Aj General Construction Services, Inc.: FDOT bid record
Aj General Construction Services, Inc. submitted 24 bids on Florida DOT contracts in the data, from 25 AUG 2021 to 25 MAR 2026, and was the low bidder on 5 of them (21%). When it was not low, its total sat a median +32% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $2,741,422
- Latest bid
- 25 MAR 2026
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 3 | 0 | 0% |
| 2022 | 13 | 4 | 31% |
| 2023 | 4 | 0 | 0% |
| 2024 | 1 | 0 | 0% |
| 2026 | 3 | 1 | 33% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 1 | 7 | 0 | 0% |
| District 3 | 7 | 1 | 14% |
| District 2 | 6 | 3 | 50% |
| District 5 | 3 | 0 | 0% |
| District 7 | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Work zone sign | 0102-60 | ED | 21 | 8 (38%) | $0.35 | $0.25 |
| Channelizing device- types I, II, VP, drum, or LCD | 0102-74-1 | ED | 21 | 8 (38%) | $0.20 | $0.13 |
| Inlet protection system | 0104-18 | EACH | 13 | 7 (54%) | $200.00 | $150.00 |
| Portable changeable message sign, temporary | 0102-99 | ED | 20 | 6 (30%) | $16.50 | $12.00 |
| Artificial coverings /rolled erosion control products | 0104-1 | SY | 7 | 6 (86%) | $2.75 | $6.00 |
| Type III barricade | 0102-115 | ED | 14 | 5 (36%) | $0.56 | $0.34 |
| Detectable warnings | 0527-2 | SF | 13 | 5 (38%) | $29.70 | $35.00 |
| Concrete curb & gutter, type F | 0520-1-10 | LF | 10 | 5 (50%) | $44.00 | $42.32 |
| Arrow board / advance warning arrow panel | 0102-76 | ED | 8 | 5 (63%) | $8.93 | $5.90 |
| Removal of existing concrete | 0110-4-10 | SY | 17 | 4 (24%) | $37.03 | $33.96 |
| Regular excavation | 0120-1 | CY | 16 | 4 (25%) | $58.44 | $25.47 |
| Raised pavement marker, type B | 0706-1-3 | EACH | 12 | 4 (33%) | $5.81 | $5.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| American Design Engineering Construction Inc. | 7 | 7 of 7 |
| Rogar Management & Consulting of Florida LLC | 7 | 3 of 7 |
| DB Civil Construction, LLC | 4 | 2 of 4 |
| Blacktip Services Incorporated | 4 | 2 of 4 |
| CDM Contracting, Inc. | 3 | 3 of 3 |
| Leon America Construction | 3 | 3 of 3 |
| National Traffic Solution, Inc | 3 | 2 of 3 |
| Wrangler Construction Inc. | 3 | 1 of 3 |
| C.W. Roberts Contracting, Inc. | 2 | 1 of 2 |
| Concept Construction and Demoli | 2 | 2 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 25 MAR 2026 | T1928 | District 1 | SR 544 FROM LAKE BLUE DR TO 26TH ST NW | 6 of 10 | $1,407,980 | +18% |
| 25 FEB 2026 | T5868 | District 5 | SR A1A FROM HIDDEN COVE DR TO SEA DUNES DR | 10 of 11 | $317,680 | +113% |
| 28 JAN 2026 | T7580 | District 7 | SR 574 (W REYNOLDS ST) FROM E OF SR 39 TO W OF US 92 | 1 of 4 | $809,030 | Low, 46% under the second |
| 27 MAR 2024 | T1854 | District 1 | SR 45 (US 41 BUSINESS) FROM 6TH AVE 2 TO MANATEE AVE W | 2 of 3 | $1,309,703 | +3.0% |
| 06 DEC 2023 | T1884 | District 1 | SR 17, AT HILLCREST AVE | 2 of 4 | $1,292,522 | +9.0% |
| 24 MAY 2023 | T3773 | District 3 | CLARA AVE | 2 of 2 | $688,117 | +24% |
| 22 FEB 2023 | T3687 | District 3 | CR 274 (BARACK OBAMA BLVD) | 8 of 8 | $1,424,703 | +60% |
| 22 FEB 2023 | T3784 | District 3 | HORSE BARN RD | 2 of 2 | $1,154,776 | +39% |
| 16 NOV 2022 | T2882 | District 2 | SR 122 (GOLFAIR BLVD) | 2 of 2 | $1,337,089 | +4.0% |
| 26 OCT 2022 | T5765 | District 5 | SR 40 | 5 of 5 | $1,693,121 | +58% |
| 31 AUG 2022 | T2887 | District 2 | SR 5 (US 17) | 1 of 1 | $782,704 | Low |
| 31 AUG 2022 | T2923 | District 2 | SR 13 (SAN JOSE BLVD) | 1 of 4 | $212,969 | Low, 8.0% under the second |
| 31 AUG 2022 | T3833 | District 3 | SR 97 | 1 of 3 | $192,351 | Low, 44% under the second |
| 27 JUL 2022 | T1845 | District 1 | SR 80 | 5 of 5 | $2,813,212 | +99% |
| 27 JUL 2022 | T3750 | District 3 | SR 30 (US 98B) | 2 of 2 | $1,657,405 | +68% |
| 15 JUN 2022 | T2877 | District 2 | SR 212 (US 90) (BEACH BLVD) | 1 of 3 | $744,369 | Low, 20% under the second |
| 08 JUN 2022 | T2867 | District 2 | SR 207 | 4 of 6 | $573,822 | +32% |
| 25 MAY 2022 | T3801 | District 3 | SR 4 | 3 of 3 | $853,257 | +142% |
| 30 MAR 2022 | T1831 | District 1 | SR 78 | 4 of 5 | $2,044,392 | +47% |
| 30 MAR 2022 | T5726 | District 5 | SR A1A | 2 of 6 | $1,080,570 | +2.0% |
| 23 FEB 2022 | T1828 | District 1 | SR 45 | 2 of 3 | $671,689 | +20% |
| 08 DEC 2021 | T3598 | District 3 | CR 296 (SAUFLEY FIELD RD) AND SR 296 (MICHIGAN AVE) | 3 of 4 | $1,689,082 | +17% |
| 25 AUG 2021 | T1771 | District 1 | EDGEWOOD DR N | 4 of 6 | $1,104,743 | +26% |
| 25 AUG 2021 | T2851 | District 2 | SR 25 (US 41) | 6 of 7 | $406,410 | +74% |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.