FDOT contract T2A26 bid tabulation
SR A1A FROM S OF OCEAN SANDS TO S OF CARCABA RD. Let by Florida DOT on June 11, 2025, St Johns, District 2. 6 bids received; low bid $3,740,629 by Superior Construction Company Southeast, LLC.
- Owner
- Florida DOT
- Letting
- 11 JUN 2025
- Pay items
- 42
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Construction Company Southeast, LLC | $3,740,629 | Low |
| 2 | Coxwell, J.B. Contracting, Inc. | $4,242,712 | +13% |
| 3 | Vecellio & Grogan, Inc. | $4,280,470 | +14% |
| 4 | DB Civil Construction, LLC | $4,966,966 | +33% |
| 5 | Watson Civil Construction, Inc. | $5,595,865 | +50% |
| 6 | Maer Homes, LLC | $5,855,896 | +57% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Construction Company Southeast, LLC | 2. Coxwell, J.B. Contracting, Inc. | 3. Vecellio & Grogan, Inc. | 4. DB Civil Construction, LLC | 5. Watson Civil Construction, Inc. | 6. Maer Homes, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $374,000 | $340,000 | $400,000 | $390,000 | $550,000 | $479,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $286,415 | $30,675 | $175,000 | $220,000 | $593,000 | $185,000 |
| 0015 | Work zone sign (0102-60) | ED | 4,330 | $0.25 | $0.30 | $0.30 | $0.80 | $0.40 | $1.00 |
| 0017 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 984 | $45.00 | $48.00 | $45.00 | $54.00 | $45.00 | $72.00 |
| 0020 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 9,604 | $0.15 | $0.18 | $0.20 | $0.25 | $0.25 | $0.50 |
| 0025 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 7,600 | $0.05 | $0.06 | $0.10 | $0.15 | $0.09 | $0.50 |
| 0030 | Portable changeable message sign, temporary (0102-99) | ED | 656 | $12.00 | $14.40 | $14.00 | $14.00 | $19.00 | $20.00 |
| 0031 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.83 | $8,550.00 | $21,500 | $20,500 | $9,000.00 | $20,000 | $25,000 |
| 0032 | Removable tape, white, symbol or arrow (0102-913-29) | EACH | 38 | $550.00 | $1,075.00 | $1,015.00 | $600.00 | $1,000.00 | $1,200.00 |
| 0033 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.56 | $8,550.00 | $21,500 | $20,500 | $9,000.00 | $20,000 | $25,000 |
| 0035 | Sediment barrier (0104-10-3) | LF | 794 | $2.50 | $10.00 | $7.00 | $2.00 | $2.00 | $11.00 |
| 0040 | Soil tracking prevention device (0104-15) | EACH | 2 | $7,000.00 | $4,675.00 | $2,000.00 | $1,800.00 | $5,700.00 | $9,500.00 |
| 0045 | Litter removal (0107-1) | ACRE | 2.12 | $3,000.00 | $3,300.00 | $900.00 | $200.00 | $4,200.00 | $1,000.00 |
| 0050 | Mowing (0107-2) | ACRE | 1.56 | $3,000.00 | $2,100.00 | $250.00 | $400.00 | $4,200.00 | $1,000.00 |
| 0055 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $3,700.00 | $19,350 | $10,000 | $9,000.00 | $13,000 | $29,200 |
| 0060 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $10,750 | $64,000 | $20,000 | $15,000 | $13,000 | $25,300 |
| 0065 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $498,773 | $124,000 | $100,000 | $200,000 | $200,000 | $225,000 |
| 0070 | Regular excavation (0120-1) | CY | 279.10 | $100.00 | $59.50 | $80.00 | $60.00 | $245.00 | $100.00 |
| 0075 | Subsoil excavation (0120-4) | CY | 461.10 | $60.00 | $50.50 | $50.00 | $120.00 | $585.00 | $125.00 |
| 0080 | Embankment (0120-6) | CY | 429.40 | $70.00 | $47.00 | $45.00 | $120.00 | $177.00 | $95.00 |
| 0085 | Special fill sand (0142-70100) | LS | 1 | $50,000 | $38,100 | $50,000 | $59,227 | $60,000 | $133,000 |
| 0090 | Type B stabilization (0160-4) | SY | 429 | $50.00 | $20.00 | $120.00 | $50.00 | $57.00 | $65.00 |
| 0095 | Optional base, base group 01 B-12.5 (0285-701) | SY | 831 | $40.00 | $66.75 | $68.00 | $58.00 | $73.00 | $75.00 |
| 0100 | Optional base, base group 06 B-12.5 (0285-706) | SY | 1,047 | $40.00 | $88.20 | $89.00 | $59.00 | $75.00 | $110.00 |
| 0105 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 86.40 | $162.00 | $315.00 | $317.00 | $235.00 | $188.00 | $550.00 |
| 0110 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 154.90 | $277.00 | $321.50 | $324.00 | $380.00 | $321.00 | $650.00 |
| 0115 | Conc class IV, bulkhead (0400-4-8) | CY | 115.10 | $1,700.00 | $1,680.00 | $1,200.00 | $2,750.00 | $2,000.00 | $2,500.00 |
| 0120 | Fiber reinforced polymer bars, #5 bar (0415-10-5) | LF | 9,661 | $3.50 | $3.65 | $3.50 | $3.00 | $6.70 | $9.00 |
| 0125 | Steel sheet piling, press-in method required, project 452605-3-52-01 (0455-133209) | SF | 19,017 | $95.68 | $147.50 | $145.00 | $165.00 | $155.00 | $185.00 |
| 0130 | Fencing, type B, 5.1-6.0, reset existing (0550-10228) | LF | 558 | $24.00 | $17.50 | $6.00 | $40.00 | $13.00 | $52.00 |
| 0135 | Performance turf, sod (0570-1-2) | SY | 33 | $60.00 | $20.00 | $22.00 | $20.00 | $57.00 | $55.00 |
| 0140 | Landscape complete- small plants (0580-1-1) | LS | 1 | $6,500.00 | $24,200 | $10,000 | $25,000 | $23,700 | $38,000 |
| 0145 | Raised pavement marker, type B (0706-1-3) | EACH | 973 | $7.00 | $10.75 | $10.00 | $8.00 | $8.00 | $15.00 |
| 0170 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0175 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $500.00 | $430.00 | $1,500.00 | $800.00 | $250.00 | $4,200.00 |
| 0180 | Raised pavement marker, type B (0706-1-3) | EACH | 257 | $7.00 | $10.75 | $10.00 | $8.00 | $8.00 | $15.00 |
| 0185 | Painted pavement markings, surface (0710-90) | LS | 1 | $2,500.00 | $8,065.00 | $7,600.00 | $3,000.00 | $2,900.00 | $9,500.00 |
| 0190 | Thermoplastic, standard, arrow (0711-11170) | EACH | 7 | $85.00 | $215.00 | $200.00 | $100.00 | $96.00 | $235.00 |
| 0195 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 194 | $10.00 | $21.50 | $20.00 | $12.00 | $11.30 | $25.00 |
| 0200 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.82 | $10,500 | $10,750 | $10,200 | $12,000 | $11,800 | $15,000 |
| 0205 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 1.02 | $10,500 | $10,750 | $8,400.00 | $12,000 | $11,800 | $15,000 |
| 0207 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 4,407 | $2.00 | $2.15 | $2.00 | $2.00 | $1.05 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of June 11, 2025. Compiled by Mirage Metrics.