FDOT contract T2A65 bid tabulation

SR 8 (I-10), SR 91 (I-295) AND SR 115 (US 1) AT VARIOUS LO.. Let by Florida DOT on March 25, 2026, Duval, District 2. 2 bids received; low bid $2,346,000 by American Lighting and Signalization, LLC..

Owner
Florida DOT
Letting
25 MAR 2026
Pay items
67
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1American Lighting and Signalization, LLC.$2,346,000Low
2Chinchor Electric Inc.$2,667,228+14%
FDOT contract T2A65: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. American Lighting and Signalization, LLC.2. Chinchor Electric Inc.
0005Mobilization (0101-1)LS1$239,155$244,122
0010Maintenance of traffic (0102-1)DA1$134,313$264,420
0015Traffic control officer (0102-14)HR128$97.00$113.00
0020Work zone sign (0102-60)ED7,754$0.25$0.25
0025Barrier mounted work zone sign- index 700-013 (0102-62-13)ED510$0.50$12.43
0030Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED11,393$0.20$0.11
0035Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD1,560$0.07$0.09
0040Arrow board / advance warning arrow panel (0102-76)ED122$7.00$6.78
0045Portable changeable message sign, temporary (0102-99)ED552$13.00$12.43
0055Type III barricade (0102-115)ED371$0.35$0.34
0060Portable regulatory, sign (0102-150-1)ED144$7.00$6.78
0065Radar speed display unit (0102-150-2)ED144$7.00$6.78
0070Sediment barrier (0104-10-3)LF4,836$4.00$2.77
0075Inlet protection system (0104-18)EACH11$177.00$254.25
0080Clearing & grubbing (0110-1-1)ACRE1$29,538$47,460
0085Performance turf, sod (0570-1-2)SY2,461$6.00$8.78
0090Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000
0095Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH14$561.00$734.50
0100Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114)EACH2$3,692.00$3,616.00
0105Single column ground sign assembly, relocate (0700-1500)EACH21$443.00$169.50
0110Single column ground sign assembly, remove (0700-1600)EACH14$59.00$56.50
0115Sign panel, remove, UP to 12 SF (0700-3601)EACH1$59.00$39.55
0120Retroreflective sign strip- furnish and install, 2' (0700-13-12)EACH21$89.00$141.25
0125Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH45$100.00$180.80
0130Enhanced highway sign AC powered, F&I ground mount, highlighted sign <12 SF (0700-141140)EACH24$7,632.00$7,104.13
0135Object marker, type 1 (0705-10-1)EACH3$266.00$28.25
0140Raised pavement marker, type B (0706-1-3)EACH780$12.00$8.48
0145Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF25$18.00$11.30
0150Thermoplastic, standard, message or symbol (0711-11160)EACH6$591.00$282.50
0155Thermoplastic, standard, arrow (0711-11170)EACH37$177.00$175.15
0160Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF56$18.00$11.30
0165Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF54$35.00$24.86
0170Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570)EACH24$886.00$904.00
0175Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.00$11,815$20,340
0180Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.03$14,178$24,860
0185Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.02$11,815$20,340
0190Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF36$118.00$8.48
0195Load center, F&I, secondary voltage (0715-7-11)EACH2$4,914.00$6,847.80
0200Load center, rework, voltage (0715-7-21)EACH4$892.00$2,328.37
0205Itsfm subsurface documentation- project length (0611-1-1)MI2.75$3,828.00$3,955.00
0210Itsfm location documentation- ITS site (0611-2-2)EACH12$2,038.00$1,638.50
0215Conduit, furnish & install, open trench (0630-2-11)LF6,174$15.00$17.35
0220Conduit, furnish & install, directional bore (0630-2-12)LF5,105$32.00$34.43
0225Conduit, furnish & install, aboveground (0630-2-14)LF268$22.00$54.57
0230Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF9,998$4.00$4.12
0235Fiber optic connection, install, splice (0633-2-31)EACH4$53.00$72.22
0240Fiber optic connection, install, termination (0633-2-32)EACH276$89.00$78.92
0245Fiber optic connection hardware, F&I, splice (0633-3-11)EACH1$1,477.00$1,645.74
0250Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH1$59.00$63.70
0255Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14)EACH23$100.00$149.01
0260Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH21$1,566.00$1,276.12
0265Fiber optic cable locator (0633-6)DA330$266.00$187.13
0270Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH84$1,530.00$1,732.04
0275Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH33$2,550.00$2,950.76
0280Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$4,740.00$4,878.28
0285Electrical service wire, & install (0639-2-1)LF8,547$8.00$7.15
0290Electrical service disconnect, F&I, pole mount (0639-3-11)EACH12$1,494.00$2,197.92
0295Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH1$131.00$415.84
0300Electrical power service- transformer, F&I, <5 kva, single phase, copper windings (0639-6111)EACH3$1,574.00$2,305.48
0305Electrical power service- transformer, F&I, 5-10 kva, phase, copper windings (0639-6121)EACH9$3,664.00$4,010.31
0310Prestressed concrete pole, type P-II service pole (0641-2-12)EACH13$1,247.00$2,196.71
0315Vehicle detection system- wrong way for exit ramp, 1 or 2 lanes, AC powered (0660-7-21)EACH5$34,870$43,478
0320Vehicle detection system- wrong way for exit ramp, 3 or more lanes, AC powered (0660-7-22)EACH7$34,870$43,478
0325ITS cabinet, furnish & install, base mount, 334, 24" W X 66" H X 30" D (0676-2143)EACH12$12,241$13,277
0330Managed field ethernet switch, furnish & install (0684-1-1)EACH12$4,549.00$4,819.80
0335Uninterruptible power supply, furnish and install, line interactive (0685-1-11)EACH12$6,351.00$6,740.19
0340Remote power management rpmu, furnish and install (0685-2-1)EACH12$975.00$905.53
FDOT contract T2A65: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy