IDOT contract 61L20 bid tabulation
South Holland, section 22-00117-00-RS. Let by Illinois DOT on March 7, 2025, Cook, District 01. 2 bids received; low bid $413,449 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 47
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $413,449 | Low |
| 2 | Gallagher Asphalt Corporation | $469,959 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Gallagher Asphalt Corporation |
|---|---|---|---|---|---|
| 1 | Seeding CL 2A SPL (X2501020) | ACRE | 0.25 | $10,208 | $10,000 |
| 2 | Temp access- priv ent (X4021000) | EACH | 1 | $1,200.00 | $200.00 |
| 3 | Temp access- com ent (X4022000) | EACH | 16 | $1,500.00 | $285.00 |
| 4 | Aggregate SHLD removl (X4810200) | CY | 18 | $50.00 | $128.00 |
| 5 | FR & lids adjust SPL (X6030310) | EACH | 1 | $1,000.00 | $3,300.00 |
| 6 | HMA driveway pavt 8 (Z0004530) | SY | 1,391 | $45.00 | $81.00 |
| 7 | Drain util STR adj (Z0017400) | EACH | 4 | $1,000.00 | $1,000.00 |
| 8 | Drain util STR recon (Z0017700) | EACH | 1 | $2,000.00 | $1,900.00 |
| 9 | Temp info signing (Z0030850) | SF | 200 | $35.00 | $21.00 |
| 10 | Rem & disp uns matl (20201200) | CY | 15 | $65.00 | $90.00 |
| 11 | Topsoil F & P 4 (21101615) | SY | 741 | $13.48 | $3.00 |
| 12 | Agg subgrade improve (30300001) | CY | 15 | $60.00 | $124.00 |
| 13 | Agg base cse B 4 (35101600) | SY | 1,404 | $9.00 | $6.75 |
| 14 | Bit matls tack CT (40600290) | LB | 3,942 | $0.01 | $0.01 |
| 15 | Long joint sealant (40600370) | LF | 1,890 | $6.69 | $6.90 |
| 16 | Mix CR JTS flangewys (40600400) | TON | 9 | $0.01 | $400.00 |
| 17 | HMA surf rem butt JT (40600982) | SY | 80 | $0.01 | $15.50 |
| 18 | HMA BC IL-19.0 N50 (40603080) | TON | 736 | $95.00 | $92.00 |
| 19 | HMA SC IL-9.5 D N50 (40604060) | TON | 655 | $95.00 | $99.00 |
| 20 | PC conc sidewalk 5 (42400200) | SF | 115 | $18.00 | $26.00 |
| 21 | Detectable warnings (42400800) | SF | 40 | $40.00 | $87.00 |
| 22 | HMA surf rem 4 (44000165) | SY | 5,840 | $3.50 | $5.45 |
| 23 | Drive pavement rem (44000200) | SY | 1,406 | $15.00 | $25.50 |
| 24 | Sidewalk rem (44000600) | SF | 115 | $5.00 | $11.00 |
| 25 | CL D patch T2 4 (44201692) | SY | 59 | $75.00 | $170.00 |
| 26 | CL D patch T3 4 (44201694) | SY | 22 | $75.00 | $155.00 |
| 27 | Aggregate SHLDS B 4 (48101498) | SY | 159 | $8.50 | $39.00 |
| 28 | Valve box adj (60266600) | EACH | 3 | $600.00 | $950.00 |
| 29 | Guardrail remov (63200310) | LF | 118 | $20.00 | $27.00 |
| 30 | Non SPL waste disposl (66900200) | CY | 10 | $120.00 | $130.00 |
| 31 | Soil disposal analy (66900530) | EACH | 1 | $1,815.00 | $2,100.00 |
| 32 | Reg sub P-const plan (66901001) | LS | 1 | $2,475.00 | $2,400.00 |
| 33 | Reg sub F con report (66901003) | LS | 1 | $2,475.00 | $2,200.00 |
| 34 | Reg sub mon (66901006) | CAL DAY | 4 | $1,045.00 | $1,050.00 |
| 35 | Mobilization (67100100) | LS | 1 | $24,800 | $28,150 |
| 36 | TR cont & prot 701501 (70102620) | LS | 1 | $22,260 | $5,500.00 |
| 37 | TR cont & prot 701801 (70102640) | LS | 1 | $0.01 | $100.00 |
| 38 | Changeable message SN (70107025) | CAL DAY | 60 | $100.00 | $41.00 |
| 39 | Short term pavt mking (70300100) | LF | 600 | $2.00 | $6.00 |
| 40 | SHRT TRM pavt MK rem (70300150) | SF | 200 | $5.00 | $0.01 |
| 41 | Sign panel T1 (72000100) | SF | 99 | $27.50 | $26.00 |
| 42 | Remov sin pan assy TA (72400100) | EACH | 8 | $82.50 | $77.00 |
| 43 | Remov sin pan assy TB (72400200) | EACH | 1 | $99.00 | $92.00 |
| 44 | Teles STL sin support (72800100) | LF | 199 | $16.50 | $16.00 |
| 45 | THPL PVT MK line 4 (78000200) | LF | 7,040 | $0.94 | $1.20 |
| 46 | THPL PVT MK line 12 (78000600) | LF | 84 | $2.86 | $3.35 |
| 47 | THPL PVT MK line 24 (78000650) | LF | 80 | $6.05 | $7.95 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.