FDOT contract T4743 bid tabulation

SR 805 (US 1/N DIXIE HWY) FROM N OF LUCERNE AVE TO WPB CANAL. Let by Florida DOT on October 29, 2025, Palm Beach, District 4. 10 bids received; low bid $2,487,603 by Sice Inc.

Owner
Florida DOT
Letting
29 OCT 2025
Pay items
40
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Sice Inc$2,487,603Low
2American Lighting and Signalization, LLC.$2,575,000+4.0%
3Aum Construction Inc.$2,769,699+11%
4Arc Electric Inc$2,777,778+12%
5Weekley Asphalt Paving, Inc.$2,871,379+15%
6Horsepower Electric, Inc.$2,881,116+16%
7Signal Technology and Installation Corp.$2,998,906+21%
8Florida Engineering & Development Corp$3,025,662+22%
9Traffic Management Solutions, LLC$3,333,481+34%
10Ferreira Construction Co., Inc.$3,654,228+47%
FDOT contract T4743: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Sice Inc2. American Lighting and Signalization, LLC.3. Aum Construction Inc.4. Arc Electric Inc5. Weekley Asphalt Paving, Inc.6. Horsepower Electric, Inc.
0005Mobilization (0101-1)LS1$25,103$94,856$100,000$84,900$15,000$50,000
0010Mobilization (0101-1)LS1$223,610$95,000$200,000$84,900$150,000$95,000
0015Maintenance of traffic (0102-1)DA1$48,635$51,679$50,000$50,000$23,000$21,717
0020Maintenance of traffic (0102-1)DA1$146,422$51,679$90,000$50,000$220,000$75,000
0025Traffic control officer (0102-14)HR102$102.39$206.00$80.00$85.00$89.00$90.00
0030Work zone sign (0102-60)ED11,596$0.25$2.00$0.50$0.35$0.23$0.23
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED27,454$0.10$0.50$0.75$0.20$0.12$0.13
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD2,631$0.17$4.50$0.30$1.00$0.05$0.12
0045Arrow board / advance warning arrow panel (0102-76)ED716$4.55$19.00$10.00$10.00$6.00$5.75
0050Portable changeable message sign, temporary (0102-99)ED854$10.24$22.00$15.00$20.00$12.00$11.30
0055Type III barricade (0102-115)ED210$0.27$50.00$2.00$1.00$0.30$0.75
0060Portable regulatory, sign (0102-150-1)ED108$5.69$101.00$15.00$15.00$6.00$9.20
0065Radar speed display unit (0102-150-2)ED108$6.83$101.00$15.00$15.00$6.00$9.20
0070Sediment barrier (0104-10-3)LF73$3.41$147.00$15.00$20.00$6.00$10.00
0075Inlet protection system (0104-18)EACH193$113.77$247.00$150.00$80.00$155.00$100.00
0080Litter removal (0107-1)ACRE153$40.96$84.00$35.00$80.00$10.00$30.00
0085Removal of existing concrete (0110-4-10)SY1,066$56.88$98.00$45.00$60.00$45.00$49.20
0090Concrete curb & gutter, type F (0520-1-10)LF131$73.95$137.00$60.00$100.00$110.00$73.60
0095Concrete sidewalk and driveways, 4" thick (0522-1)SY965$136.52$166.00$100.00$90.00$61.00$127.00
0100Concrete sidewalk and driveways, 6" thick (0522-2)SY72$159.27$326.00$120.00$150.00$71.00$156.00
0105Detectable warnings (0527-2)SF51$113.77$244.00$60.00$50.00$44.00$55.20
0110Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00
0115Initial contingency amount, DO not bid (0999-25)LS1$5,665.00$5,665.00$5,665.00$5,665.00$5,665.00$5,665.00
0120Initial contingency amount, DO not bid (0999-25)LS1$44,335$44,335$44,335$44,335$44,335$44,335
0125Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH2$739.48$5,572.00$2,000.00$500.00$900.00$731.00
0130Single column ground sign assembly, remove (0700-1600)EACH2$56.88$5,202.00$500.00$100.00$300.00$230.00
0135Conduit, furnish & install, directional bore (0630-2-12)LF19,014$28.44$23.00$32.00$30.00$31.47$30.00
0140Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH78$568.83$1,012.00$1,800.00$1,500.00$1,499.87$2,000.00
0145Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF64,173$1.56$2.00$3.00$5.00$3.34$2.00
0150Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF60,162$0.27$0.50$0.15$0.25$0.32$0.10
0155Load center, rework, voltage (0715-7-21)EACH3$2,574.52$4,125.00$4,700.00$6,000.00$4,970.00$3,000.00
0160Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH153$942.03$1,467.00$1,250.00$1,250.00$1,585.00$1,700.00
0165Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 8' arm length (0715-61111)EACH7$6,709.78$6,905.00$7,500.00$10,000$8,990.00$13,000
0170Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 8' arm length (0715-61311)EACH59$10,492$8,455.00$8,500.00$11,500$11,723$14,200
0175Light pole complete, remove pole and foundation (0715-69000)EACH122$769.06$901.00$1,500.00$800.00$920.00$1,000.00
0180Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH66$619.09$699.00$750.00$650.00$1,096.00$990.00
0185Fiber optic cable locator (0633-6)DA247$163.82$62.00$150.00$175.00$167.00$200.00
0190Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH7$824.80$2,630.00$2,000.00$2,000.00$1,750.00$2,200.00
0195Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH6$824.80$2,875.00$2,000.00$2,000.00$1,749.00$2,200.00
0200Pull & splice box, F&I, 30" X 48" cover size (0635-2-15)EACH1$3,299.20$14,263$5,009.90$5,036.87$3,900.00$2,500.00
FDOT contract T4743: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of October 29, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy