FDOT contract T4734 bid tabulation

SR A1A, SR 816, SR 845, SR 810 AND SR 870 AT VARIOUS... Let by Florida DOT on March 25, 2026, Broward, District 4. 7 bids received; low bid $1,689,793 by Sice Inc.

Owner
Florida DOT
Letting
25 MAR 2026
Pay items
68
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Sice Inc$1,689,793Low
2Signal Technology and Installation Corp.$1,690,6460.0%
3Arc Electric Inc$1,747,475+3.0%
4Horsepower Electric, Inc.$1,869,698+11%
5American Lighting and Signalization, LLC.$1,899,267+12%
6Aum Construction Inc.$1,946,800+15%
7Traffic Management Solutions, LLC$2,047,121+21%
FDOT contract T4734: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Sice Inc2. Signal Technology and Installation Corp.3. Arc Electric Inc4. Horsepower Electric, Inc.5. American Lighting and Signalization, LLC.6. Aum Construction Inc.
0005Mobilization (0101-1)LS1$161,332$111,878$100,000$124,727$225,176$250,000
0010Maintenance of traffic (0102-1)DA1$68,308$42,206$100,000$100,000$100,900$200,000
0015Pedestrian or bicycle special detour (0102-4-1)SY1$13,136$14,069$10,000$7,500.00$24,061$5,000.00
0020Traffic control officer (0102-14)HR72$157.63$95.48$125.00$100.00$114.01$80.00
0025Work zone sign (0102-60)ED1,742$0.37$0.38$0.50$0.25$0.30$0.30
0030Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED8,428$0.20$0.21$0.20$0.15$0.12$0.20
0035Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD9,803$0.08$0.09$0.20$0.05$0.07$0.10
0040Arrow board / advance warning arrow panel (0102-76)ED1,836$6.57$6.72$10.00$6.00$6.00$8.00
0045Portable changeable message sign, temporary (0102-99)ED2,004$12.48$12.77$12.00$12.00$11.40$12.00
0050Temporary signalization and maintenance, intersection (0102-104)ED918$34.94$20.64$6.00$50.00$24.75$15.00
0055Temporary traffic detection and maintenance, intersection (0102-107-1)ED918$26.14$20.64$6.00$50.00$29.00$15.00
0060Type III barricade (0102-115)ED356$0.55$0.74$1.00$0.25$0.36$1.50
0065Inlet protection system (0104-18)EACH5$250.33$185.05$325.00$100.00$720.25$200.00
0070Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$6,568.05$2,687.37$8,500.00$10,000$7,080.75$4,000.00
0075Clearing & grubbing (0110-1-1)ACRE1$4,539.83$10,078$3,500.54$25,000$48,005$9,769.50
0080Removal of existing concrete (0110-4-10)SY140$69.79$40.32$55.00$40.00$242.00$50.00
0085Tree protection barrier (0110-21)LF48$32.64$9.26$25.00$15.00$60.00$25.00
0090Borrow excavation, truck measure (0120-2-2)CY9.70$386.28$335.93$50.00$300.00$600.10$250.00
0095Concrete curb & gutter, type F (0520-1-10)LF162$145.59$104.81$75.00$100.00$121.00$60.00
0100Concrete sidewalk and driveways, 4" thick (0522-1)SY148$353.93$161.25$130.00$140.00$325.35$120.00
0105Concrete sidewalk and driveways, 6" thick (0522-2)SY12$367.81$214.99$200.00$175.00$685.50$150.00
0110Pavers, architectural, remove existing and reinstall (0526-1101)SY110$268.33$154.53$100.00$130.00$300.00$200.00
0115Detectable warnings (0527-2)SF56$59.11$51.06$35.00$50.00$78.00$50.00
0120Performance turf, sod (0570-1-2)SY52$36.01$4.94$100.00$15.00$121.00$30.00
0125Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00
0130Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000$50,000$50,000
0135Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH2$856.04$1,019.29$1,400.00$750.00$600.00$850.00
0140Single column ground sign assembly, remove (0700-1600)EACH2$197.04$137.57$700.00$150.00$90.00$100.00
0145Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH4$1,337.96$1,049.14$1,000.00$850.00$1,255.00$1,500.00
0150Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360)EACH1$7,486.92$11,685$10,000$9,500.00$5,360.00$9,000.00
0155Enhanced highway sign solar powered, F&I overhead mount, W/2 beacons, 21-30 SF of static sign panels (0700-142323)EACH2$5,652.66$15,851$12,500$15,000$12,050$15,000
0160Conduit, furnish & install, directional bore (0630-2-12)LF246$55.69$33.60$35.00$40.00$50.50$35.00
0165Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH4$1,839.05$1,646.82$2,500.00$2,000.00$1,635.00$2,000.00
0170Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF738$9.99$2.79$5.00$3.00$2.03$3.50
0175Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH4$1,094.57$828.66$600.00$1,100.00$579.50$750.00
0180Conduit, furnish & install, directional bore (0630-2-12)LF1,474$55.69$33.60$38.00$40.00$31.15$50.00
0185Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI4$11,838$10,038$15,000$20,000$12,158$12,000
0190Signal cable, remove- intersection (0632-7-6)PI4$2,269.92$2,063.39$750.00$1,000.00$1,152.00$500.00
0195Fiber optic cable locator (0633-6)DA153$141.87$201.56$150.00$100.00$236.00$100.00
0200Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH60$1,313.61$1,646.82$1,400.00$1,800.00$1,632.50$2,000.00
0205Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH1$3,284.02$2,640.82$3,500.00$3,500.00$2,799.00$3,000.00
0210Electrical power service, F&I, underground, meter by contractor (0639-1122)AS4$5,626.85$5,686.13$6,700.00$9,000.00$6,979.00$7,500.00
0215Electrical power service, F&I, underground, meter not required (0639-1123)AS2$5,626.85$5,686.13$6,500.00$9,000.00$4,007.25$7,000.00
0220Electrical service wire, & install (0639-2-1)LF772$16.18$6.38$12.00$20.00$8.00$10.00
0225Electrical service wire, (0639-2-6)LF794$6.57$1.38$1.00$1.00$0.60$1.00
0230Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH2$756.64$1,100.48$250.00$5,000.00$249.10$500.00
0235Prestressed concrete pole, type P-II service pole (0641-2-12)EACH6$2,645.69$3,349.71$3,000.00$4,500.00$1,342.50$3,000.00
0240Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH2$756.64$825.36$500.00$750.00$264.75$750.00
0245Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70)EACH5$3,483.69$3,301.43$4,000.00$3,000.00$8,200.00$3,500.00
0250Aluminum signals pole, (0646-1-11)EACH3$2,175.21$4,533.06$1,800.00$4,500.00$2,169.00$2,500.00
0255Aluminum signals pole, remove (0646-1-60)EACH1$1,134.96$275.13$250.00$500.00$1,463.50$250.00
0260Steel mast arm assembly, and install, single arm 40' (0649-21-3)EACH3$49,661$63,919$70,000$65,000$64,106$60,000
0265Steel mast arm assembly, and install, single arm 50' (0649-21-6)EACH2$58,049$69,617$77,000$70,000$72,270$70,000
0270Steel mast arm assembly, and install, single arm 60' (0649-21-10)EACH1$74,640$81,231$89,000$85,000$93,845$85,000
0275Steel mast arm assembly, and install on existing foundation, double arm 70'-50' (0649-22-18)EACH2$65,557$99,768$120,000$71,000$67,607$87,000
0280Steel mast arm assembly, remove, pole only- entire foundation remains (0649-26-1)EACH2$4,539.83$5,898.55$4,000.00$4,500.00$5,825.00$2,500.00
0285Steel mast arm assembly, remove, shallow foundation- bolt on attachment (0649-26-3)EACH4$7,167.05$6,635.87$3,500.00$3,500.00$4,328.00$3,500.00
0290Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS18$1,651.10$1,796.23$2,000.00$2,500.00$1,356.50$1,800.00
0295Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16)AS1$1,929.61$2,218.68$2,197.00$2,750.00$1,675.50$2,000.00
0300Vehicular traffic signal, furnish & install aluminum, 5 section straight, 1 way (0650-1-18)AS4$2,172.53$2,604.72$2,400.00$3,000.00$2,100.00$2,500.00
0305Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS3$1,178.90$965.41$1,300.00$1,200.00$541.00$1,800.00
0310Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH7$9,576.34$4,040.02$4,000.00$5,500.00$2,879.00$5,000.00
0315Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH7$6,533.49$11,844$9,000.00$10,500$8,441.00$11,000
0320Pedestrian detector, furnish & install, standard (0665-1-11)EACH3$307.23$441.91$650.00$500.00$310.00$450.00
0325Traffic controller assembly, F&I, caltrans W/electronic lock (0670-5190)AS1$49,568$49,322$57,000$60,000$42,007$55,000
0330Traffic controller assembly, remove controller with (0670-5600)AS1$4,897.14$1,925.85$1,200.00$1,000.00$997.00$1,500.00
0335Managed field ethernet switch, layer 3, furnish & install (0684-1-10)EACH1$4,988.72$12,006$9,000.00$6,500.00$10,725$12,000
0340Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH5$3,651.00$5,018.41$4,000.00$7,500.00$3,656.00$4,000.00
FDOT contract T4734: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy