-2-11)LF917$25.00$35.00$35.00
0055Conduit, furnish & install, directional bore (0630-2-12)LF970$31.00$57.00$45.00
0060Conduit, furnish & install, aboveground (0630-2-14)LF130$30.00$44.50$45.90
0065Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF2,004$4.00$7.30$4.75
0070Fiber optic connection, install, splice (0633-2-31)EACH12$50.00$87.50$62.65
0075Fiber optic connection, install, termination (0633-2-32)EACH36$83.00$145.00$101.25
0080Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14)EACH3$94.00$165.00$147.20
0085Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH3$1,253.00$2,200.00$1,830.00
0090Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51)EACH3$1,021.00$1,800.00$1,550.00
0095Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH11$2,225.00$2,250.00$1,691.95
0100Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH5$3,667.00$4,100.00$3,110.20
0105Electrical power service, adjust/modify (0639-1500)AS3$600.00$965.00$1,695.60
0110Electrical service wire, & install (0639-2-1)LF1,111$7.00$22.50$13.45
0115Electrical service disconnect, F&I, pole mount (0639-3-11)EACH3$3,131.00$3,300.00$3,383.40
0120Electrical power service- transformer, F&I, 5-10 kva, phase, copper windings (0639-6121)EACH3$1,559.00$3,750.00$2,900.00
0125Prestressed concrete pole, type P-II service pole (0641-2-12)EACH6$2,360.00$3,600.00$3,311.20
0130Concrete CCTV pole, furnish & install with lowering device, (0641-3163)EACH1$54,586$74,400$55,000
0135ITS cabinet, furnish & install, pole mount with sunshield, 24" W X 46" H X 22" D (0676-2122)EACH3$6,411.00$12,500$9,710.00
0140Small equipment enclosure, furnish and install, less than 10"W X 13"H X 11" D (0676-3-10)EACH4$2,238.00$3,550.00$2,236.95
0145ITS CCTV camera, F&I, dome PTZ enclosure - pressurized, IP, definition (0682-1113)EACH1$8,272.00$7,750.00$7,707.30
0150ITS CCTV camera, F&I, stationary, IP, high definition (0682-1153)EACH8$5,850.00$2,700.00$6,209.00
0155Managed field ethernet switch, furnish & install (0684-1-1)EACH3$6,617.00$6,800.00$7,500.00
0160Uninterruptible power supply, furnish and install, line interactive (0685-1-11)EACH3$4,462.00$6,800.00$6,074.85
0165Remote power management rpmu, furnish and install (0685-2-1)EACH3$1,087.00$1,450.00$1,344.25
FDOT contract T7571: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy