IDOT contract 61L47 bid tabulation

West Chicago, section 20-00084-00-CH. Let by Illinois DOT on August 1, 2025, Dupage, District 01. 5 bids received; low bid $1,807,185 by Everlast Blacktop Inc..

Owner
Illinois DOT
Letting
01 AUG 2025
Pay items
132
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Everlast Blacktop Inc.$1,807,185Low
2Schroeder Asphalt Services, Inc.$2,019,656+12%
3Alliance Contractors, Inc.$2,054,889+14%
4Plote Construction, Inc.$2,181,976+21%
5A Lamp Concrete Contractors, Inc.$2,374,977+31%
IDOT contract 61L47: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Everlast Blacktop Inc.2. Schroeder Asphalt Services, Inc.3. Alliance Contractors, Inc.4. Plote Construction, Inc.5. A Lamp Concrete Contractors, Inc.
1T-betula nigra 2-1/2 (A2002320)EACH3$900.00$770.00$950.00$950.00$795.00
2T-celtis occid 2 (A2002916)EACH5$900.00$770.00$925.00$925.00$585.00
3T-platanus occ 2 (A2005816)EACH5$900.00$715.00$925.00$925.00$795.00
4T-quercus bicol 2 (A2006516)EACH1$975.00$770.00$950.00$950.00$585.00
5S-amoupha fruit CG 3G (C2C003G3)EACH10$300.00$100.00$75.00$75.00$126.00
6S-cornus obliq CG 3G (C2C015G3)EACH7$300.00$100.00$75.00$75.00$135.00
7S-sambucus canad 3'C (C2C09636)EACH8$300.00$100.00$100.00$100.00$114.00
8S-viburn lentag CG 5G (C2C100G5)EACH6$350.00$100.00$75.00$75.00$114.00
9S-cephalan occi CG 5G (C2001162)EACH9$300.00$100.00$90.00$90.00$105.00
10P PL wetlnd 2X4 DPPLG (K0013030)UNIT4.50$1,444.00$770.00$1,900.00$1,900.00$2,000.00
11Seeding sedge MDW mix (K1005428)ACRE0.30$11,000$14,500$9,680.00$9,680.00$8,500.00
12Mat stream bed est 24 (XX009719)SY379$105.50$200.00$119.50$150.00$170.00
13Monitoring well (XX009720)EACH1$4,500.00$5,200.00$1,200.00$4,500.00$3,600.00
14In stream work plan (XX009721)LS1$1,000.00$23,000$1.00$1,000.00$2,500.00
15Emergent seed mix (XX009722)ACRE0.10$26,000$16,500$10,000$10,000$9,000.00
16Low prof praire seed (XX009723)ACRE0.20$24,000$16,500$10,000$10,000$8,900.00
17Cip end sec ers 42 SP (XX009724)EACH1$6,900.00$7,300.00$46,000$6,550.00$25,000
18Washout basin (X0326806)LS1$2,000.00$1,000.00$750.00$1,500.00$1,000.00
19Mowing SPL (X2503110)ACRE50$450.00$60.00$1.00$1.00$190.00
20Perimeter eros bar SP (X2800400)LF260$4.00$11.00$10.00$10.00$10.00
21Temp access- com ent (X4022000)EACH1$800.00$200.00$1.00$350.00$500.00
22HMA driveway pavt 10 (X4060294)SY69$100.80$120.00$130.00$300.00$79.00
23PC conc sidewalk 5 SP (X4240430)SF3,349$14.00$15.00$21.05$13.50$12.00
24Detectable warn SPL (X4240800)SF146$69.00$50.00$40.00$45.00$35.00
25Dewatering (X5021507)LS1$15,000$12,000$1.00$5,000.00$51,000
26Cofferdam typ 1 IS WW (X5021512)EACH1$15,000$9,500.00$1.00$1,000.00$24,500
27Man TA 10 dia T1F CL (X6022110)EACH2$18,920$28,500$40,000$26,255$37,300
28Comb CC&G TB6.12 SPL (X6064200)LF3,081$38.00$55.00$74.75$50.00$51.50
29Temp constr fence (X6640638)LF2,375$6.00$30.00$27.33$27.33$5.00
30Traf cont & prot SPL (X7010216)LS1$65,286$50,000$105,500$180,000$332,825
