FDOT contract T7616 bid tabulation

SR 55 (US 19) FROM S OF TUDOR LN TO N OF TUDOR LN. Let by Florida DOT on October 28, 2026, Pasco, District 7. 5 bids received; low bid $889,242 by Chinchor Electric Inc..

Owner
Florida DOT
Letting
28 OCT 2026
Pay items
82
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Chinchor Electric Inc.$889,242Low
2Sun Civil LLC$1,004,532+13%
3Blacktip Services Incorporated$1,019,891+15%
4American Lighting and Signalization, LLC.$1,064,144+20%
5Ajax Paving Industries of Florida LLC$1,067,387+20%
FDOT contract T7616: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Chinchor Electric Inc.2. Sun Civil LLC3. Blacktip Services Incorporated4. American Lighting and Signalization, LLC.5. Ajax Paving Industries of Florida LLC
0005Mobilization (0101-1)LS1$88,180$90,000$118,000$140,105$106,000
0010Maintenance of traffic 150 days (0102-1)DA1$46,386$36,015$16,000$60,000$85,000
0015Work zone sign (0102-60)ED4,320$0.32$0.25$2.22$0.21$0.01
0020Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED11,940$0.13$0.14$0.11$0.10$0.02
0025Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD7,020$0.06$0.06$0.07$0.06$0.01
0030Arrow board / advance warning arrow panel (0102-76)ED180$5.18$7.06$5.50$5.57$2.00
0035Temporary raised/retroreflective pavement marker, type B (0102-78-2)EACH30$7.56$11.76$5.50$5.58$11.52
0040Portable changeable message sign, temporary (0102-99)ED328$11.34$14.11$12.00$10.59$11.12
0045Existing ITS maintenance (0102-112)DA150$108.00$130.62$34.62$111.50$139.81
0050Inlet protection system (0104-18)EACH6$216.00$207.85$40.00$223.00$229.65
0055Litter removal (0107-1)ACRE2.01$2,014.92$2,194.03$40.00$2,341.45$792.83
0060Mowing (0107-2)ACRE1.34$3,022.39$3,291.05$40.00$3,344.93$1,189.25
0065Clearing & grubbing (0110-1-1)ACRE1$14,580$30,121$53,250$15,052$33,000
0070Removal of existing concrete (0110-4-10)SY220$41.04$46.33$50.00$42.37$34.16
0075Regular excavation (0120-1)CY32$51.84$44.72$25.00$53.52$378.03
0080Embankment (0120-6)CY13.30$56.16$69.53$20.00$57.98$454.77
0085Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11)SY2,204$17.82$16.58$18.32$8.92$7.12
0090Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN181.80$432.00$465.70$440.00$418.12$345.07
0095Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25)TN88.40$648.00$577.42$660.00$925.43$732.50
0100Inlets, DT bot, type D, <10' (0425-1541)EACH1$11,286$10,876$6,820.00$11,652$11,554
0105Pipe culvert, optional material, round, 18"SD (0430-174118)LF16$194.40$247.47$258.00$200.70$1,049.26
0110Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218)LF42$221.40$282.11$258.00$228.57$529.91
0115Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625)EACH2$3,240.00$3,067.82$1,150.00$3,344.93$3,047.44
0120Concrete curb & gutter, type E (0520-1-7)LF207$54.00$54.13$40.00$55.75$45.45
0125Concrete sidewalk and driveways, 6" thick (0522-2)SY202$110.16$111.11$82.00$113.73$99.55
0130Detectable warnings (0527-2)SF48$36.72$48.89$30.00$37.91$22.24
0135Performance turf, sod (0570-1-2)SY516$11.61$15.19$7.50$11.99$10.19
0140Painted pavement markings, standard, white, solid, 6" (0710-11101)GM0.19$1,728.00$5,224.66$6,850.00$3,902.42$2,633.71
0145Painted pavement markings, standard, white, arrows (0710-11170)EACH4$43.20$195.92$49.50$50.18$65.84
0150Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.05$1,728.00$5,224.66$3,850.00$3,902.42$2,633.71
0155Initial contingency amount, DO not bid (0999-25)LS1$44,000$44,000$44,000$44,000$44,000
0160Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH8$1,026.00$783.70$718.00$696.86$741.40
0165Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH1$8,547.12$15,021$9,250.00$8,362.32$7,546.37
0170Multi-column ground sign assembly, remove (0700-2600)EACH1$577.80$1,959.25$2,400.00$1,393.72$1,323.92
0175Sign panel, furnish & install ground mount, 31-50 SF (0700-3104)EACH1$2,108.16$2,351.10$1,650.00$1,672.46$2,647.85
0180Sign panel, remove, 31-50 SF (0700-3604)EACH1$280.80$457.16$22.00$22.30$264.78
0185Raised pavement marker, type B (0706-1-3)EACH30$7.56$13.06$5.50$5.58$11.52
0190Painted pavement markings, surface (0710-90)LS1$2,484.00$9,796.24$7,535.00$7,637.59$3,785.96
0195Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF212$9.72$7.84$4.50$4.46$14.81
0200Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF103$15.12$15.67$8.80$8.92$23.05
0205Thermoplastic, standard, arrow (0711-11170)EACH4$129.60$163.27$72.00$72.48$197.53
0210Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF180$12.96$26.12$23.00$23.42$19.75
0215Thermoplastic, preformed, white, message (0711-14160)EACH1$194.40$326.54$550.00$557.49$296.29
0220Thermoplastic, preformed, white, arrow (0711-14170)EACH1$135.00$195.92$550.00$557.49$205.76
0225Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101)GM0.19$8,424.00$13,062$12,650$12,822$12,839
0230Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201)GM0.05$8,424.00$13,062$12,650$12,822$12,839
0235Conduit, furnish & install, open trench (0630-2-11)LF60$11.09$24.12$32.00$16.95$44.59
0240Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH4$1,554.51$2,174.57$3,363.00$1,474.25$1,482.80
0245Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF372$2.16$4.51$19.50$1.77$2.28
0250Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 0' arm length (0715-61300)EACH2$9,393.06$9,824.71$10,490$11,736$9,184.86
0255Light pole complete, remove pole and foundation (0715-69000)EACH2$1,296.00$1,370.95$6,202.00$2,568.00$2,647.85
0260Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH2$826.69$737.40$2,487.00$531.00$831.42
0265Itsfm subsurface documentation- project length (0611-1-1)MI0.19$3,672.00$4,440.96$4,488.00$3,791.00$5,692.88
0270Itsfm location documentation- intersection (0611-2-1)EACH1$2,570.40$3,108.67$3,142.00$2,654.00$3,632.85
0275Conduit, furnish & install, open trench (0630-2-11)LF161$16.55$44.99$37.00$22.75$38.92
0280Conduit, furnish & install, directional bore (0630-2-12)LF421$26.13$51.07$53.00$29.75$53.49
0285Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$7,502.52$9,538.53$18,979$13,485$10,962
0290Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF394$3.73$4.51$4.55$3.85$6.62
0295Fiber optic connection, install, splice (0633-2-31)EACH4$50.76$61.39$62.00$52.41$65.83
0300Fiber optic connection, install, termination (0633-2-32)EACH12$95.04$114.94$117.00$98.12$122.86
0305Fiber optic connection hardware, F&I, splice enclosure (0633-3-11)EACH1$1,398.60$1,691.48$1,709.00$1,443.89$1,813.25
0310Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH1$59.40$71.84$73.00$61.33$77.05
0315Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14)EACH1$91.80$111.02$112.00$94.77$119.05
0320Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH1$1,715.04$2,074.19$2,097.00$1,770.58$2,224.19
0325Fiber optic connection hardware, F&I, connector panel (0633-3-17)EACH1$101.52$122.78$124.00$104.81$131.33
0330Fiber optic cable locator (0633-6)DA150$124.20$150.21$110.00$128.22$139.81
0335Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH2$1,554.51$1,346.00$2,263.00$1,475.00$1,510.33
0340Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH1$2,373.42$2,527.30$4,221.00$2,626.00$2,302.57
0345Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13)EACH1$4,748.12$4,578.76$6,992.00$5,951.00$4,321.29
0350Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH9$1,770.29$1,485.76$3,654.00$1,819.00$1,781.47
0355Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$4,332.96$4,242.69$5,738.00$5,702.00$4,668.69
0360Electrical service wire, & install (0639-2-1)LF45$5.76$8.86$24.00$4.82$6.14
0365Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$2,178.88$2,984.85$3,298.00$1,201.00$2,380.95
0370Aluminum signals pole, (0646-1-11)EACH4$2,971.52$2,789.35$4,340.00$2,175.00$2,660.56
0375Steel mast arm assembly, and install, single arm 60' (0649-21-10)EACH1$69,985$91,589$80,815$106,075$119,863
0380Steel mast arm assembly, and install, single arm 70' (0649-21-15)EACH1$78,986$110,215$100,510$141,525$90,827
0385Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS8$1,814.95$1,581.44$2,771.00$1,362.00$1,922.34
0390Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS4$1,075.14$950.69$1,062.00$720.00$980.76
0395Pedestrian detector, furnish & install, accessible (0665-1-12)EACH4$2,383.33$2,143.81$386.00$2,174.00$2,675.39
0400Traffic controller assembly, F&I, NEMA W/standard lock (0670-5160)AS1$47,824$55,684$48,178$45,420$56,577
0405Managed field ethernet switch, furnish & install (0684-1-1)EACH1$7,155.00$5,142.89$3,583.00$7,387.00$9,405.16
0410Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14)EACH1$15,431$15,711$9,213.00$8,551.00$12,313
FDOT contract T7616: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way