FDOT contract T5893 bid tabulation
SR 483 (CLYDE MORRIS BLVD) FROM RICHARD PETTY BLVD TO SR 600. Let by Florida DOT on September 30, 2026, Volusia, District 5. 8 bids received; low bid $5,641,959 by Masci General Contractors, Inc.
- Owner
- Florida DOT
- Letting
- 30 SEP 2026
- Pay items
- 155
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Masci General Contractors, Inc | $5,641,959 | Low |
| 2 | Halifax Paving, Inc. | $5,934,449 | +5.0% |
| 3 | DB Civil Construction, LLC | $6,265,974 | +11% |
| 4 | GPS Civil Construction, Inc | $6,392,353 | +13% |
| 5 | Watson Civil Construction, Inc. | $6,727,353 | +19% |
| 6 | C.W. Roberts Contracting, Inc. | $7,068,139 | +25% |
| 7 | Maer Homes, LLC | $8,159,115 | +45% |
| 8 | Southland Construction, Inc. | $8,777,778 | +56% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Masci General Contractors, Inc | 2. Halifax Paving, Inc. | 3. DB Civil Construction, LLC | 4. GPS Civil Construction, Inc | 5. Watson Civil Construction, Inc. | 6. C.W. Roberts Contracting, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $260,917 | $590,590 | $400,000 | $630,000 | $671,000 | $390,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $115,000 | $176,500 | $146,000 | $100,000 | $445,000 | $140,000 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $14,540 | $5,000.00 | $35,000 | $20,000 | $20,000 | $12,500 |
| 0020 | Traffic control officer (0102-14) | HR | 1,120 | $90.00 | $125.00 | $85.00 | $90.00 | $115.00 | $92.50 |
| 0025 | Work zone sign (0102-60) | ED | 8,565 | $0.25 | $0.21 | $0.40 | $0.24 | $0.30 | $0.25 |
| 0030 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 1,416 | $43.00 | $34.00 | $35.00 | $40.00 | $34.00 | $37.40 |
| 0035 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 996 | $13.00 | $16.00 | $17.00 | $20.00 | $16.00 | $17.60 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 22,825 | $0.12 | $0.10 | $0.12 | $0.11 | $0.14 | $0.10 |
| 0045 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 58,297 | $0.09 | $0.05 | $0.10 | $0.06 | $0.06 | $0.05 |
| 0050 | Temporary separator, F&I remove (0102-75-1) | LF | 400 | $11.00 | $21.00 | $25.00 | $25.00 | $21.00 | $23.00 |
| 0055 | Arrow board / advance warning arrow panel (0102-76) | ED | 460 | $5.00 | $5.00 | $6.00 | $6.00 | $7.00 | $5.50 |
| 0060 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 794 | $4.50 | $5.00 | $5.00 | $5.00 | $5.60 | $4.20 |
| 0065 | Portable changeable message sign, temporary (0102-99) | ED | 488 | $11.00 | $10.00 | $12.00 | $12.00 | $13.00 | $11.00 |
| 0070 | Temporary signalization and maintenance, intersection (0102-104) | ED | 460 | $12.00 | $11.18 | $60.00 | $13.00 | $20.00 | $12.50 |
| 0075 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 460 | $5.00 | $4.05 | $5.00 | $5.00 | $7.00 | $4.50 |
| 0080 | Existing ITS maintenance (0102-112) | DA | 230 | $190.00 | $180.04 | $400.00 | $200.00 | $230.00 | $203.50 |
| 0085 | Type III barricade (0102-115) | ED | 480 | $0.40 | $0.25 | $0.50 | $1.00 | $0.30 | $0.30 |
| 0090 | Sediment barrier (0104-10-3) | LF | 2,225 | $1.25 | $1.50 | $1.50 | $4.00 | $1.05 | $1.15 |
| 0095 | Floating turbidity barrier (0104-11) | LF | 31 | $25.00 | $12.00 | $18.00 | $20.00 | $11.00 | $12.50 |
| 0100 | Inlet protection system (0104-18) | EACH | 27 | $145.00 | $160.00 | $160.00 | $200.00 | $150.00 | $169.50 |
| 0105 | Litter removal (0107-1) | ACRE | 53.50 | $100.00 | $95.00 | $90.00 | $100.00 | $95.00 | $97.50 |
| 0110 | Mowing (0107-2) | ACRE | 53.29 | $175.00 | $150.00 | $90.00 | $155.00 | $150.00 | $154.00 |
| 0115 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $55,500 | $150,000 | $180,000 | $270,000 | $150,000 | $361,300 |
| 0120 | Removal of existing concrete (0110-4-10) | SY | 550 | $10.00 | $50.00 | $25.00 | $20.00 | $29.00 | $45.00 |
| 0125 | Regular excavation (0120-1) | CY | 1,025 | $6.00 | $20.00 | $32.00 | $11.00 | $26.00 | $21.75 |
| 0130 | Subsoil excavation (0120-4) | CY | 3,449.50 | $9.00 | $30.00 | $25.00 | $16.00 | $26.00 | $45.27 |
| 0135 | Embankment (0120-6) | CY | 26,133.40 | $17.34 | $22.00 | $28.00 | $24.00 | $30.00 | $31.60 |
| 0140 | Type B stabilization (0160-4) | SY | 553 | $12.50 | $35.00 | $40.00 | $30.00 | $34.00 | $33.65 |
| 0145 | Optional base, base group 13 (0285-713) | SY | 553 | $82.50 | $92.00 | $109.00 | $78.00 | $107.00 | $85.90 |
| 0150 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 19,558 | $2.50 | $3.00 | $4.50 | $6.00 | $3.30 | $6.60 |
| 0155 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 1,882.40 | $141.29 | $150.00 | $180.00 | $186.00 | $196.00 | $208.75 |
| 0160 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 1,651.60 | $155.29 | $165.00 | $225.00 | $220.00 | $201.00 | $243.00 |
| 0165 | Inlets, curb, type P-3, <10' (0425-1331) | EACH | 1 | $11,383 | $9,300.00 | $10,000 | $9,500.00 | $7,800.00 | $10,781 |
| 0170 | Inlets, curb, type P-4, <10' (0425-1341) | EACH | 2 | $11,542 | $9,500.00 | $11,000 | $9,700.00 | $8,300.00 | $11,000 |
| 0175 | Inlets, DT bot, type E, >10' (0425-1552) | EACH | 1 | $8,496.00 | $11,000 | $10,000 | $12,000 | $16,200 | $12,750 |
| 0180 | Inlets, DT bot, type E, J bot, <10' (0425-1553) | EACH | 2 | $33,579 | $50,000 | $39,000 | $43,000 | $28,000 | $58,000 |
| 0185 | Inlets, DT bot, type H, J bottom <10' (0425-1583) | EACH | 5 | $24,923 | $40,000 | $35,000 | $35,000 | $23,000 | $46,400 |
| 0190 | Manholes, P-7, <10' (0425-2-41) | EACH | 1 | $8,129.00 | $7,400.00 | $8,000.00 | $8,000.00 | $5,400.00 | $8,600.00 |
| 0195 | Manholes, P-8, partial (0425-2-63) | EACH | 8 | $6,623.00 | $5,900.00 | $5,500.00 | $6,000.00 | $4,350.00 | $6,850.00 |
| 0200 | Manholes, J-8, <10' (0425-2-91) | EACH | 3 | $14,610 | $14,000 | $18,000 | $14,000 | $12,500 | $16,250 |
| 0205 | Manholes, J-8, >10' (0425-2-92) | EACH | 3 | $25,121 | $50,000 | $32,000 | $45,000 | $31,000 | $58,000 |
| 0210 | Modify existing drainage structure (0425-11) | EACH | 1 | $5,900.00 | $4,300.00 | $6,000.00 | $4,500.00 | $7,400.00 | $5,000.00 |
| 0215 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 13 | $334.50 | $504.00 | $600.00 | $150.00 | $241.00 | $580.00 |
| 0220 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 208 | $129.35 | $150.00 | $190.00 | $160.00 | $163.00 | $174.00 |
| 0225 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 16 | $399.39 | $479.00 | $320.00 | $270.00 | $340.00 | $550.00 |
| 0230 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 25 | $347.59 | $391.00 | $330.00 | $280.00 | $340.00 | $450.00 |
| 0235 | Pipe culvert, opt material, round, 42"S/CD (0430-175142) | LF | 15 | $389.95 | $738.00 | $850.00 | $290.00 | $450.00 | $850.00 |
| 0240 | Pipe culvert, opt material, round, 48"S/CD (0430-175148) | LF | 268 | $307.45 | $283.00 | $340.00 | $300.00 | $375.00 | $330.00 |
| 0245 | Pipe culvert, opt material, round, 60"S/CD (0430-175160) | LF | 2,819 | $495.57 | $316.00 | $280.00 | $325.00 | $379.00 | $365.00 |
| 0250 | Straight concrete endwalls, single, 0 degrees, round (0430-560100) | EACH | 1 | $14,950 | $70,000 | $45,000 | $35,000 | $21,500 | $81,175 |
| 0255 | Pipe filling and plugging- place out of service (0430-830) | CY | 51.90 | $359.00 | $550.00 | $700.00 | $600.00 | $450.00 | $640.00 |
| 0260 | Concrete curb & gutter, type E (0520-1-7) | LF | 1,419 | $37.00 | $30.00 | $57.00 | $45.00 | $53.00 | $51.00 |
| 0265 | Concrete curb & gutter, type F (0520-1-10) | LF | 637 | $39.50 | $35.00 | $65.00 | $26.00 | $55.00 | $65.00 |
| 0270 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 383 | $69.90 | $75.00 | $52.00 | $65.00 | $56.00 | $80.00 |
| 0275 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 3,513 | $99.65 | $60.00 | $64.00 | $73.00 | $68.00 | $75.00 |
| 0280 | Detectable warnings (0527-2) | SF | 166 | $30.00 | $38.00 | $35.00 | $30.00 | $40.00 | $22.50 |
| 0285 | Guardrail removal (0536-73) | LF | 1,885 | $2.50 | $2.00 | $3.00 | $3.00 | $1.55 | $3.00 |
| 0290 | Performance turf, sod (0570-1-2) | SY | 20,813 | $4.00 | $3.50 | $4.00 | $5.60 | $5.75 | $5.50 |
| 0295 | Irrigation sleeve, 4" diameter (0591-1400) | LF | 1,203 | $35.00 | $30.00 | $26.00 | $31.00 | $35.00 | $34.75 |
| 0300 | Irrigation sleeve, 6" diameter (0591-1600) | LF | 1,203 | $47.00 | $44.00 | $36.00 | $45.00 | $40.00 | $51.00 |
| 0305 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 2.50 | $1,260.00 | $1,500.00 | $1,300.00 | $2,000.00 | $2.80 | $1,750.00 |
| 0310 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 1,672 | $1.05 | $1.50 | $1.10 | $2.00 | $1.70 | $1.50 |
| 0315 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,732 | $1.58 | $1.75 | $1.80 | $2.00 | $2.00 | $2.00 |
| 0320 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.72 | $525.00 | $650.00 | $550.00 | $800.00 | $720.00 | $615.00 |
| 0325 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.21 | $630.00 | $650.00 | $650.00 | $800.00 | $715.00 | $710.00 |
| 0330 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 12 | $52.50 | $55.00 | $60.00 | $62.00 | $61.50 | $46.50 |
| 0335 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 63 | $42.00 | $45.00 | $45.00 | $51.00 | $51.00 | $46.25 |
| 0340 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 2.08 | $1,260.00 | $1,500.00 | $1,400.00 | $2,000.00 | $1,670.00 | $1,740.00 |
| 0345 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 131 | $1.26 | $3.00 | $1.50 | $4.00 | $3.35 | $1.80 |
| 0350 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.27 | $630.00 | $650.00 | $650.00 | $800.00 | $720.00 | $712.00 |
| 0355 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $60,000 | $60,000 | $60,000 | $60,000 | $60,000 | $60,000 |
| 0360 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 6 | $595.35 | $525.00 | $700.00 | $600.00 | $542.00 | $810.00 |
| 0365 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 3 | $2,296.35 | $2,100.00 | $2,600.00 | $2,350.00 | $2,200.00 | $2,000.00 |
| 0370 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 2 | $3,119.55 | $2,600.00 | $3,600.00 | $2,950.00 | $2,700.00 | $2,350.00 |
| 0375 | Single column ground sign assembly, relocate (0700-1500) | EACH | 2 | $525.00 | $100.00 | $600.00 | $120.00 | $104.00 | $325.00 |
| 0380 | Single column ground sign assembly, remove (0700-1600) | EACH | 10 | $52.50 | $50.00 | $60.00 | $55.00 | $52.00 | $55.50 |
| 0385 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 2 | $8,092.35 | $4,600.00 | $9,500.00 | $5,200.00 | $4,800.00 | $6,600.00 |
| 0390 | Delineator, flexible tubular (0705-11-1) | EACH | 2 | $157.50 | $150.00 | $200.00 | $170.00 | $155.00 | $200.00 |
| 0395 | Raised pavement marker, type B (0706-1-3) | EACH | 724 | $4.20 | $5.00 | $5.00 | $5.50 | $5.60 | $5.15 |
| 0400 | Painted pavement markings, surface (0710-90) | LS | 1 | $8,442.00 | $10,821 | $9,000.00 | $13,000 | $12,100 | $13,300 |
| 0405 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.12 | $7,560.00 | $4,800.00 | $7,600.00 | $6,000.00 | $5,200.00 | $5,750.00 |
| 0410 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,285 | $5.25 | $3.50 | $6.00 | $4.00 | $4.00 | $3.60 |
| 0415 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 361 | $7.35 | $5.00 | $8.00 | $6.00 | $5.60 | $4.60 |
| 0420 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 258 | $8.61 | $7.00 | $10.00 | $8.00 | $7.80 | $6.20 |
| 0425 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.14 | $3,150.00 | $2,000.00 | $3,400.00 | $2,300.00 | $2,150.00 | $1,460.00 |
| 0430 | Thermoplastic, standard, arrow (0711-11170) | EACH | 38 | $131.25 | $75.00 | $140.00 | $90.00 | $84.00 | $98.00 |
| 0435 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 105 | $7.35 | $5.00 | $8.00 | $6.00 | $5.60 | $4.70 |
| 0440 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.12 | $3,150.00 | $2,000.00 | $3,000.00 | $2,300.00 | $2,060.00 | $1,330.00 |
| 0445 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,143 | $15.75 | $13.50 | $16.00 | $15.00 | $15.10 | $14.50 |
| 0450 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.53 | $6,195.00 | $4,600.00 | $6,500.00 | $5,200.00 | $5,000.00 | $5,750.00 |
| 0455 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.61 | $2,520.00 | $2,000.00 | $2,600.00 | $2,300.00 | $2,200.00 | $1,320.00 |
| 0460 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 1.13 | $6,195.00 | $4,500.00 | $6,500.00 | $5,200.00 | $5,000.00 | $5,730.00 |
| 0465 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 998 | $3.68 | $3.00 | $4.00 | $4.00 | $3.35 | $2.50 |
| 0470 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 2,445 | $0.57 | $0.54 | $2.50 | $0.60 | $0.55 | $0.60 |
| 0475 | Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31) | EACH | 4 | $1,570.25 | $1,495.48 | $1,800.00 | $1,700.00 | $1,520.00 | $1,690.00 |
| 0480 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 8 | $793.80 | $756.00 | $2,300.00 | $850.00 | $765.00 | $850.00 |
| 0485 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.39 | $3,855.61 | $3,672.00 | $4,500.00 | $4,200.00 | $3,670.00 | $4,100.00 |
| 0490 | Itsfm location documentation- intersection (0611-2-1) | EACH | 3 | $2,551.50 | $2,430.00 | $1,900.00 | $2,700.00 | $2,450.00 | $2,750.00 |
| 0495 | Conduit, furnish & install, open trench (0630-2-11) | LF | 818 | $11.76 | $11.20 | $20.00 | $13.00 | $11.30 | $12.50 |
| 0500 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 687 | $24.41 | $23.25 | $52.00 | $26.00 | $23.50 | $26.25 |
| 0505 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 75 | $53.39 | $50.85 | $65.00 | $57.00 | $51.50 | $57.50 |
| 0510 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 2 | $9,362.22 | $8,916.40 | $14,000 | $10,000 | $9,000.00 | $10,100 |
| 0515 | Signal cable, remove- intersection (0632-7-6) | PI | 2 | $2,268.00 | $2,160.00 | $1,700.00 | $2,400.00 | $2,200.00 | $2,450.00 |
| 0520 | Fiber optic cable, relocate, underground (0633-1420) | LF | 50 | $2.84 | $2.70 | $4.00 | $3.00 | $2.75 | $3.00 |
| 0525 | Fiber optic connection, install, splice (0633-2-31) | EACH | 12 | $51.03 | $48.60 | $60.00 | $55.00 | $49.00 | $55.00 |
| 0530 | Fiber optic connection hardware, F&I, splice enclosure (0633-3-11) | EACH | 3 | $1,468.53 | $1,398.60 | $1,800.00 | $1,600.00 | $1,410.00 | $1,580.00 |
