FDOT contract T4717 bid tabulation
SR 736 (DAVIE BLVD) FROM SR 9 (I-95) TO SR 5 (US 1). Let by Florida DOT on December 3, 2025, Broward, District 4. 8 bids received; low bid $2,258,253 by Rtech Engineering, LLC.
- Owner
- Florida DOT
- Letting
- 03 DEC 2025
- Pay items
- 68
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rtech Engineering, LLC | $2,258,253 | Low |
| 2 | Arc Electric Inc | $2,299,999 | +2.0% |
| 3 | Sice Inc | $2,366,463 | +5.0% |
| 4 | Weekley Asphalt Paving, Inc. | $2,486,564 | +10% |
| 5 | American Lighting and Signalization, LLC. | $2,497,373 | +11% |
| 6 | Horsepower Electric, Inc. | $2,545,360 | +13% |
| 7 | Aum Construction Inc. | $2,598,998 | +15% |
| 8 | Signal Technology and Installation Corp. | $2,665,028 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rtech Engineering, LLC | 2. Arc Electric Inc | 3. Sice Inc | 4. Weekley Asphalt Paving, Inc. | 5. American Lighting and Signalization, LLC. | 6. Horsepower Electric, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $205,000 | $125,000 | $231,472 | $119,885 | $222,000 | $150,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $119,500 | $125,000 | $137,301 | $181,200 | $250,000 | $100,000 |
| 0015 | Traffic control officer (0102-14) | HR | 8 | $105.00 | $300.00 | $165.09 | $95.00 | $106.00 | $100.00 |
| 0020 | Work zone sign (0102-60) | ED | 11,205 | $0.27 | $0.50 | $0.28 | $0.20 | $0.25 | $0.20 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 24,380 | $0.13 | $0.35 | $0.12 | $0.09 | $0.11 | $0.10 |
| 0030 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 49,192 | $0.06 | $0.25 | $0.07 | $0.05 | $0.06 | $0.05 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 697 | $5.64 | $15.00 | $6.88 | $5.00 | $6.00 | $7.50 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 925 | $18.20 | $20.00 | $13.76 | $10.00 | $12.00 | $10.00 |
| 0045 | Temporary signalization and maintenance, intersection (0102-104) | ED | 1,624 | $21.00 | $3.00 | $20.64 | $7.81 | $20.00 | $50.00 |
| 0050 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 1,624 | $21.00 | $3.00 | $14.45 | $7.81 | $29.00 | $50.00 |
| 0055 | Existing ITS maintenance (0102-112) | DA | 232 | $145.00 | $450.00 | $126.79 | $585.62 | $469.00 | $100.00 |
| 0060 | Type III barricade (0102-115) | ED | 510 | $0.30 | $1.00 | $0.34 | $0.25 | $0.29 | $0.25 |
| 0065 | Inlet protection system (0104-18) | EACH | 20 | $205.00 | $300.00 | $323.30 | $200.00 | $587.00 | $100.00 |
| 0070 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $17,000 | $5,000.00 | $4,333.64 | $9,000.00 | $46,945 | $15,000 |
| 0075 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $36,000 | $5,000.00 | $22,012 | $20,000 | $23,473 | $15,000 |
| 0080 | Removal of existing concrete (0110-4-10) | SY | 160 | $45.00 | $65.00 | $82.55 | $53.00 | $176.00 | $75.00 |
| 0085 | Tree root and branch pruning (0110-22) | EACH | 1 | $585.00 | $2,000.00 | $1,375.76 | $3,000.00 | $5,281.00 | $3,000.00 |
| 0090 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 164 | $150.00 | $125.00 | $165.09 | $89.00 | $293.00 | $180.00 |
| 0095 | Performance turf, sod (0570-1-2) | SY | 293 | $94.00 | $35.00 | $17.88 | $19.00 | $29.00 | $20.00 |
| 0100 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0105 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0110 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 1.85 | $3,300.00 | $3,500.00 | $4,402.42 | $4,143.33 | $3,756.00 | $3,000.00 |
| 0115 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 7 | $1,750.00 | $2,500.00 | $2,607.06 | $2,448.32 | $2,224.00 | $2,000.00 |
| 0120 | Conduit, furnish & install, open trench (0630-2-11) | LF | 334 | $22.00 | $40.00 | $23.55 | $19.97 | $23.00 | $40.00 |
| 0125 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 9,874 | $38.00 | $42.00 | $45.40 | $40.35 | $29.00 | $40.00 |
| 0130 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 350 | $40.00 | $50.00 | $61.91 | $47.15 | $36.00 | $50.00 |
| 0135 | Signal cable- repair/replace/other, furnish & install (0632-7-2) | LF | 467 | $7.80 | $6.00 | $12.38 | $11.00 | $6.00 | $25.00 |
| 0140 | Signal cable, remove- outside intersection (0632-7-7) | LF | 437 | $1.80 | $1.00 | $2.06 | $0.56 | $0.83 | $0.10 |
| 0145 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 1,545 | $4.60 | $4.00 | $4.13 | $4.52 | $4.00 | $5.00 |
| 0150 | Fiber optic cable, F&I, underground, 97 - 144 fibers (0633-1124) | LF | 12,912 | $5.95 | $5.00 | $4.47 | $5.49 | $5.00 | $7.50 |
| 0155 | Fiber optic connection, install, splice (0633-2-31) | EACH | 108 | $58.00 | $55.00 | $61.91 | $58.14 | $53.00 | $100.00 |
| 0160 | Fiber optic connection hardware, F&I, splice (0633-3-11) | EACH | 6 | $1,595.00 | $1,350.00 | $1,616.52 | $1,518.09 | $1,379.00 | $1,500.00 |
| 0165 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 14 | $62.00 | $70.00 | $68.79 | $64.60 | $59.00 | $100.00 |
| 0170 | Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13) | EACH | 72 | $55.00 | $75.00 | $75.67 | $71.06 | $65.00 | $100.00 |
| 0175 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 6 | $1,870.00 | $1,250.00 | $1,644.03 | $1,543.93 | $1,402.00 | $1,500.00 |
| 0180 | Fiber optic connection hardware, F&I, connector panel (0633-3-17) | EACH | 6 | $148.00 | $130.00 | $137.58 | $129.20 | $117.00 | $200.00 |
| 0185 | Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51) | EACH | 3 | $875.00 | $1,000.00 | $1,066.21 | $1,001.29 | $910.00 | $1,000.00 |
| 0190 | Fiber optic connection hardware, adjust/modify splice tray (0633-3-52) | EACH | 1 | $22.00 | $99.50 | $20.64 | $19.38 | $31.24 | $75.00 |
| 0195 | Fiber optic cable locator (0633-6) | DA | 232 | $145.00 | $250.00 | $198.11 | $355.30 | $323.00 | $100.00 |
| 0200 | Multi-conductor cable, furnish & install, cat 6 (0633-8-11) | LF | 438 | $6.00 | $6.00 | $10.11 | $11.48 | $3.00 | $5.00 |
| 0205 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 29 | $1,650.00 | $2,000.00 | $1,816.00 | $1,970.93 | $1,206.00 | $1,800.00 |
| 0210 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 8 | $3,250.00 | $5,000.00 | $3,879.64 | $2,781.62 | $2,454.00 | $3,500.00 |
| 0215 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 10 | $6,350.00 | $7,300.00 | $5,874.48 | $5,812.29 | $5,143.00 | $5,000.00 |
| 0220 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 6 | $5,800.00 | $7,500.00 | $5,304.23 | $6,762.02 | $4,945.00 | $15,000 |
| 0225 | Electrical service wire, & install (0639-2-1) | LF | 1,153 | $11.00 | $17.00 | $11.87 | $14.35 | $5.00 | $10.00 |
| 0230 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 6 | $2,300.00 | $5,000.00 | $2,257.14 | $3,428.39 | $696.00 | $3,500.00 |
| 0235 | Electrical power service- transformer, F&I, <5 kva, single phase, copper windings (0639-6111) | EACH | 1 | $2,850.00 | $7,500.00 | $2,154.09 | $4,119.61 | $1,298.00 | $3,000.00 |
