FDOT contract T1928 bid tabulation
SR 544 FROM LAKE BLUE DR TO 26TH ST NW. Let by Florida DOT on March 25, 2026, Polk, District 1. 10 bids received; low bid $1,197,154 by Garcia Civil Contractors.
- Owner
- Florida DOT
- Letting
- 25 MAR 2026
- Pay items
- 60
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Garcia Civil Contractors | $1,197,154 | Low |
| 2 | Blacktip Services Incorporated | $1,268,638 | +6.0% |
| 3 | American Lighting and Signalization, LLC. | $1,352,917 | +13% |
| 4 | Yoroca Engineering Contractors, LLC | $1,385,948 | +16% |
| 5 | American Design Engineering Construction Inc. | $1,404,542 | +17% |
| 6 | Aj General Construction Services, Inc. | $1,407,980 | +18% |
| 7 | Sun Civil LLC | $1,436,644 | +20% |
| 8 | Central Concrete Products, Inc. | $1,563,033 | +31% |
| 9 | Gibbs & Register, Inc. | $1,633,324 | +36% |
| 10 | Hubbard Construction Company | $2,483,812 | +107% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Garcia Civil Contractors | 2. Blacktip Services Incorporated | 3. American Lighting and Signalization, LLC. | 4. Yoroca Engineering Contractors, LLC | 5. American Design Engineering Construction Inc. | 6. Aj General Construction Services, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $152,015 | $156,713 | $193,758 | $150,000 | $190,000 | $100,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $85,781 | $20,580 | $97,705 | $20,000 | $35,000 | $80,000 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $6,741.00 | $5,000.00 | $13,532 | $10,000 | $15,000 | $16,000 |
| 0020 | Traffic control officer (0102-14) | HR | 60 | $97.75 | $85.00 | $100.00 | $85.00 | $85.00 | $75.00 |
| 0025 | Work zone sign (0102-60) | ED | 10,935 | $0.25 | $0.72 | $0.25 | $0.22 | $3.00 | $0.50 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 16,154 | $0.12 | $0.11 | $0.11 | $0.10 | $3.00 | $0.25 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 9,729 | $0.09 | $0.09 | $0.05 | $0.08 | $2.98 | $0.25 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 405 | $6.90 | $6.00 | $6.00 | $6.00 | $45.00 | $11.00 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 686 | $12.65 | $12.00 | $11.00 | $15.00 | $45.00 | $16.50 |
| 0050 | Temporary signalization and maintenance, intersection (0102-104) | ED | 270 | $17.25 | $34.37 | $15.00 | $40.00 | $75.00 | $33.00 |
| 0055 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 270 | $23.00 | $30.25 | $66.00 | $40.00 | $75.00 | $22.00 |
| 0060 | Type III barricade (0102-115) | ED | 360 | $0.35 | $0.35 | $0.39 | $0.30 | $1.00 | $2.75 |
| 0065 | Removable tape, white, 24" stop bar (0102-913-23) | LF | 149 | $13.80 | $4.00 | $11.00 | $11.30 | $5.00 | $21.25 |
| 0070 | Removable tape, white, 12" crosswalk (0102-913-24) | LF | 1,291 | $6.90 | $3.00 | $7.00 | $5.65 | $10.00 | $10.50 |
| 0075 | Sediment barrier (0104-10-3) | LF | 3,937 | $1.58 | $2.50 | $6.00 | $3.50 | $12.00 | $5.50 |
| 0080 | Soil tracking prevention device (0104-15) | EACH | 1 | $2,696.40 | $500.00 | $3,383.00 | $4,000.00 | $3,500.00 | $4,600.00 |
| 0085 | Inlet protection system (0104-18) | EACH | 14 | $250.68 | $50.00 | $677.00 | $425.00 | $75.00 | $200.00 |
| 0090 | Litter removal (0107-1) | ACRE | 8.70 | $475.31 | $100.00 | $338.00 | $10.00 | $50.00 | $2,125.00 |
| 0095 | Mowing (0107-2) | ACRE | 7.54 | $663.75 | $100.00 | $677.00 | $10.00 | $50.00 | $2,250.00 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $51,722 | $90,260 | $67,659 | $30,000 | $25,000 | $28,000 |
| 0105 | Removal of existing concrete (0110-4-10) | SY | 2,431 | $30.33 | $50.00 | $40.00 | $15.00 | $11.00 | $39.75 |
| 0110 | Regular excavation (0120-1) | CY | 442.60 | $54.18 | $50.00 | $39.00 | $35.00 | $20.00 | $58.00 |
| 0115 | Embankment (0120-6) | CY | 114.60 | $106.82 | $20.00 | $39.00 | $35.00 | $20.00 | $51.00 |
| 0120 | Optional base, base group 01 (0285-701) | SY | 26 | $118.18 | $55.00 | $141.00 | $100.00 | $35.00 | $54.00 |
| 0125 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 2,153 | $10.17 | $8.70 | $11.00 | $18.00 | $20.00 | $9.00 |
| 0130 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 1.40 | $963.44 | $500.00 | $423.00 | $1,000.00 | $350.00 | $285.00 |
| 0135 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 177.60 | $268.73 | $330.00 | $423.00 | $300.00 | $350.00 | $290.00 |
