FDOT contract T2A88 bid tabulation

SW 4TH AVE, SW 11TH ST AND S LAKE AVE FROM SR 121 TO SR 121. Let by Florida DOT on October 28, 2026, Union, District 2. 6 bids received; low bid $627,923 by DB Civil Construction, LLC.

Owner
Florida DOT
Letting
28 OCT 2026
Pay items
44
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1DB Civil Construction, LLC$627,923Low
2Yoroca Engineering Contractors, LLC$646,576+3.0%
3CDM Contracting, Inc.$662,418+5.0%
4Curt'S Construction, Inc$678,476+8.0%
5Maer Homes, LLC$859,115+37%
6Rogar Management & Consulting of Florida LLC$1,474,794+135%
FDOT contract T2A88: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. DB Civil Construction, LLC2. Yoroca Engineering Contractors, LLC3. CDM Contracting, Inc.4. Curt'S Construction, Inc5. Maer Homes, LLC6. Rogar Management & Consulting of Florida LLC
0005Mobilization (0101-1)LS1$58,000$100,000$70,956$32,300$82,585$100,000
0010Maintenance of traffic (0102-1)DA1$15,000$15,000$15,640$75,000$43,912$50,000
0015Work zone sign (0102-60)ED7,200$0.50$0.22$0.25$0.45$0.50$1.00
0020Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED34,350$0.20$0.11$0.11$0.31$0.25$1.00
0025Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD15,300$0.12$0.08$0.08$0.11$1.00$1.00
0030Portable changeable message sign, temporary (0102-99)ED300$18.00$6.00$17.60$20.00$16.00$30.00
0035Sediment barrier (0104-10-3)LF4,558$1.50$1.93$1.33$7.00$5.00$2.00
0040Inlet protection system (0104-18)EACH16$150.00$200.00$137.50$300.00$427.50$100.00
0045Clearing & grubbing (0110-1-1)ACRE1$37,500$15,000$10,621$30,000$42,110$35,000
0050Removal of existing concrete (0110-4-10)SY1,095$23.00$9.00$35.80$9.00$20.00$55.00
0055Mailbox, F&I single (0110-7-1)EACH2$200.00$300.00$273.75$150.00$425.00$200.00
0060Tree removal (0110-23)EACH1$8,491.30$2,000.00$550.00$1,500.00$4,500.00$1,000.00
0065Regular excavation (0120-1)CY650.10$37.00$30.00$50.92$25.00$21.00$51.00
0070Embankment (0120-6)CY224.20$40.00$30.00$57.54$15.00$30.00$61.00
0075Concrete class NS, gravity index 400-011 (0400-0-11)CY8.90$1,100.00$800.00$2,950.79$2,000.00$1,800.00$4,800.00
0080Inlets, DT bot, type D, <10' (0425-1541)EACH2$6,000.00$6,900.00$6,906.50$3,200.00$7,500.00$25,000
0085Manhole, adjust, utilities (0425-5-1)EACH1$800.00$750.00$1,220.00$600.00$2,200.00$10,000
0090Yard drain (0425-10)EACH1$2,500.00$8,000.00$2,904.50$1,500.00$1,800.00$5,000.00
0095Pipe culvert, optional material, round, 18"SD (0430-174118)LF198$120.00$180.00$154.67$82.00$175.00$260.00
0100Pipe culvert,optional material,round, 12"S/CD (0430-175112)LF14$180.00$180.00$110.36$78.00$250.00$500.00
0105Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF4$240.00$180.00$203.75$74.00$400.00$500.00
0110Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF4$260.00$18.00$228.13$82.00$400.00$500.00
0115Pipe culvert,optional material,other-elip/arch, (0430-175218)LF14$260.00$180.00$167.14$99.60$400.00$500.00
0120Straight concrete endwalls, single, 0 degrees, round (0430-515100)EACH1$3,500.00$6,000.00$2,885.00$2,956.00$4,000.00$10,000
0125Straight concrete endwalls, single, 0 degrees, round (0430-518100)EACH1$4,000.00$6,000.00$3,665.00$3,011.20$4,000.00$15,000
0130Straight concrete endwalls, single, 0 degrees, elliptical (0430-518102)EACH1$4,000.00$6,000.00$3,665.00$3,032.00$4,500.00$15,000
0135Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625)EACH1$2,800.00$1,500.00$1,747.50$1,750.00$4,300.00$15,000
0140Pipe handrail - guiderail, aluminum (0515-1-2)LF314$74.00$110.00$64.98$65.80$70.00$70.00
0145Concrete curb & gutter, type F (0520-1-10)LF266$35.00$45.00$66.92$31.10$45.00$75.00
0150Concrete curb, type D (0520-2-4)LF233$32.00$35.00$60.93$30.35$45.00$78.00
0155Concrete sidewalk and driveways, 6" thick (0522-2)SY3,904$60.00$65.00$58.10$68.81$82.00$165.00
0160Concrete ditch pavt, non reinforced, 3" (0524-1-1)SY53$70.00$65.00$280.00$58.86$140.00$200.00
0165Detectable warnings (0527-2)SF871$32.00$11.50$31.57$40.00$29.00$35.00
0170Performance turf, sod (0570-1-2)SY3,750$5.00$4.00$3.23$5.00$6.50$18.00
0175Architectural- special, remove 73'X8' covering with 12 poles (0751-11601)LS1$6,500.00$4,000.00$5,000.00$7,500.00$2,920.00$15,000
0180Initial contingency amount, DO not bid (0999-25)LS1$123.00$123.00$123.00$123.00$123.00$123.00
0185Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH1$900.00$750.00$1,100.00$175.00$610.00$1,500.00
0190Single column ground sign assembly, relocate (0700-1500)EACH3$200.00$150.00$266.20$125.00$654.00$500.00
0195Single column ground sign assembly, remove (0700-1600)EACH2$100.00$50.00$203.50$75.00$85.00$500.00
0200Painted pavement markings, surface (0710-90)LS1$3,000.00$3,000.00$2,739.00$4,200.00$29,000$15,000
0205Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF1,542$4.50$7.00$4.56$5.50$6.20$6.00
0210Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF38$9.00$9.00$9.12$12.55$15.00$10.00
0215Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF304$16.00$25.00$36.30$20.25$25.00$35.00
0220Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF806$5.00$3.50$4.84$7.75$10.00$6.61
FDOT contract T2A88: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy