FDOT contract T4750 bid tabulation

SR 5 (US 1) FROM MIDWAY RD TO S OF EDWARDS RD. Let by Florida DOT on January 28, 2026, St Lucie, District 4. 11 bids received; low bid $1,856,551 by Carr Construction, LLC.

Owner
Florida DOT
Letting
28 JAN 2026
Pay items
36
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Carr Construction, LLC$1,856,551Low
2American Lighting and Signalization, LLC.$1,874,958+1.0%
3New Era Electric Inc$1,926,833+4.0%
4Sice Inc$1,984,923+7.0%
5Arc Electric Inc$2,100,000+13%
6Traffic Management Solutions, LLC$2,102,867+13%
7Ferreira Construction Co., Inc.$2,114,794+14%
8Gerelco Traffic Controls, Inc.$2,262,634+22%
9Signal Technology and Installation Corp.$2,345,343+26%
10Horsepower Electric, Inc.$2,370,442+28%
11Aum Construction Inc.$2,467,000+33%
FDOT contract T4750: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Carr Construction, LLC2. American Lighting and Signalization, LLC.3. New Era Electric Inc4. Sice Inc5. Arc Electric Inc6. Traffic Management Solutions, LLC
0005Mobilization (0101-1)LS1$72,300$220,121$220,000$192,193$185,000$194,395
0010Maintenance of traffic (0102-1)DA1$37,500$35,128$151,550$107,974$75,000$192,893
0015Work zone sign (0102-60)ED8,064$0.20$0.24$0.22$0.35$0.50$0.30
0020Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED52,416$0.10$0.11$0.11$0.15$0.15$0.14
0025Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD3,360$0.10$0.07$0.04$0.06$0.75$0.10
0030Arrow board / advance warning arrow panel (0102-76)ED168$5.50$6.51$2.97$8.64$10.00$7.72
0035Portable changeable message sign, temporary (0102-99)ED364$9.50$11.25$10.45$18.51$15.00$15.43
0040Type III barricade (0102-115)ED728$0.30$0.36$0.29$0.47$0.50$0.64
0045Sediment barrier (0104-10-3)LF365$5.90$3.55$1.32$3.70$5.00$2.02
0050Inlet protection system (0104-18)EACH6$566.00$142.06$160.90$246.80$301.00$209.90
0055Litter removal (0107-1)ACRE52.23$130.00$41.78$132.00$1.96$50.00$33.61
0060Mowing (0107-2)ACRE45.79$90.00$57.82$132.00$43.19$50.00$44.82
0065Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$5,000.00$1.18$8,768.64$2,467.99$10,000$3,362.12
0070Monitor existing structures- vibration monitoring (0108-2)LS1$5,000.00$1.18$5,970.33$3,084.98$10,000$3,362.12
0075Tree root and branch pruning (0110-22)EACH10$396.00$1,014.05$521.51$55.53$1,000.00$450.08
0080Performance turf, sod (0570-1-2)SY46$41.75$50.52$4.75$17.89$100.00$4.57
0085Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00
0090Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000$50,000$50,000
0095Conduit, furnish & install, open trench (0630-2-11)LF2,467$14.25$14.14$15.40$18.51$14.00$9.85
0100Conduit, furnish & install, directional bore (0630-2-12)LF11,546$21.50$18.95$22.00$30.85$28.00$34.27
0105Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH98$1,457.00$1,351.19$1,320.00$905.98$2,800.00$1,343.79
0110Electrical power service, F&I, underground, meter by contractor (0639-1122)AS3$5,100.00$5,451.31$5,882.86$3,226.03$1,350.00$7,306.61
0115Electrical service wire, & install (0639-2-1)LF62$10.00$4.72$13.26$22.27$8.00$8.97
0120Electrical service wire, (0639-2-6)LF2,868$0.90$0.95$1.27$1.23$1.00$0.75
0125Prestressed concrete pole, type P-II service pole (0641-2-12)EACH3$2,254.00$1,560.37$2,786.74$2,816.26$2,310.00$1,295.33
0130Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF49,077$2.20$1.89$2.09$2.63$3.50$2.45
0135Luminaire & bracket arm, luminaire and arm; pole remains (0715-5-51)EACH18$307.00$329.77$235.22$473.85$4,000.00$273.55
0140Load center, F&I, secondary voltage (0715-7-11)EACH3$21,054$11,921$21,419$11,917$14,000$13,736
0145Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 12' arm length (0715-61242)EACH1$9,620.00$8,460.51$9,020.00$8,699.27$7,500.00$7,551.42
0150Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 12' arm length (0715-61342)EACH1$10,742$9,715.76$8,781.49$9,607.68$7,700.00$8,590.86
0155Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 8' arm length (0715-61411)EACH2$11,035$9,785.24$10,291$9,915.33$7,700.00$8,879.81
0160Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 12' arm length (0715-61442)EACH66$11,035$10,512$8,256.05$9,113.42$8,100.00$9,132.71
0165Light pole complete, F&I, utility conflict pole standard foundation, 35' mounting height, 16' arm length (0715-65266)EACH13$10,863$10,456$11,474$9,866.48$8,500.00$8,735.33
0170Light pole complete, remove pole and foundation (0715-69000)EACH20$246.00$1,343.03$963.22$2,132.34$1,000.00$1,161.37
0175Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH83$1,136.00$604.50$605.00$679.44$650.00$842.31
0180Fiber optic cable locator (0633-6)DA168$43.75$248.61$165.00$259.14$220.00$208.05
FDOT contract T4750: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 28, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy