FDOT contract T2A72 bid tabulation

SR 200 (US 441 / N MLK MEMORIAL HWY) FROM NW 125TH STREET TO W OF. Let by Florida DOT on July 29, 2026, Alachua, District 2. 9 bids received; low bid $148,618 by Concept Construction and Demoli.

Owner
Florida DOT
Letting
29 JUL 2026
Pay items
30
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Concept Construction and Demoli$148,618Low
2Yoroca Engineering Contractors, LLC$163,532+10%
3Burnett Civil Contracting of FL$167,610+13%
4CDM Contracting, Inc.$176,956+19%
5Leon America Construction$233,796+57%
6DB Civil Construction, LLC$256,418+73%
7Rogar Management & Consulting of Florida LLC$321,469+116%
8Higher Ground Land Services, LL$344,192+132%
9Wrangler Construction Inc.$423,239+185%
FDOT contract T2A72: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Concept Construction and Demoli2. Yoroca Engineering Contractors, LLC3. Burnett Civil Contracting of FL4. CDM Contracting, Inc.5. Leon America Construction6. DB Civil Construction, LLC
0005Mobilization (0101-1)LS1$10,000$20,000$7,500.00$7,250.00$40,000$24,000
0010Maintenance of traffic (0102-1)DA1$5,000.00$1,000.00$3,500.00$2,200.00$30,000$23,000
0015Work zone sign (0102-60)ED975$0.35$0.20$0.42$0.34$0.21$1.00
0020Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED3,000$0.25$0.10$0.30$0.22$0.09$0.30
0025Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD827$0.15$0.04$0.20$0.13$0.04$0.20
0030Arrow board / advance warning arrow panel (0102-76)ED75$15.00$5.00$18.00$9.90$5.70$12.00
0035Portable changeable message sign, temporary (0102-99)ED89$25.00$10.00$30.00$18.54$10.35$20.00
0040Artificial coverings /rolled erosion control products (0104-1)SY16$30.00$9.00$5.00$3.58$5.87$22.00
0045Sediment barrier (0104-10-3)LF937$0.75$3.00$2.50$2.35$2.34$2.00
0050Inlet protection system (0104-18)EACH1$100.00$250.00$500.00$130.00$137.47$250.00
0055Litter removal (0107-1)ACRE6.80$50.00$1.00$25.00$62.50$71.11$60.00
0060Mowing (0107-2)ACRE5.68$50.00$1.00$150.00$150.00$76.49$300.00
0065Clearing & grubbing (0110-1-1)ACRE1$11,000$7,000.00$3,500.00$2,000.00$18,217$35,000
0070Regular excavation (0120-1)CY326.80$20.00$20.00$25.00$41.91$22.78$40.00
0075Embankment (0120-6)CY214.80$20.00$20.00$100.00$50.68$21.20$48.00
0080Manholes, P-7, <10' (0425-2-41)EACH1$5,200.00$7,000.00$6,500.00$6,905.00$7,602.00$12,000
0085Manhole, adjust (0425-5)EACH1$500.00$500.00$650.00$1,820.00$936.00$1,100.00
0090Pipe culvert, optional material, round, 18"SD (0430-174118)LF104$100.00$165.00$108.00$158.83$124.60$122.00
0095Mitered end section, optional round, 18" SD (0430-984125)EACH3$2,000.00$1,500.00$650.00$1,803.33$3,800.00$2,600.00
0100Concrete sidewalk and driveways, 4" thick (0522-1)SY769$54.00$70.00$55.00$75.76$75.00$85.00
0105Concrete sidewalk and driveways, 6" thick (0522-2)SY99$72.00$70.00$75.00$90.29$85.00$94.00
0110Detectable warnings (0527-2)SF124$22.00$18.50$50.00$31.98$30.00$40.00
0115Fencing, type B, 5.1-6.0', W/ barb wire attmt (0550-10221)LF8$150.00$25.00$15.00$412.50$22.04$180.00
0120Fence gate, type B, sliding/cantilever, 6.1-12' (0550-60232)EACH1$4,500.00$1,000.00$7,500.00$1,925.00$1,290.00$3,000.00
0125Performance turf, sod (0570-1-2)SY1,610$4.00$3.50$8.00$3.07$4.46$4.00
0130Initial contingency amount, DO not bid (0999-25)LS1$8,526.50$8,526.50$8,526.50$8,526.50$8,526.50$8,526.50
0135Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH6$750.00$550.00$660.00$550.00$529.00$500.00
0140Single column ground sign assembly, remove (0700-1600)EACH1$25.00$50.00$100.00$55.00$39.00$60.00
0145Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF472$5.00$9.50$7.20$11.00$4.07$6.00
0150Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF214$20.00$20.00$6.00$22.00$15.74$15.00
FDOT contract T2A72: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of July 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy