IDOT contract 46937 bid tabulation

Section ILLINI. Let by Illinois DOT on June 13, 2025, Lasalle, District 03. 3 bids received; low bid $1,632,707 by D. Construction, Inc..

Owner
Illinois DOT
Letting
13 JUN 2025
Pay items
46
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D. Construction, Inc.$1,632,707Low
2Advanced Asphalt Company$1,737,725+6.0%
3Tobey's Construction & Cartage, Inc.$2,048,310+25%
IDOT contract 46937: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D. Construction, Inc.2. Advanced Asphalt Company3. Tobey's Construction & Cartage, Inc.
1Wood grdrail rem (X0327176)LF701$9.71$10.00$11.00
2Bit surf treatmnt A1 (X1500004)SY12,655$4.00$4.00$3.64
3Bit surf treatmnt A3 (X1500006)SY6,570$10.42$12.15$9.47
4Grad & shap ditch SPL (X2020114)LF5,635$40.00$3.50$18.50
5Explor trench SPL (X2130010)LF200$50.00$12.00$33.50
6Bit matls FS (X4060107)LB10,382$1.08$1.00$0.98
7Pavement patching SPL (X4420201)SY329$70.00$115.00$165.00
8Pipe culvert rem SPL (X5015225)LF6$100.00$110.00$175.00
9Traf cont-prot BLR 22 (X7011801)LS1$47,364$8,500.00$4,975.00
10HMA removal SPL (Z0004542)SY10,690$17.00$31.50$33.50
11Construction layout (Z0013798)LS1$15,000$8,875.00$11,200
12Seeding CL 1B (25000115)ACRE1.50$3,135.00$2,850.00$6,000.00
13Nitrogen fert nutr (25000400)LB135$3.30$3.00$4.00
14Phosphorus fert nutr (25000500)LB135$3.30$3.00$4.00
15Potassium fert nutr (25000600)LB135$3.30$3.00$4.00
16Mulch method 2 (25100115)ACRE1.50$3,850.00$3,500.00$6,000.00
17Earth exc - eros cont (28000200)CY21$50.00$150.00$72.00
18Temp eros contr seed (28000250)LB150$4.40$4.00$5.00
19Perimeter eros bar (28000400)LF5,116$2.48$2.25$3.50
20Inlet & pipe protect (28000500)EACH17$220.00$200.00$120.00
21Aggregate - eros cont (28001000)TON9$65.00$170.00$200.00
22Agg subgrade impr 12 (30300112)SY13,919$20.65$27.50$25.75
23Preparation of base (35800100)SY6,570$2.00$1.35$1.25
24Bit matls PR CT (40600275)LB31,318$0.01$1.10$0.01
25Bit matls tack CT (40600290)LB2,953$0.01$2.45$0.01
26Long joint sealant (40600370)LF5,271$4.35$2.50$5.50
27HMA BC IL-19.0 N50 (40603080)TON1,668$82.00$110.00$170.00
28HMA SC IL-9.5 C N50 (40604050)TON1,097$89.00$130.00$180.00
29Pipe culvert remov (50105220)LF558$20.00$50.00$31.50
30P cul CL A 1 15 (542A0220)LF30$100.00$88.50$134.00
31P cul CL A 1 48 (542A0253)LF94$255.00$185.00$264.00
32P cul CL A 1 54 (542A0259)LF129$299.00$240.00$385.00
33P cul CL A 1 eqrs 15 (542A5470)LF314$115.00$82.25$197.00
34PRC flar end sec 15 (54213660)EACH2$1,500.00$1,275.00$1,625.00
35PRC flar end sec 48 (54213693)EACH4$3,500.00$3,750.00$4,300.00
36PRC flar end sec 54 (54213699)EACH6$6,200.00$6,000.00$5,200.00
37PRC FL end S EQ RS 15 (54214500)EACH22$2,000.00$1,250.00$1,700.00
38Contr low-streng matl (59300100)CY139$300.00$200.00$295.00
39SPBGR TY A 6FT posts (63000001)LF600$32.08$44.00$42.00
40TR bar TRM T1 SPL tan (63100167)EACH2$3,676.20$5,500.00$3,900.00
41Engr field office A (67000400)CAL MO6$4,000.00$3,000.00$3,750.00
42Mobilization (67100100)LS1$97,800$97,350$115,000
43Sign panel T1 (72000100)SF30$27.50$37.50$25.00
44Terminal marker - DA (72501000)EACH2$38.50$50.00$40.00
45Wood sin support (73000100)LF57$27.50$65.00$25.00
46Grdrail ref type B (78200006)EACH9$13.20$41.50$24.00
IDOT contract 46937: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy