American Lighting and Signalization, LLC.: FDOT bid record
American Lighting and Signalization, LLC. submitted 146 bids on Florida DOT contracts in the data, from 31 JAN 2018 to 28 OCT 2026, and was the low bidder on 30 of them (21%). When it was not low, its total sat a median +20% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $45,879,243
- Latest bid
- 28 OCT 2026
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2018 | 36 | 6 | 17% |
| 2019 | 28 | 3 | 11% |
| 2020 | 21 | 0 | 0% |
| 2021 | 25 | 7 | 28% |
| 2022 | 10 | 6 | 60% |
| 2023 | 6 | 1 | 17% |
| 2024 | 3 | 1 | 33% |
| 2025 | 5 | 3 | 60% |
| 2026 | 12 | 3 | 25% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 2 | 35 | 13 | 37% |
| District 5 | 32 | 3 | 9% |
| District 1 | 29 | 6 | 21% |
| District 4 | 23 | 2 | 9% |
| District 7 | 20 | 5 | 25% |
| StateWide | 6 | 1 | 17% |
| District 3 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Channelizing device- types I, II, VP, drum, or LCD | 0102-74-1 | ED | 121 | 52 (43%) | $0.15 | $0.13 |
| Pull & splice box, F&I, 13" X 24" cover size | 0635-2-11 | EACH | 142 | 47 (33%) | $800.00 | $1,150.00 |
| Work zone sign | 0102-60 | ED | 122 | 37 (30%) | $0.30 | $0.25 |
| Prestressed concrete pole, type P-II service pole | 0641-2-12 | EACH | 72 | 36 (50%) | $1,200.50 | $2,200.00 |
| Inlet protection system | 0104-18 | EACH | 87 | 35 (40%) | $100.00 | $150.00 |
| Lighting conductors, F&I, insulated, no.8 - 6 | 0715-1-12 | LF | 63 | 35 (56%) | $1.25 | $2.40 |
| Conduit, furnish & install, directional bore | 0630-2-12 | LF | 146 | 31 (21%) | $25.00 | $30.82 |
| Conduit, furnish & install, open trench | 0630-2-11 | LF | 138 | 27 (20%) | $12.00 | $16.54 |
| Arrow board / advance warning arrow panel | 0102-76 | ED | 110 | 26 (24%) | $7.00 | $5.90 |
| Removal of existing concrete | 0110-4-10 | SY | 88 | 26 (30%) | $40.00 | $33.96 |
| Mowing | 0107-2 | ACRE | 71 | 26 (37%) | $100.00 | $80.65 |
| Traffic controller assembly, remove controller with | 0670-5600 | AS | 32 | 26 (81%) | $400.00 | $871.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Traffic Control Devices, Inc. | 63 | 37 of 63 |
| Chinchor Electric Inc. | 52 | 40 of 52 |
| Highway Safety Devices, Inc. | 47 | 30 of 47 |
| Powercore, Inc. | 44 | 26 of 44 |
| Florida Safety Contractors, Inc. | 36 | 21 of 36 |
| Sice Inc | 33 | 21 of 33 |
| Horsepower Electric, Inc. | 25 | 13 of 25 |
| Arc Electric Inc | 18 | 13 of 18 |
| Contact Network LLC | 15 | 11 of 15 |
| Aum Construction Inc. | 15 | 4 of 15 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 28 OCT 2026 | T7616 | District 7 | SR 55 (US 19) FROM S OF TUDOR LN TO N OF TUDOR LN | 4 of 5 | $1,064,144 | +20% |
| 26 AUG 2026 | T4757 | District 4 | SR 93 (I-75) FROM SR 869 (I-595) TO SR 25 (US 27) | 1 of 12 | $6,106,000 | Low, 2.0% under the second |
| 26 AUG 2026 | T4773 | District 4 | SR 713 TURNPIKE FEEDER RD / KINGS HWY) FROM N OF INDRIO RD TO US 1 | 6 of 13 | $3,048,000 | +17% |
| 26 AUG 2026 | T7624 | District 7 | SR 93 (I-275), SR 690 AND SR 686 FROM SR 686 TO OLD TAMPA BAY, FROM SR 694 TO | 1 of 7 | $410,768 | Low, 11% under the second |
| 20 MAY 2026 | T4737 | District 4 | SR 9 (I-95) AND SR 862 (I-595) AT VARIOUS LOCATIONS AS... | 2 of 7 | $3,049,596 | +7.0% |
| 25 MAR 2026 | T1928 | District 1 | SR 544 FROM LAKE BLUE DR TO 26TH ST NW | 3 of 10 | $1,352,917 | +13% |
| 25 MAR 2026 | T1934 | District 1 | SR 45 (US 41) AT MIDWAY BLVD | 4 of 4 | $2,073,008 | +21% |
| 25 MAR 2026 | T2A65 | District 2 | SR 8 (I-10), SR 91 (I-295) AND SR 115 (US 1) AT VARIOUS LO.. | 1 of 2 | $2,346,000 | Low, 14% under the second |
| 25 MAR 2026 | T4734 | District 4 | SR A1A, SR 816, SR 845, SR 810 AND SR 870 AT VARIOUS... | 5 of 7 | $1,899,267 | +12% |
| 25 MAR 2026 | T4735 | District 4 | SR 5, SR 805, SR 9, SR A1A AND SR 786 AT VARIOUS LOCATIONS.. | 5 of 6 | $3,901,531 | +12% |
| 25 FEB 2026 | T2A36 | District 2 | SR 103 (LANE AVE) AND SR 111 (EDGEWOOD AVE) AT S OF MANOTAK | 2 of 2 | $984,265 | +1.0% |
| 28 JAN 2026 | T4750 | District 4 | SR 5 (US 1) FROM MIDWAY RD TO S OF EDWARDS RD | 2 of 11 | $1,874,958 | +1.0% |
| 03 DEC 2025 | T4717 | District 4 | SR 736 (DAVIE BLVD) FROM SR 9 (I-95) TO SR 5 (US 1) | 5 of 8 | $2,497,373 | +11% |
| 29 OCT 2025 | T4743 | District 4 | SR 805 (US 1/N DIXIE HWY) FROM N OF LUCERNE AVE TO WPB CANAL | 2 of 10 | $2,575,000 | +4.0% |
| 28 MAY 2025 | T2991 | District 2 | SR A1A (US 90A / 3RD ST) AT 3RD AVE S AND AT 7TH AVE N | 1 of 3 | $1,901,412 | Low, 5.0% under the second |
| 29 JAN 2025 | T1907 | District 1 | SR 93 (I-275) AT NB/SB REST AREA | 1 of 3 | $714,571 | Low, 3.0% under the second |
| 29 JAN 2025 | T7571 | District 7 | SR 93 (I-275) NB/SB SKYWAY REST AREA | 1 of 3 | $714,390 | Low, 0.0% under the second |
| 28 AUG 2024 | T2992 | District 2 | SR 9 AND SR 9A (I-295) AT VARIOUS LOCATIONS AS SHOWN IN ... | 2 of 3 | $2,827,822 | +19% |
| 31 JUL 2024 | T4703 | District 4 | SR 5, SR 704, SR 809, SR 882, SR 818, SR 811, SR 7 AND SR814 | 1 of 6 | $688,162 | Low, 1.0% under the second |
| 27 MAR 2024 | T7529 | District 7 | SR 580 (E BUSCH BLVD) AT N 18TH ST AND E OF N 22ND ST | 6 of 6 | $1,855,930 | +39% |
| 06 DEC 2023 | T2954 | District 2 | SR 212 (US 90), FROM 12TH ST TO SR A1A | 3 of 4 | $4,917,143 | +29% |
| 15 NOV 2023 | T1862 | District 1 | HARDEE, LEE, | 1 of 2 | $3,737,000 | Low, 29% under the second |
| 15 NOV 2023 | T2949 | District 2 | SR 13 (HENDRICKS AVE) AT SAN MARCO BLVD | 2 of 2 | $1,896,084 | +2.0% |
| 25 OCT 2023 | T9030 | StateWide | SR 9 (I-95) AT FLAGLER WEIGH STATION | 4 of 5 | $6,391,388 | +15% |
| 13 SEP 2023 | T5803 | District 5 | SR 492 (NW 10TH/NE 14TH ST) AT NE 25TH AVE | 3 of 3 | $1,995,455 | +24% |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.