| 0240 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 8 | $2,800.00 | $4,000.00 | $3,244.35 | $3,428.39 | $1,521.00 | $3,500.00 |
| 0245 | Concrete CCTV pole, furnish & install with lowering device, (0641-3163) | EACH | 5 | $33,150 | $32,000 | $49,505 | $39,217 | $45,258 | $60,000 |
| 0250 | Strain pole, wood, remove (0643-600) | EACH | 1 | $2,500.00 | $2,500.00 | $1,188.65 | $669.48 | $436.00 | $500.00 |
| 0255 | Vehicle detection system- avi, bluetooth, furnish & install, cabinet equipment (0660-6121) | EACH | 3 | $1,250.00 | $1,500.00 | $1,013.86 | $1,531.01 | $1,477.00 | $1,000.00 |
| 0260 | Vehicle detection system- avi, bluetooth, furnish & install, above ground equipment (0660-6122) | EACH | 3 | $9,530.00 | $11,000 | $8,587.00 | $12,112 | $11,083 | $12,500 |
| 0265 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 1 | $2,650.00 | $2,765.00 | $1,584.87 | $3,023.51 | $433.00 | $5,000.00 |
| 0270 | ITS cabinet, furnish & install, pole mount with sunshield, 24" W X 46" H X 22" D (0676-2122) | EACH | 4 | $8,900.00 | $12,500 | $8,594.48 | $11,965 | $7,979.00 | $12,000 |
| 0275 | ITS cabinet, furnish & install, base mount, 334, 24" W X 66" H X 30" D (0676-2143) | EACH | 2 | $11,500 | $15,000 | $15,484 | $15,865 | $9,577.00 | $18,000 |
| 0280 | ITS cabinet- adjust/modify (0676-2500) | EACH | 1 | $2,400.00 | $4,000.00 | $792.44 | $3,023.51 | $866.00 | $3,000.00 |
| 0285 | Small equipment enclosure, furnish and install, less than 10"W X 13"H X 11" D (0676-3-10) | EACH | 1 | $2,500.00 | $3,800.00 | $2,729.02 | $3,435.89 | $1,428.00 | $2,500.00 |
| 0290 | ITS CCTV camera, F&I, stationary, IP, high definition (0682-1153) | EACH | 1 | $7,100.00 | $10,000 | $2,313.07 | $10,917 | $10,947 | $5,000.00 |
| 0295 | ITS CCTV camera, non- pressurized, IP, high definition (0682-1173) | EACH | 6 | $5,250.00 | $7,000.00 | $4,749.34 | $7,680.88 | $7,715.00 | $7,500.00 |
| 0300 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 6 | $9,500.00 | $12,500 | $11,334 | $15,278 | $13,878 | $10,000 |
| 0305 | Managed field ethernet switch, adjust / modify (0684-1-5) | EACH | 1 | $3,200.00 | $2,800.00 | $378.33 | $355.30 | $323.00 | $900.00 |
| 0310 | Wireless communication system device, furnish & install (0684-6-1) | EACH | 4 | $3,500.00 | $6,000.00 | $6,226.94 | $7,224.35 | $6,562.00 | $5,000.00 |
| 0315 | Managed hub ethernet switch, adjust/modify (0684-7-5) | EACH | 2 | $2,850.00 | $15,000 | $11,694 | $17,248 | $15,668 | $2,000.00 |
| 0320 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 6 | $6,450.00 | $8,000.00 | $4,129.83 | $7,470.28 | $3,857.00 | $7,500.00 |
| 0325 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 6 | $1,200.00 | $1,500.00 | $1,292.08 | $1,675.09 | $796.00 | $1,000.00 |
| 0330 | Front access dynamic message sign, furnish & install- with UPS, full color, 51-100 SF (0700-8135) | EACH | 2 | $89,500 | $60,000 | $46,103 | $87,606 | $70,245 | $65,000 |
| 0335 | DMS support structure, cantilever, 21-30 FT (0700-10122) | EACH | 1 | $107,000 | $80,000 | $109,126 | $101,366 | $110,409 | $135,000 |
| 0340 | DMS support structure, cantilever, 31-40 FT (0700-10123) | EACH | 1 | $112,000 | $90,000 | $126,067 | $114,136 | $118,920 | $150,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of December 3, 2025. Compiled by Mirage Metrics.