DB Civil Construction, LLC: FDOT bid record
DB Civil Construction, LLC submitted 25 bids on Florida DOT contracts in the data, from 29 JUL 2020 to 28 OCT 2026, and was the low bidder on 5 of them (20%). When it was not low, its total sat a median +27% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $12,969,402
- Latest bid
- 28 OCT 2026
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 2 | 0 | 0% |
| 2021 | 1 | 0 | 0% |
| 2022 | 8 | 1 | 13% |
| 2023 | 1 | 0 | 0% |
| 2025 | 2 | 1 | 50% |
| 2026 | 11 | 3 | 27% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 2 | 13 | 3 | 23% |
| District 5 | 6 | 1 | 17% |
| District 1 | 3 | 0 | 0% |
| District 7 | 3 | 1 | 33% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Litter removal | 0107-1 | ACRE | 22 | 12 (55%) | $60.00 | $52.98 |
| Mowing | 0107-2 | ACRE | 21 | 8 (38%) | $250.00 | $80.65 |
| Sediment barrier | 0104-10-3 | LF | 20 | 7 (35%) | $2.50 | $2.60 |
| Performance turf, sod | 0570-1-2 | SY | 20 | 5 (25%) | $5.00 | $5.00 |
| Thermoplastic, standard, solid, 24" for stop line and crosswalk | 0711-11125 | LF | 18 | 5 (28%) | $9.50 | $6.09 |
| Soil tracking prevention device | 0104-15 | EACH | 6 | 5 (83%) | $1,300.00 | $3,400.00 |
| Thermoplastic, standard, solid, 12" for crosswalk and roundabout | 0711-11123 | LF | 17 | 4 (24%) | $6.00 | $3.25 |
| Thermoplastic, preformed, white, solid, 24" for crosswalk | 0711-14125 | LF | 14 | 4 (29%) | $16.50 | $17.00 |
| Pull & splice box, F&I, 13" X 24" cover size | 0635-2-11 | EACH | 12 | 4 (33%) | $1,600.00 | $1,150.00 |
| Fiber optic cable locator | 0633-6 | DA | 8 | 4 (50%) | $190.00 | $224.54 |
| Valve boxes, adjust | 0425-6 | EACH | 5 | 4 (80%) | $150.00 | $780.00 |
| Channelizing device- pedestrian LCD (longitudinal channelizing device) | 0102-74-8 | FD | 20 | 3 (15%) | $0.14 | $0.07 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Preferred Materials Inc. | 7 | 3 of 7 |
| Maer Homes, LLC | 6 | 3 of 6 |
| Watson Civil Construction, Inc. | 5 | 0 of 5 |
| Wrangler Construction Inc. | 4 | 3 of 4 |
| Aj General Construction Services, Inc. | 4 | 2 of 4 |
| Halifax Paving, Inc. | 4 | 4 of 4 |
| C.W. Roberts Contracting, Inc. | 4 | 1 of 4 |
| CDM Contracting, Inc. | 3 | 2 of 3 |
| Atlantic Civil Constructors Corp | 3 | 2 of 3 |
| Masci General Contractors, Inc | 3 | 2 of 3 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 28 OCT 2026 | T2A73 | District 2 | SR A1A FROM BEGIN 4-LANE TO SR 312, FROM FLAGLER CO LINE TO E MAGNOLIA AVE | 4 of 8 | $20,589,700 | +26% |
| 28 OCT 2026 | T2A82 | District 2 | SR 24A / SR 226 (SW 16TH AVE) FROM SR 24 (ARCHER RD) TO SR 331 (SE WILLISTON | 3 of 5 | $3,386,800 | +16% |
| 28 OCT 2026 | T2A83 | District 2 | SR 13 (HENDRICKS AVE) FROM SAN MARCO BLVD TO PRUDENTIAL DR | 4 of 6 | $2,348,950 | +14% |
| 28 OCT 2026 | T2A88 | District 2 | SW 4TH AVE, SW 11TH ST AND S LAKE AVE FROM SR 121 TO SR 121 | 1 of 6 | $627,923 | Low, 3.0% under the second |
| 30 SEP 2026 | T5893 | District 5 | SR 483 (CLYDE MORRIS BLVD) FROM RICHARD PETTY BLVD TO SR 600 | 3 of 8 | $6,265,974 | +11% |
| 30 SEP 2026 | T7622 | District 7 | SR 699 (GULF BLVD) FROM SR 682 (PINELLAS BAYWAY) TO SR 688 (WALSINGHAM | 7 of 9 | $853,397 | +44% |
| 29 JUL 2026 | T2A72 | District 2 | SR 200 (US 441 / N MLK MEMORIAL HWY) FROM NW 125TH STREET TO W OF | 6 of 9 | $256,418 | +73% |
| 29 JUL 2026 | T7619 | District 7 | MULTIUSE TRAIL AT SR 60 (W COURTNEY CAMPBELL CAUSEWAY) | 6 of 6 | $2,479,826 | +53% |
| 10 JUN 2026 | T2A47 | District 2 | SR 10 (US 90 / BEAVER ST) AT CR 119 (OTTIS RD) | 1 of 5 | $739,490 | Low, 10% under the second |
| 10 JUN 2026 | T2A63 | District 2 | SR 24 (US 441 / SW 13TH ST / MLK JR HWY) AT SR 24 (SW ARCHER | 3 of 4 | $4,299,243 | +27% |
| 10 JUN 2026 | T5886 | District 5 | SR 50 (BROAD ST) FROM 2ND AVE TO SILVER EAGLE RD | 1 of 9 | $2,517,370 | Low, 9.0% under the second |
| 11 JUN 2025 | T2A26 | District 2 | SR A1A FROM S OF OCEAN SANDS TO S OF CARCABA RD | 4 of 6 | $4,966,966 | +33% |
| 28 MAY 2025 | T7533 | District 7 | SR 93 (US 19/I-275) FROM N OF SKYWAY FISHING PIER TO S OF... | 1 of 3 | $7,799,799 | Low, 58% under the second |
| 24 MAY 2023 | T5789 | District 5 | SR 471 | 2 of 6 | $8,466,979 | 0.0% |
| 16 NOV 2022 | T2882 | District 2 | SR 122 (GOLFAIR BLVD) | 1 of 2 | $1,284,820 | Low, 4.0% under the second |
| 31 AUG 2022 | T2923 | District 2 | SR 13 (SAN JOSE BLVD) | 3 of 4 | $271,382 | +27% |
| 31 AUG 2022 | T5763 | District 5 | SR A1A | 4 of 4 | $2,513,424 | +49% |
| 08 JUN 2022 | T2867 | District 2 | SR 207 | 3 of 6 | $557,777 | +28% |
| 25 MAY 2022 | T2845 | District 2 | SR A1A | 2 of 3 | $1,031,809 | +12% |
| 30 MAR 2022 | T5726 | District 5 | SR A1A | 5 of 6 | $1,177,634 | +11% |
| 26 JAN 2022 | T1811 | District 1 | SR 555 (US 17) | 2 of 5 | $2,977,048 | +8.0% |
| 26 JAN 2022 | T1819 | District 1 | SR 600 (US 92) | 2 of 2 | $1,473,421 | +23% |
| 27 JAN 2021 | T1791 | District 1 | SR 17 | 5 of 6 | $1,008,038 | +65% |
| 29 JUL 2020 | T2780 | District 2 | SR 121 | 9 of 9 | $482,980 | +103% |
| 29 JUL 2020 | T5714 | District 5 | SR 19 | 5 of 5 | $942,048 | +77% |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.