FDOT contract T1934 bid tabulation

SR 45 (US 41) AT MIDWAY BLVD. Let by Florida DOT on March 25, 2026, Charlotte, District 1. 4 bids received; low bid $1,717,616 by Ajax Paving Industries of Florida LLC.

Owner
Florida DOT
Letting
25 MAR 2026
Pay items
103
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ajax Paving Industries of Florida LLC$1,717,616Low
2Horsepower Electric, Inc.$1,769,769+3.0%
3Blacktip Services Incorporated$1,867,531+9.0%
4American Lighting and Signalization, LLC.$2,073,008+21%
FDOT contract T1934: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ajax Paving Industries of Florida LLC2. Horsepower Electric, Inc.3. Blacktip Services Incorporated4. American Lighting and Signalization, LLC.
0005Mobilization (0101-1)LS1$142,686$138,322$185,000$200,000
0010Maintenance of traffic (0102-1)DA1$95,483$115,000$52,060$25,914
0015Pedestrian or bicycle special detour (0102-4-1)SY1$5,092.90$1,500.00$26,000$11,404
0020Pedestrian escort/flagger (0102-5)HR12$106.56$55.00$40.00$73.00
0025Traffic control officer (0102-14)HR122$111.59$100.00$85.00$143.00
0030Work zone sign (0102-60)ED5,180$0.23$0.35$0.65$0.34
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED9,504$0.11$0.15$0.11$0.17
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD34,373$0.09$0.10$0.10$0.05
0045Arrow board / advance warning arrow panel (0102-76)ED240$6.38$7.50$7.00$9.00
0050Portable changeable message sign, temporary (0102-99)ED776$11.69$12.00$12.00$18.00
0055Temporary signalization and maintenance, intersection (0102-104)ED120$136.03$100.00$34.37$135.00
0060Temporary traffic detection and maintenance, intersection (0102-107-1)ED120$1.06$100.00$33.00$26.00
0065Type III barricade (0102-115)ED200$0.32$0.50$0.35$0.34
0070Sediment barrier (0104-10-3)LF365$4.78$1.00$5.00$10.00
0075Inlet protection system (0104-18)EACH6$185.98$100.00$50.00$684.00
0080Clearing & grubbing (0110-1-1)ACRE1$12,647$25,000$110,428$57,018
0085Removal of existing concrete (0110-4-10)SY103$95.49$25.00$100.00$228.00
0090Borrow excavation, truck measure (0120-2-2)CY2.20$743.93$150.00$20.00$1,368.00
0095Regular excavation (3-R projects only) (0120-71)LS1$4,463.58$1,000.00$20,000$57,018
0100Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY5,235$6.46$7.50$7.11$23.00
0105Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN431.90$232.84$275.00$254.00$798.00
0110Concrete curb & gutter, type F (0520-1-10)LF116$26.57$200.00$60.00$114.00
0115Concrete sidewalk and driveways, 4" thick (0522-1)SY34$74.39$120.00$100.00$285.00
0120Concrete sidewalk and driveways, 6" thick (0522-2)SY62$83.69$140.00$150.00$399.00
0125Detectable warnings (0527-2)SF59$40.92$50.00$35.00$74.00
0130Performance turf, sod (0570-1-2)SY332$12.08$15.00$8.00$27.00
0135Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF460$2.13$1.50$3.30$2.50
0140Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF35$4.25$3.00$3.30$6.00
0145Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000
0150Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH4$1,009.62$700.00$770.00$741.00
0155Single column ground sign assembly, remove (0700-1600)EACH1$106.28$150.00$110.00$80.00
0160Raised pavement marker, type B (0706-1-3)EACH62$5.31$7.00$6.60$6.00
0165Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF17$10.63$7.00$11.00$11.00
0170Painted pavement markings, surface (0710-90)LS1$4,902.49$7,500.00$8,800.00$5,260.00
0175Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF944$3.27$6.00$6.60$4.00
0180Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF235$6.55$8.00$13.20$7.00
0185Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.06$2,922.58$7,500.00$6,600.00$3,136.00
0190Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.09$2,922.58$7,500.00$6,600.00$3,136.00
0195Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF744$17.10$30.00$19.80$18.00
0200Thermoplastic, preformed, white, message (0711-14160)EACH3$412.35$550.00$880.00$442.00
0205Thermoplastic, preformed, white, arrow (0711-14170)EACH8$269.94$450.00$385.00$290.00
0210Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.23$8,759.23$8,000.00$8,800.00$9,399.00
0215Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.05$11,679$10,000$13,200$12,531
0220Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.03$2,190.34$7,500.00$2,420.00$2,350.00
0225Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.08$4,380.68$8,000.00$5,500.00$4,701.00
0230Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.05$8,051.44$8,000.00$8,800.00$8,639.00
0235Conduit, furnish & install, open trench (0630-2-11)LF136$15.94$30.00$13.30$23.00
0240Conduit, furnish & install, directional bore (0630-2-12)LF556$31.88$30.00$37.13$40.00
0245Conduit, furnish & install, aboveground (0630-2-14)LF10$43.57$50.00$42.53$29.00
0250Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH9$2,281.74$1,800.00$1,812.00$961.00
0255Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$5,815.40$7,500.00$5,530.00$4,068.00
0260Electrical service disconnect, F&I, pole mount (0639-3-11)EACH1$2,532.55$3,500.00$4,764.00$2,028.00
0265Prestressed concrete pole, type P-II pedestal (0641-2-11)EACH1$2,690.90$3,000.00$2,171.00$1,519.00
0270Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF2,867$1.70$2.00$6.00$2.00
0275Load center, F&I, secondary voltage (0715-7-11)EACH1$13,043$20,000$15,499$14,252
0280Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 0' arm length (0715-61400)EACH7$11,734$12,000$9,941.00$12,406
0285Light pole complete, F&I, utility conflict pole standard foundation, 45' mounting height, 16' arm length (0715-65466)EACH1$12,871$15,000$10,724$13,175
0290Light pole complete, remove pole and foundation (0715-69000)EACH1$1,691.91$1,500.00$3,978.00$1,003.00
0295Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH8$834.26$1,000.00$1,325.00$592.00
0300Itsfm location documentation- intersection (0611-2-1)EACH1$1,750.36$7,500.00$3,780.00$3,125.00
0305Conduit, furnish & install, open trench (0630-2-11)LF303$23.38$50.00$13.30$23.00
0310Conduit, furnish & install, directional bore (0630-2-12)LF456$80.77$50.00$37.13$40.00
0315Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$17,826$20,000$32,845$8,427.00
0320Signal cable, remove- intersection (0632-7-6)PI1$1,602.64$1,500.00$3,978.00$1,388.00
0325Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF178$3.45$5.00$5.30$4.50
0330Fiber optic connection, install, splice (0633-2-31)EACH4$69.08$100.00$62.00$57.00
0335Fiber optic connection, install, termination (0633-2-32)EACH12$84.49$100.00$103.00$86.00
0340Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14)EACH1$85.02$200.00$117.00$97.00
0345Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH1$1,254.05$1,500.00$1,643.00$1,363.00
0350Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51)EACH1$852.33$1,200.00$1,066.00$884.00
0355Fiber optic cable locator (0633-6)DA120$305.01$100.00$233.00$211.00
0360Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH1$3,439.08$3,500.00$3,058.00$3,413.00
0365Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH15$2,162.71$2,300.00$2,090.00$2,325.00
0370Electrical service wire, & install (0639-2-1)LF20$8.02$20.00$16.52$9.00
0375Aluminum signals pole, (0646-1-11)EACH5$3,340.24$3,500.00$4,593.00$2,716.00
0380Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH2$2,450.72$2,500.00$3,616.00$1,759.00
0385Aluminum signals pole, remove (0646-1-60)EACH4$320.95$500.00$1,592.00$320.00
0390Aluminum pole- index 695-001, remove (0646-2600)EACH1$1,353.95$550.00$1,592.00$639.00
0395Steel strain pole, remove, deep foundation removal, bolt on attachment (0649-1-65)EACH4$22,485$5,000.00$15,990$12,416
0400Steel mast arm assembly, and install, single arm 70' (0649-21-15)EACH1$117,459$120,000$107,726$115,000
0405Steel mast arm assembly, and install, single arm 78' (0649-21-21)EACH3$120,710$135,000$108,579$125,000
0410Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS14$1,586.69$2,000.00$1,923.00$1,400.00
0415Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16)AS4$2,038.37$2,500.00$2,393.00$1,900.00
0420Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19)AS2$2,195.65$3,000.00$3,158.00$2,300.00
0425Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS5$759.87$1,000.00$891.00$789.00
0430Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH1$39,286$22,500$37,602$8,437.00
0435Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH4$8,477.60$7,500.00$30,956$9,800.00
0440Vehicle detection system- remove (0660-4-60)EACH1$1,602.64$1,500.00$796.00$694.00
0445Vehicle detection system- avi, bluetooth, furnish & install, cabinet equipment (0660-6121)EACH1$1,178.60$1,500.00$1,188.00$1,135.00
0450Vehicle detection system- avi, bluetooth, furnish & install, above ground equipment (0660-6122)EACH1$16,860$20,000$17,471$10,520
0455Vehicle detection system- avi, remove complete system (0660-6600)EACH1$2,596.31$500.00$795.00$1,065.00
0460Pedestrian detector, furnish & install, standard (0665-1-11)EACH8$266.75$500.00$344.00$340.00
0465Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH3$174.29$100.00$199.00$73.00
0470Traffic controller assembly, F&I, NEMA W/standard lock (0670-5160)AS1$52,050$60,000$31,709$45,000
0475Traffic controller assembly, remove controller with (0670-5600)AS1$1,564.38$1,000.00$1,591.00$673.00
0480ITS CCTV camera, non- pressurized, IP, high definition (0682-1173)EACH1$8,993.04$10,000$6,636.00$8,670.00
0485ITS CCTV camera, remove & disposal (0682-1600)EACH1$649.34$250.00$796.00$428.00
0490Managed field ethernet switch, furnish & install (0684-1-1)EACH1$4,571.98$5,500.00$2,331.00$3,872.00
0495Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH1$12,946$12,500$12,787$9,834.00
0500Remote power management rpmu, furnish and install (0685-2-1)EACH1$1,971.41$1,000.00$2,148.00$764.00
0505Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH1$951.17$750.00$1,259.00$970.00
0510Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21)EACH2$7,033.32$6,500.00$4,424.00$3,198.00
0515Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH2$7,775.12$7,500.00$4,562.00$3,333.00
FDOT contract T1934: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy