FDOT contract T2A83 bid tabulation
SR 13 (HENDRICKS AVE) FROM SAN MARCO BLVD TO PRUDENTIAL DR. Let by Florida DOT on October 28, 2026, Duval, District 2. 6 bids received; low bid $2,053,866 by Preferred Materials Inc..
- Owner
- Florida DOT
- Letting
- 28 OCT 2026
- Pay items
- 84
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Preferred Materials Inc. | $2,053,866 | Low |
| 2 | Hubbard Construction Company | $2,179,120 | +6.0% |
| 3 | Duval Asphalt Products, Inc. | $2,254,698 | +10% |
| 4 | DB Civil Construction, LLC | $2,348,950 | +14% |
| 5 | Reeves Construction Company | $2,456,940 | +20% |
| 6 | Janus Construction Corp. | $2,781,748 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Preferred Materials Inc. | 2. Hubbard Construction Company | 3. Duval Asphalt Products, Inc. | 4. DB Civil Construction, LLC | 5. Reeves Construction Company | 6. Janus Construction Corp. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $174,955 | $220,966 | $375,000 | $220,000 | $435,330 | $489,049 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $249,855 | $211,122 | $137,500 | $199,700 | $136,500 | $146,725 |
| 0015 | Traffic control officer (0102-14) | HR | 212 | $100.00 | $89.87 | $90.00 | $85.00 | $110.00 | $102.13 |
| 0020 | Work zone sign (0102-60) | ED | 10,795 | $0.20 | $0.25 | $0.25 | $0.40 | $0.24 | $0.26 |
| 0025 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 156 | $45.00 | $74.73 | $55.00 | $50.00 | $76.00 | $54.00 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 23,800 | $0.10 | $0.14 | $0.25 | $0.20 | $0.13 | $0.14 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 3,551 | $0.04 | $0.06 | $0.50 | $0.20 | $0.05 | $1.07 |
| 0040 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 656 | $5.00 | $4.74 | $5.50 | $6.00 | $5.42 | $6.00 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 818 | $12.00 | $15.85 | $16.00 | $16.00 | $15.00 | $16.80 |
| 0050 | Temporary signalization and maintenance, intersection (0102-104) | ED | 1,500 | $23.09 | $24.06 | $28.60 | $27.00 | $25.00 | $46.80 |
| 0055 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 1,500 | $23.09 | $24.06 | $28.50 | $27.00 | $25.00 | $1.20 |
| 0060 | Type III barricade (0102-115) | ED | 565 | $0.25 | $0.45 | $0.50 | $1.00 | $0.45 | $1.20 |
| 0065 | Inlet protection system (0104-18) | EACH | 34 | $165.00 | $201.24 | $105.00 | $160.00 | $228.00 | $180.00 |
| 0070 | Litter removal (0107-1) | ACRE | 25.22 | $300.00 | $719.74 | $1,800.00 | $100.00 | $158.00 | $960.00 |
| 0075 | Mowing (0107-2) | ACRE | 0.41 | $750.00 | $80,193 | $3,000.00 | $400.00 | $11,267 | $1,200.00 |
| 0080 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $18,985 | $17,487 | $23,100 | $153,000 | $23,727 | $18,000 |
| 0085 | Removal of existing concrete (0110-4-10) | SY | 49 | $56.50 | $63.52 | $70.00 | $60.00 | $74.00 | $90.00 |
| 0090 | Optional base, base group 10 (0285-710) | SY | 30 | $246.04 | $374.51 | $232.00 | $300.00 | $264.00 | $318.00 |
| 0095 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 16,112 | $3.64 | $3.78 | $2.75 | $6.00 | $3.25 | $6.15 |
| 0100 | Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12) | SY | 7,722 | $4.55 | $7.86 | $3.75 | $9.00 | $4.75 | $6.96 |
| 0105 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 1,111.90 | $224.15 | $184.17 | $173.00 | $215.00 | $214.00 | $265.41 |
| 0110 | Asphalt concrete friction course,traffic B, FC-9.5, PG 76-22 (0337-7-80) | TN | 1,638.60 | $236.68 | $203.22 | $215.00 | $225.00 | $261.00 | $276.20 |
| 0115 | Inlets, curb, type 9, partial (0425-1205) | EACH | 1 | $6,300.00 | $7,082.68 | $7,800.00 | $3,500.00 | $12,415 | $4,200.00 |
| 0120 | Inlets, curb, type P-5, partial (0425-1355) | EACH | 1 | $8,850.00 | $9,949.47 | $10,960 | $5,000.00 | $15,176 | $9,000.00 |
| 0125 | Inlets, curb, type P-6, partial (0425-1365) | EACH | 2 | $8,850.00 | $9,949.48 | $10,960 | $5,500.00 | $15,176 | $10,800 |
| 0130 | Manhole, adjust (0425-5) | EACH | 22 | $1,260.00 | $1,449.78 | $1,600.00 | $800.00 | $1,690.00 | $1,800.00 |
| 0135 | Manhole, adjust, utilities (0425-5-1) | EACH | 55 | $1,260.00 | $2,175.74 | $1,600.00 | $800.00 | $1,690.00 | $2,100.00 |
| 0140 | Valve boxes, adjust (0425-6) | EACH | 58 | $1,260.00 | $1,445.36 | $1,500.00 | $150.00 | $1,690.00 | $1,250.00 |
| 0145 | Special drainage structure, utility conflict manhole, type 8 (0425-100-44) | EACH | 1 | $23,550 | $26,476 | $30,000 | $26,700 | $40,000 | $34,200 |
| 0150 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 64 | $295.00 | $331.65 | $350.00 | $300.00 | $686.00 | $540.00 |
| 0155 | Pipe liner, cured in place, 12" (0431-1112) | LF | 49 | $210.00 | $273.81 | $240.00 | $400.00 | $334.00 | $270.30 |
| 0160 | Pipe liner, cured in place, 15" (0431-1115) | LF | 210 | $200.00 | $254.15 | $280.00 | $500.00 | $308.00 | $306.60 |
| 0165 | Pipe liner, cured in place, 42" (0431-1142) | LF | 47 | $790.00 | $952.05 | $955.00 | $1,200.00 | $1,272.00 | $1,020.30 |
| 0170 | Concrete curb & gutter, type F (0520-1-10) | LF | 47 | $47.50 | $53.40 | $60.00 | $84.00 | $51.00 | $120.00 |
| 0175 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 16 | $56.00 | $62.96 | $70.00 | $190.00 | $61.00 | $180.00 |
| 0180 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 22 | $95.50 | $107.36 | $118.00 | $250.00 | $103.00 | $240.00 |
| 0185 | Detectable warnings (0527-2) | SF | 78 | $35.50 | $39.35 | $45.00 | $42.00 | $38.00 | $42.00 |
| 0190 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 1.40 | $1,600.00 | $2,104.99 | $1,650.00 | $1,600.00 | $1,733.00 | $1,560.00 |
| 0195 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 1,295 | $2.00 | $1.05 | $2.05 | $4.00 | $2.17 | $3.60 |
| 0200 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.47 | $985.01 | $777.54 | $1,050.00 | $800.00 | $1,090.00 | $780.00 |
| 0205 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.96 | $1,591.62 | $2,093.98 | $1,650.00 | $1,500.00 | $1,724.00 | $1,500.00 |
| 0210 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0215 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 52 | $510.00 | $539.50 | $600.00 | $720.00 | $552.00 | $972.00 |
| 0220 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 2 | $2,050.00 | $2,168.58 | $2,450.00 | $2,600.00 | $2,220.00 | $2,460.00 |
| 0225 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 1 | $2,250.00 | $2,380.14 | $2,500.00 | $3,500.00 | $2,437.00 | $2,700.00 |
| 0230 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $175.00 | $185.13 | $200.00 | $600.00 | $190.00 | $210.00 |
| 0235 | Single column ground sign assembly, remove (0700-1600) | EACH | 32 | $50.00 | $52.89 | $60.00 | $60.00 | $54.00 | $120.00 |
| 0240 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 2 | $125.00 | $132.23 | $150.00 | $500.00 | $135.00 | $150.00 |
| 0245 | Tubular marker, 36" yellow (0704-1-4) | EACH | 5 | $125.00 | $132.23 | $150.00 | $250.00 | $135.00 | $150.00 |
| 0250 | Raised pavement marker, type B (0706-1-3) | EACH | 656 | $5.00 | $4.74 | $6.00 | $6.00 | $5.25 | $6.00 |
| 0255 | Painted pavement markings, surface (0710-90) | LS | 1 | $18,000 | $37,469 | $25,000 | $25,996 | $19,500 | $24,000 |
| 0260 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 2,481 | $4.00 | $4.74 | $4.50 | $6.00 | $4.25 | $4.80 |
| 0265 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 476 | $5.00 | $6.84 | $5.50 | $7.00 | $5.25 | $6.00 |
| 0270 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 692 | $6.00 | $8.42 | $6.50 | $9.00 | $6.50 | $7.20 |
| 0275 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.47 | $2,462.53 | $2,591.82 | $3,000.00 | $2,700.00 | $2,725.00 | $3,000.00 |
| 0280 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $300.00 | $157.88 | $350.00 | $250.00 | $325.00 | $360.00 |
| 0285 | Thermoplastic, standard, arrow (0711-11170) | EACH | 53 | $80.00 | $105.25 | $90.00 | $100.00 | $87.00 | $96.00 |
| 0290 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 506 | $5.00 | $6.84 | $6.00 | $7.00 | $5.25 | $6.00 |
| 0295 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.07 | $4,029.85 | $2,356.42 | $5,000.00 | $2,700.00 | $5,092.00 | $5,400.00 |
| 0300 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,766 | $16.00 | $13.68 | $18.00 | $16.00 | $17.00 | $19.20 |
| 0305 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 52 | $250.00 | $263.12 | $300.00 | $280.00 | $270.00 | $300.00 |
| 0310 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 35 | $100.00 | $105.25 | $120.00 | $150.00 | $108.00 | $120.00 |
| 0315 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.47 | $5,995.92 | $6,836.59 | $7,000.00 | $6,000.00 | $6,493.00 | $7,200.00 |
| 0320 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 1.80 | $5,983.29 | $6,822.19 | $7,000.00 | $6,000.00 | $6,481.00 | $7,200.00 |
| 0325 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.30 | $4,500.00 | $2,631.27 | $5,000.00 | $3,000.00 | $4,874.00 | $5,400.00 |
| 0330 | Conduit, furnish & install, open trench (0630-2-11) | LF | 100 | $19.46 | $20.28 | $24.10 | $25.00 | $21.00 | $24.00 |
| 0335 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 6 | $4,847.53 | $5,051.00 | $6,004.04 | $6,000.00 | $5,303.00 | $7,366.20 |
| 0340 | Aluminum signals pole, (0646-1-11) | EACH | 7 | $3,642.50 | $3,795.39 | $4,511.52 | $4,500.00 | $3,984.00 | $4,596.00 |
| 0345 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 7 | $2,006.93 | $2,091.17 | $2,485.74 | $2,600.00 | $2,195.00 | $3,576.00 |
| 0350 | Aluminum signals pole, remove (0646-1-60) | EACH | 8 | $540.00 | $562.67 | $668.83 | $650.00 | $590.00 | $534.00 |
| 0355 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 5 | $909.89 | $948.08 | $1,126.97 | $1,200.00 | $995.00 | $1,494.00 |
| 0360 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 3 | $1,913.28 | $1,993.59 | $2,369.75 | $2,400.00 | $2,093.00 | $3,198.00 |
| 0365 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 1 | $216.00 | $225.07 | $267.53 | $269.00 | $236.00 | $180.00 |
| 0370 | Loop assembly, F&I, type F (0660-2106) | AS | 34 | $1,700.46 | $1,771.83 | $2,106.15 | $2,200.00 | $1,860.00 | $2,490.00 |
| 0375 | Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11) | EACH | 1 | $9,791.78 | $10,203 | $12,128 | $13,000 | $10,711 | $12,270 |
| 0380 | Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12) | EACH | 1 | $10,488 | $10,938 | $13,002 | $14,000 | $11,484 | $30,792 |
| 0385 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 39 | $354.67 | $369.56 | $439.29 | $500.00 | $388.00 | $462.00 |
| 0390 | Pedestrian detector, adjust/modify on existing pole (0665-1-50) | EACH | 19 | $346.90 | $361.46 | $429.66 | $100.00 | $379.00 | $474.00 |
| 0395 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 25 | $54.00 | $56.27 | $66.88 | $1,300.00 | $59.00 | $378.00 |
| 0400 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 1 | $1,129.36 | $1,176.76 | $1,398.80 | $1,300.00 | $1,235.00 | $1,692.00 |
| 0405 | Sign panel, furnish & install overhead mount, 12-20 SF (0700-3202) | EACH | 1 | $2,033.99 | $2,119.36 | $2,519.26 | $2,500.00 | $2,225.00 | $3,642.00 |
| 0410 | Sign panel, install, UP to 12 SF (0700-3401) | EACH | 12 | $239.11 | $249.15 | $296.16 | $300.00 | $261.00 | $1,794.00 |
| 0415 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 13 | $108.00 | $112.53 | $133.77 | $120.00 | $118.00 | $198.00 |
| 0420 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 1 | $162.00 | $168.80 | $200.65 | $220.00 | $177.00 | $498.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.