FDOT contract T7619 bid tabulation
MULTIUSE TRAIL AT SR 60 (W COURTNEY CAMPBELL CAUSEWAY). Let by Florida DOT on July 29, 2026, Hillsborough, District 7. 6 bids received; low bid $1,622,913 by Turtle Infrastructure Partners, LLC.
- Owner
- Florida DOT
- Letting
- 29 JUL 2026
- Pay items
- 49
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Turtle Infrastructure Partners, LLC | $1,622,913 | Low |
| 2 | Superior Construction Company Southeast, LLC | $2,081,188 | +28% |
| 3 | Ajax Paving Industries of Florida LLC | $2,408,939 | +48% |
| 4 | Blacktip Services Incorporated | $2,444,954 | +51% |
| 5 | Southern Road & Bridge, LLC | $2,464,246 | +52% |
| 6 | DB Civil Construction, LLC | $2,479,826 | +53% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Turtle Infrastructure Partners, LLC | 2. Superior Construction Company Southeast, LLC | 3. Ajax Paving Industries of Florida LLC | 4. Blacktip Services Incorporated | 5. Southern Road & Bridge, LLC | 6. DB Civil Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Bridge deck expansion joint, rehabilitation, poured joint backer rod (0458-1-21) | LF | 56 | $271.48 | $140.00 | $99.57 | $200.00 | $150.00 | $450.00 |
| 0010 | Single component injection (0906-173100) | GA | 3,375 | $105.00 | $150.00 | $107.13 | $187.11 | $97.50 | $210.00 |
| 0015 | Mobilization (0101-1) | LS | 1 | $203,455 | $208,115 | $212,681 | $200,000 | $255,000 | $230,000 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $183,400 | $50,000 | $398,809 | $5,000.00 | $200,000 | $111,000 |
| 0025 | Work zone sign (0102-60) | ED | 1,010 | $0.35 | $0.25 | $0.31 | $0.27 | $0.33 | $1.00 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 52,000 | $0.17 | $0.10 | $0.15 | $0.14 | $0.16 | $0.25 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 100,000 | $0.06 | $0.04 | $0.05 | $0.08 | $0.05 | $0.10 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 456 | $14.00 | $10.00 | $12.60 | $13.00 | $13.00 | $16.00 |
| 0045 | Existing ITS maintenance (0102-112) | DA | 100 | $175.00 | $125.00 | $157.54 | $50.00 | $250.00 | $130.00 |
| 0050 | Type III barricade (0102-115) | ED | 100 | $0.49 | $0.35 | $0.44 | $0.38 | $0.46 | $1.00 |
| 0055 | Sediment barrier (0104-10-3) | LF | 15,953 | $1.95 | $3.25 | $2.84 | $2.00 | $1.50 | $1.20 |
| 0060 | Floating turbidity barrier (0104-11) | LF | 954 | $14.38 | $20.00 | $30.82 | $13.00 | $10.00 | $16.00 |
| 0065 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 147 | $7.19 | $12.00 | $17.04 | $10.00 | $22.00 | $10.00 |
| 0070 | Soil tracking prevention device (0104-15) | EACH | 2 | $3,899.06 | $3,800.00 | $7,588.83 | $920.00 | $1,800.00 | $1,400.00 |
| 0075 | Inlet protection system (0104-18) | EACH | 2 | $273.90 | $750.00 | $385.39 | $50.00 | $150.00 | $200.00 |
| 0080 | Litter removal (0107-1) | ACRE | 114.31 | $16.95 | $70.00 | $81.92 | $40.00 | $65.00 | $50.00 |
| 0085 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $23,808 | $255,567 | $230,295 | $600,000 | $50,000 | $350,000 |
| 0090 | Removal of existing concrete (0110-4-10) | SY | 115 | $107.17 | $190.00 | $285.48 | $50.00 | $185.00 | $100.00 |
| 0095 | Tree removal (0110-23) | EACH | 1 | $1,232.50 | $5,000.00 | $1,770.79 | $1,500.00 | $1,850.00 | $6,000.00 |
| 0100 | Embankment (0120-6) | CY | 229 | $97.45 | $145.00 | $76.06 | $50.00 | $185.00 | $140.00 |
| 0105 | Flowable fill (0121-70) | CY | 4 | $2,599.31 | $3,000.00 | $1,525.68 | $423.00 | $900.00 | $900.00 |
| 0110 | Type B stabilization (0160-4) | SY | 1,180 | $31.92 | $55.00 | $25.97 | $50.00 | $85.00 | $80.00 |
| 0115 | Turnout base- optional materials (0286-1) | SY | 2,895 | $11.76 | $30.00 | $24.19 | $50.00 | $88.00 | $60.00 |
| 0120 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 2,365 | $2.96 | $7.50 | $21.26 | $5.88 | $30.00 | $15.00 |
| 0125 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 130 | $315.51 | $495.00 | $1,021.77 | $327.00 | $550.00 | $250.00 |
| 0130 | Miscellaneous asphalt (0339-1) | TN | 281.50 | $385.65 | $540.00 | $843.86 | $667.00 | $722.00 | $300.00 |
| 0135 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 4.20 | $2,500.21 | $3,500.00 | $2,519.32 | $1,420.00 | $5,000.00 | $3,800.00 |
| 0140 | Pedestrian/ bicycle railing, aluminum only,42" type 1 (0515-2311) | LF | 1,917 | $124.22 | $86.00 | $113.43 | $113.00 | $120.00 | $100.00 |
| 0145 | Bollards (0519-78) | EACH | 6 | $1,415.57 | $2,500.00 | $3,303.41 | $900.00 | $800.00 | $1,500.00 |
| 0150 | Concrete curb, type D (0520-2-4) | LF | 336 | $51.38 | $40.00 | $65.70 | $32.00 | $165.00 | $70.00 |
| 0155 | Concrete slope pavement, 6", reinforced (0524-2-49) | SY | 132 | $207.14 | $285.00 | $249.90 | $75.00 | $385.00 | $320.00 |
| 0160 | Detectable warnings (0527-2) | SF | 144 | $57.00 | $40.00 | $27.73 | $33.00 | $95.00 | $40.00 |
| 0165 | Riprap- rubble, coastal shore- large boulders (0530-3-5) | TN | 50 | $138.88 | $600.00 | $435.82 | $139.00 | $1,505.00 | $500.00 |
| 0170 | Bedding stone (0530-74) | TN | 4 | $178.92 | $4,200.00 | $924.19 | $139.00 | $445.00 | $450.00 |
| 0175 | Guardrail -roadway, general (0536-1-1) | LF | 1,263 | $33.38 | $25.00 | $31.51 | $46.00 | $40.00 | $30.00 |
| 0180 | Guardrail- roadway, double (0536-1-3) | LF | 63 | $50.97 | $33.00 | $41.59 | $61.00 | $80.00 | $45.00 |
| 0185 | Pipe rail for guardrail (0536-6) | LF | 50 | $12.08 | $16.00 | $20.17 | $38.00 | $40.00 | $20.00 |
| 0190 | Guardrail removal (0536-73) | LF | 1,326 | $4.41 | $2.00 | $2.52 | $6.00 | $25.00 | $7.00 |
| 0195 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $3,417.37 | $3,500.00 | $4,411.21 | $4,025.00 | $5,250.00 | $4,500.00 |
| 0200 | Retaining wall system, permanent, excluding barrier (0548-12) | SF | 132 | $177.66 | $370.00 | $113.43 | $300.00 | $880.00 | $350.00 |
| 0205 | Performance turf, sod (0570-1-2) | SY | 161 | $8.03 | $60.00 | $52.42 | $10.00 | $18.00 | $15.00 |
| 0210 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0215 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 2 | $797.05 | $750.00 | $661.68 | $567.00 | $975.00 | $650.00 |
| 0220 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 1 | $2,003.10 | $2,500.00 | $3,150.87 | $2,700.00 | $3,250.00 | $3,000.00 |
| 0225 | Single column ground sign assembly, remove (0700-1600) | EACH | 3 | $154.06 | $45.00 | $81.92 | $71.00 | $58.80 | $100.00 |
| 0230 | Single column ground sign assembly, repair (0700-1800) | EACH | 11 | $308.13 | $700.00 | $409.61 | $351.00 | $910.00 | $400.00 |
| 0235 | Multi-column ground sign assembly, repair (0700-2800) | EACH | 1 | $1,232.50 | $7,500.00 | $1,922.03 | $1,647.00 | $9,750.00 | $1,700.00 |
| 0240 | Object marker, type 3 (0705-10-3) | EACH | 3 | $152.36 | $350.00 | $252.07 | $216.00 | $455.00 | $230.00 |
| 0245 | Fiber optic cable locator (0633-6) | DA | 100 | $161.00 | $115.00 | $144.94 | $120.00 | $149.50 | $115.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.