| 0140 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 43.30 | $1,048.36 | $400.00 | $1,071.00 | $1,000.00 | $1,150.00 | $950.00 |
| 0145 | Concrete curb & gutter, type F (0520-1-10) | LF | 2,381 | $31.11 | $28.00 | $32.00 | $85.00 | $30.00 | $45.00 |
| 0150 | Concrete curb, type D (0520-2-4) | LF | 26 | $33.43 | $30.00 | $32.00 | $85.00 | $30.00 | $133.00 |
| 0155 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 2,147 | $53.58 | $63.00 | $54.00 | $90.00 | $60.00 | $72.00 |
| 0160 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 2,116 | $66.32 | $79.00 | $76.00 | $100.00 | $75.00 | $95.00 |
| 0165 | Detectable warnings (0527-2) | SF | 160 | $26.88 | $35.00 | $43.00 | $20.00 | $30.00 | $41.25 |
| 0170 | Performance turf, sod (0570-1-2) | SY | 2,002 | $6.32 | $6.00 | $23.00 | $7.00 | $8.00 | $14.50 |
| 0175 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0180 | Single column ground sign assembly, relocate (0700-1500) | EACH | 8 | $862.50 | $324.00 | $338.00 | $260.00 | $300.00 | $300.00 |
| 0185 | Single column ground sign assembly, remove (0700-1600) | EACH | 3 | $402.50 | $108.00 | $56.00 | $70.00 | $300.00 | $215.00 |
| 0190 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 6 | $258.75 | $54.00 | $254.00 | $40.00 | $300.00 | $480.00 |
| 0195 | Raised pavement marker, type B (0706-1-3) | EACH | 16 | $4.89 | $6.00 | $6.00 | $7.00 | $4.00 | $17.00 |
| 0200 | Painted pavement markings, surface (0710-90) | LS | 1 | $17,250 | $4,320.00 | $5,638.00 | $3,200.00 | $10,000 | $3,300.00 |
| 0205 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 763 | $4.03 | $6.48 | $6.00 | $3.10 | $6.00 | $10.50 |
| 0210 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 149 | $6.33 | $13.00 | $10.00 | $6.20 | $9.00 | $17.00 |
| 0215 | Thermoplastic, standard, arrow (0711-11170) | EACH | 2 | $86.25 | $86.00 | $101.00 | $53.00 | $90.00 | $220.00 |
| 0220 | Thermoplastic, refurbishment, white, solid, 12" for cross walk or roundabout (0711-12123) | LF | 716 | $16.06 | $4.32 | $5.00 | $2.00 | $6.00 | $10.00 |
| 0225 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,041 | $16.10 | $17.00 | $18.00 | $15.23 | $10.00 | $22.00 |
| 0230 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.04 | $12,144 | $8,640.00 | $6,766.00 | $8,295.00 | $6,000.00 | $10,450 |
| 0235 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.06 | $12,144 | $8,640.00 | $6,766.00 | $7,625.00 | $6,000.00 | $10,450 |
| 0240 | Conduit, furnish & install, open trench (0630-2-11) | LF | 78 | $28.75 | $13.30 | $16.00 | $30.00 | $20.00 | $24.00 |
| 0245 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 443 | $41.40 | $34.38 | $28.00 | $50.00 | $40.00 | $32.00 |
| 0250 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 2 | $6,497.50 | $13,023 | $11,713 | $18,000 | $18,000 | $11,600 |
| 0255 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 20 | $2,070.00 | $2,992.00 | $1,162.00 | $1,900.00 | $2,000.00 | $2,200.00 |
| 0260 | Aluminum signals pole, (0646-1-11) | EACH | 7 | $3,335.00 | $3,094.00 | $2,376.00 | $2,999.00 | $3,800.00 | $3,850.00 |
| 0265 | Aluminum signals pole, remove (0646-1-60) | EACH | 4 | $517.50 | $3,978.00 | $637.00 | $600.00 | $1,000.00 | $1,100.00 |
| 0270 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 18 | $782.00 | $1,899.00 | $477.00 | $1,200.00 | $1,500.00 | $1,320.00 |
| 0275 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 7 | $1,299.50 | $1,289.00 | $766.00 | $2,000.00 | $1,800.00 | $1,075.00 |
| 0280 | Loop assembly, F&I, type F (0660-2106) | AS | 1 | $3,795.00 | $4,675.00 | $1,824.00 | $3,000.00 | $2,100.00 | $4,400.00 |
| 0285 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 7 | $609.50 | $336.00 | $348.00 | $1,000.00 | $1,100.00 | $715.00 |
| 0290 | Traffic controller, modify (0671-2-40) | EACH | 2 | $1,495.00 | $3,183.00 | $388.00 | $3,000.00 | $2,350.00 | $5,500.00 |
| 0295 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 2 | $4,082.50 | $3,183.00 | $971.00 | $5,000.00 | $4,780.00 | $6,000.00 |
| 0300 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 2 | $2,185.00 | $7,887.00 | $8,564.00 | $8,000.00 | $8,500.00 | $15,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.