| 0535 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 6 | $56.70 | $54.00 | $70.00 | $60.00 | $54.50 | $61.00 |
| 0540 | Fiber optic connection hardware, F&I, preterminated patch panel (0633-3-15) | EACH | 3 | $2,891.70 | $2,754.00 | $3,300.00 | $3,100.00 | $2,780.00 | $3,120.00 |
| 0545 | Fiber optic cable locator (0633-6) | DA | 230 | $191.65 | $182.52 | $200.00 | $205.00 | $185.00 | $205.00 |
| 0550 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 32 | $1,235.34 | $1,176.51 | $1,350.00 | $1,300.00 | $1,200.00 | $1,330.00 |
| 0555 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 3 | $3,316.44 | $3,158.51 | $6,000.00 | $3,500.00 | $3,200.00 | $3,580.00 |
| 0560 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 2 | $4,942.54 | $4,707.18 | $7,400.00 | $5,300.00 | $4,770.00 | $5,325.00 |
| 0565 | Electrical power service, F&I, underground, meter not required (0639-1123) | AS | 1 | $2,408.05 | $2,293.38 | $7,500.00 | $2,600.00 | $2,320.00 | $2,600.00 |
| 0570 | Electrical service wire, & install (0639-2-1) | LF | 244 | $6.05 | $5.76 | $9.00 | $7.00 | $5.85 | $6.50 |
| 0575 | Electrical service wire, (0639-2-6) | LF | 100 | $0.57 | $0.54 | $4.00 | $1.00 | $0.55 | $0.60 |
| 0580 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 2 | $2,455.37 | $2,338.45 | $2,500.00 | $2,700.00 | $2,370.00 | $2,650.00 |
| 0585 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 5 | $680.40 | $648.00 | $350.00 | $800.00 | $653.00 | $730.00 |
| 0590 | Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70) | EACH | 2 | $9,298.80 | $8,856.00 | $17,000 | $10,000 | $9,000.00 | $10,000 |
| 0595 | Aluminum signals pole, (0646-1-11) | EACH | 15 | $2,896.94 | $2,758.99 | $3,000.00 | $3,100.00 | $2,800.00 | $3,125.00 |
| 0600 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 1 | $1,721.99 | $1,639.41 | $2,500.00 | $1,800.00 | $1,660.00 | $1,850.00 |
| 0605 | Steel mast arm assembly, and install, single arm 40' (0649-21-3) | EACH | 1 | $64,593 | $61,518 | $74,000 | $70,000 | $62,000 | $69,600 |
| 0610 | Steel mast arm assembly, and install, single arm 50' (0649-21-6) | EACH | 1 | $69,701 | $66,382 | $82,000 | $75,000 | $67,000 | $75,050 |
| 0615 | Steel mast arm assembly, and install, single arm 60' (0649-21-10) | EACH | 1 | $75,014 | $71,442 | $90,000 | $81,000 | $72,000 | $80,800 |
| 0620 | Steel mast arm assembly, and install, single arm 70' (0649-21-15) | EACH | 1 | $90,266 | $85,968 | $110,000 | $97,000 | $87,000 | $97,200 |
| 0625 | Vehicular traffic signal, furnish & install 3 section, 1 way (0650-1-34) | AS | 7 | $1,697.00 | $1,616.19 | $1,500.00 | $1,800.00 | $1,650.00 | $1,825.00 |
| 0630 | Vehicular traffic signal, furnish & install 4 section, 1 way (0650-1-36) | AS | 2 | $1,976.57 | $1,882.45 | $2,000.00 | $2,200.00 | $1,900.00 | $2,125.00 |
| 0635 | Vehicular traffic signal, furnish & install 5 section cluster, 1 way (0650-1-39) | AS | 1 | $2,522.76 | $2,402.63 | $3,000.00 | $2,700.00 | $2,450.00 | $2,720.00 |
| 0640 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 7 | $645.39 | $614.66 | $550.00 | $700.00 | $620.00 | $700.00 |
| 0645 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 14 | $795.22 | $757.35 | $800.00 | $850.00 | $765.00 | $860.00 |
| 0650 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 1 | $113.40 | $108.00 | $150.00 | $120.00 | $109.00 | $122.00 |
| 0655 | Loop detector inductive, F&I, type 9 (0660-1109) | EACH | 3 | $267.38 | $254.65 | $350.00 | $290.00 | $257.00 | $290.00 |
| 0660 | Loop detector inductive, F&I, type 10 (0660-1110) | EACH | 4 | $325.62 | $310.12 | $400.00 | $350.00 | $313.00 | $350.00 |
| 0665 | Loop assembly, F&I, type F (0660-2106) | AS | 11 | $1,668.88 | $1,589.41 | $1,500.00 | $1,800.00 | $1,620.00 | $1,800.00 |
| 0670 | Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11) | EACH | 2 | $9,644.54 | $9,185.28 | $10,200 | $11,000 | $9,300.00 | $10,400 |
| 0675 | Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12) | EACH | 9 | $10,626 | $10,120 | $12,000 | $12,000 | $10,200 | $11,450 |
| 0680 | Traffic data detection system- video, furnish and install, cabinet equipment (0660-9-11) | EACH | 2 | $21,272 | $20,259 | $22,000 | $23,000 | $20,500 | $22,900 |
| 0685 | Traffic data detection system- video, furnish and install, ground equipment (0660-9-12) | EACH | 3 | $10,821 | $10,306 | $6,500.00 | $12,000 | $10,400 | $11,650 |
| 0690 | Signal priority and preemption system, furnish and install, detector (0663-1122) | EACH | 1 | $7,953.75 | $7,575.63 | $10,000 | $8,500.00 | $7,700.00 | $8,570.00 |
| 0695 | Signal priority and preemption system, furnish and install, cabinet electronics (0663-1123) | EACH | 1 | $8,826.52 | $8,406.21 | $11,000 | $9,500.00 | $8,500.00 | $9,500.00 |
| 0700 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 14 | $477.65 | $454.90 | $400.00 | $550.00 | $460.00 | $515.00 |
| 0705 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 1 | $56.70 | $54.00 | $250.00 | $60.00 | $54.50 | $61.00 |
| 0710 | Traffic controller assembly, F&I, NEMA W/standard lock, 1 preemption (0670-5161) | AS | 1 | $48,079 | $45,789 | $50,000 | $52,000 | $46,200 | $51,800 |
| 0715 | Traffic controller assembly, remove controller with (0670-5600) | AS | 2 | $907.00 | $864.00 | $1,700.00 | $970.00 | $871.00 | $975.00 |
| 0720 | Traffic controller, modify (0671-2-40) | EACH | 1 | $2,721.60 | $2,592.00 | $2,200.00 | $2,900.00 | $2,620.00 | $2,930.00 |
| 0725 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 1 | $2,154.60 | $2,052.00 | $400.00 | $2,300.00 | $2,100.00 | $2,320.00 |
| 0730 | Controller accessories, replace existing- furnish and install, load switch (0678-1104) | EACH | 1 | $154.60 | $147.24 | $9,000.00 | $200.00 | $150.00 | $166.00 |
| 0735 | ITS CCTV camera, pressurized, high definition (0682-1163) | EACH | 2 | $6,117.93 | $5,826.60 | $4,000.00 | $6,500.00 | $5,900.00 | $6,590.00 |
| 0740 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 3 | $3,781.89 | $3,601.80 | $4,000.00 | $4,100.00 | $3,700.00 | $4,075.00 |
| 0745 | Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13) | EACH | 2 | $13,771 | $13,115 | $12,000 | $15,000 | $13,300 | $14,825 |
| 0750 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 2 | $718.22 | $684.02 | $1,500.00 | $800.00 | $690.00 | $775.00 |
| 0755 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 3 | $1,075.62 | $1,024.40 | $1,000.00 | $1,200.00 | $1,035.00 | $1,160.00 |
| 0760 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 4 | $4,730.41 | $4,505.15 | $5,000.00 | $5,100.00 | $4,550.00 | $5,095.00 |
| 0765 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 2,101 | $3.38 | $3.22 | $3.00 | $4.00 | $3.30 | $3.60 |
| 0770 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 1 | $12,580 | $11,981 | $22,000 | $14,000 | $12,100 | $13,550 |
| 0775 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 4 | $750.66 | $714.91 | $900.00 | $800.00 | $721.00 | $800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of September 30, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.