31Temp info signing (X7200061)SF90$30.00$27.50$20.00$12.00$25.00
32Temp TR signal timing (X8900104)EACH1$800.00$1,250.00$600.00$600.00$600.00
33Stab constr entrance (Z0013797)SY69$35.00$18.00$45.00$70.00$25.00
34Construction layout (Z0013798)LS1$8,000.00$20,000$14,900$25,000$14,900
35RR prot liability ins (Z0048665)LS1$5,000.00$4,000.00$5,000.00$7,500.00$5,000.00
36Temp pavement (Z0062456)SY727$90.60$80.00$78.25$35.00$43.00
37Trainees (Z0076600)HR500$0.80$0.80$0.80$0.80$0.80
38Trainees TPG (Z0076604)HR500$15.00$15.00$15.00$15.00$15.00
39Tree remov 6-15 (20100110)UNIT379$17.50$16.00$14.50$16.00$14.50
40Tree remov over 15 (20100210)UNIT501$19.00$19.00$16.45$20.00$16.45
41Temporary fence (20101000)LF800$10.00$5.65$4.00$4.00$1.00
42Tree root pruning (20101200)EACH10$140.00$130.00$95.00$95.00$95.00
43Earth excavation (20200100)CY2,581$45.00$46.00$50.00$55.00$77.00
44Rem & disp uns matl (20201200)CY477$45.00$55.00$10.00$85.00$40.00
45Porous gran embank (20700220)CY28$58.00$60.00$76.00$90.00$160.00
46Trench backfill (20800150)CY183$58.00$26.00$50.00$23.00$60.00
47Geotech fab F/GR stab (21001000)SY717$2.00$3.00$1.00$5.50$3.00
48Topsoil F & P 4 (21101615)SY4,600$5.14$8.80$4.50$4.50$8.00
49Seeding CL 2A (25000210)ACRE0.50$2,500.00$6,000.00$4,840.00$4,840.00$2,400.00
50Seeding CL 4 (25000310)ACRE0.20$2,800.00$5,600.00$4,840.00$4,840.00$5,000.00
51Nitrogen fert nutr (25000400)LB37$1.00$3.50$1.00$1.00$4.00
52Potassium fert nutr (25000600)LB37$1.00$3.50$1.00$1.00$4.00
53Wildlife friendly ecb (25100645)SY4,600$3.00$3.40$3.00$3.00$1.80
54Supple watering (25200200)UNIT40$1.00$170.00$0.10$0.10$0.25
55Temp eros contr seed (28000250)LB96$1.00$11.50$0.10$0.10$3.75
56Temp ditch checks (28000305)LF20$18.00$13.50$150.00$150.00$25.00
57Perimeter eros bar (28000400)LF1,219$2.40$5.70$3.00$3.00$5.00
58Inlet filters (28000510)EACH30$170.00$220.00$25.00$200.00$15.00
59Temp eros contr blank (28001100)SY4,600$2.00$1.15$0.10$0.10$0.90
60Stone riprap CL A3 (28100105)SY36$95.00$275.00$200.00$245.00$114.00
61Filter fabric (28200200)SY36$2.00$10.00$1.00$6.00$7.75
62Agg subgrade improve (30300001)CY1,066$58.00$59.00$50.00$75.00$40.00
63Agg subgrade impr 12 (30300112)SY2,893$18.40$20.35$29.50$32.00$31.00
64Sub gran mat B 4 (31101200)SY477$5.12$9.50$10.00$18.00$12.50
65Bit matls PR CT (40600275)LB5,755$0.01$0.01$0.01$0.01$0.01
66Bit matls tack CT (40600290)LB8,310$0.01$0.01$0.01$0.01$0.01
67Long joint sealant (40600370)LF4,401$5.70$6.20$5.27$6.60$5.27
68Mix CR JTS flangewys (40600400)TON52$138.00$300.00$325.00$150.00$150.00
69HMA surf rem butt JT (40600982)SY163$22.00$12.00$15.00$10.39$26.00
70HMA BC IL-19.0 N50 (40603080)TON1,177$93.10$87.00$89.00$102.00$99.00
71P HMA BC IL-4.75 N50 (40603200)TON518$116.67$125.00$135.00$140.00$142.00
72HMA SC IL-9.5 D N50 (40604060)TON1,321$84.46$90.00$90.00$100.00$105.00
73PCC driveway pavt 6 (42300200)SY30$141.00$165.00$107.00$150.00$124.00
74Pavement rem (44000100)SY1,914$14.00$11.50$20.00$19.50$22.50
75HMA surf rem 2 (44000157)SY12,311$2.70$3.00$2.15$4.10$2.65
76Drive pavement rem (44000200)SY69$18.00$45.00$20.00$40.00$21.00
77Curb rem (44000300)LF20$9.00$14.00$15.00$12.00$13.75
78Comb curb gutter rem (44000500)LF2,009$8.00$10.00$15.00$9.00$9.50
79Sidewalk rem (44000600)SF2,267$2.00$4.75$2.00$4.00$2.25
80Conc barrier remov (44001980)LF31$38.00$100.00$10.00$48.00$35.50
81CL D patch T1 8 (44201737)SY622$82.00$84.00$83.00$75.00$50.00
82CL D patch T2 8 (44201741)SY498$82.00$84.00$82.00$75.00$40.00
83CL D patch T3 8 (44201745)SY415$82.00$82.00$81.00$75.00$40.00
84Conc headwall removal (50104400)EACH1$6,500.00$500.00$2,000.00$386.00$6,400.00
85Pipe culvert remov (50105220)LF90$70.00$11.00$20.00$386.00$14.00
86P cul CL A 1 eqrs 42 (542A5497)LF4$500.00$4,200.00$578.00$3,885.00$2,060.00
87P cul spec 12 (54205047)LF100$125.00$205.00$124.00$185.00$168.00
88PRC FL end S EQ RS 54 (54214539)EACH1$13,950$7,500.00$8,500.00$6,850.00$12,950
89Storm sew CL A 1 12 (550A0050)LF29$150.00$185.00$120.00$165.00$155.00
90Storm sew CL A 1 15 (550A0070)LF112$160.00$195.00$133.00$170.00$184.00
91SS CL A 1 eqrs 54 (550A4720)LF46$540.00$585.00$477.50$525.00$786.00
92Storm sewer rem 54 (55102000)LF92$80.00$11.50$20.00$10.00$50.00
93Pipe underdr T 2 4 (60108204)LF200$58.00$52.00$26.50$47.00$71.00
94CB TA 4 dia T1F OL (60200105)EACH1$4,900.00$6,800.00$6,800.00$6,125.00$5,700.00
95Man TA 4 dia T1F CL (60218400)EACH1$4,900.00$5,400.00$7,100.00$4,885.00$6,000.00
96Inlets TA T11F&G (60236800)EACH1$3,000.00$2,425.00$4,300.00$2,125.00$3,800.00
97CB adj new T1F OL (60250400)EACH7$850.00$1,250.00$1,000.00$1,125.00$1,225.00
98Inlets adj new T1F CL (60260400)EACH2$800.00$1,250.00$1,000.00$1,125.00$1,275.00
99SPBGR TY A 6FT posts (63000001)LF225$30.00$34.00$30.11$30.11$49.00
100TR bar TRM T1 SPL tan (63100167)EACH2$4,900.00$3,500.00$3,131.00$3,131.00$4,200.00
101Non SPL waste disposl (66900200)CY20$100.00$110.00$98.00$225.00$110.00
102Soil disposal analy (66900530)EACH1$3,000.00$1,700.00$1,500.00$1,500.00$1,500.00
103Reg sub P-const plan (66901001)LS1$3,200.00$4,400.00$4,000.00$3,400.00$3,400.00
104Reg sub F con report (66901003)LS1$3,200.00$600.00$500.00$500.00$500.00
105Reg sub mon (66901006)CAL DAY5$1,250.00$800.00$725.00$750.00$750.00
106Engr field office A (67000400)CAL MO6$2,500.00$4,000.00$500.00$4,500.00$2,500.00
107Mobilization (67100100)LS1$102,294$68,000$125,400$129,000$142,450
108Changeable message SN (70107025)CAL DAY360$38.00$45.00$30.00$22.00$1.00
109Short term pavt mking (70300100)LF423$6.00$3.00$4.00$6.50$1.00
110SHRT TRM pavt MK rem (70300150)SF1,542$1.10$4.00$0.01$6.40$1.00
111Temp PVT MK LTR & sym T4 tape (70307100)SF221$7.70$5.00$7.75$3.45$3.00
112Temp PVT MK L4 T4 tape (70307120)LF1,562$2.95$2.00$1.35$1.18$1.00
113Temp PVT MK L6 T4 tape (70307130)LF327$3.30$2.50$2.05$1.75$1.25
114Temp PVT MK L12 T4 tape (70307160)LF277$5.50$5.00$4.10$3.45$1.50
115Temp PVT MK L24 T4 tape (70307210)LF109$7.70$9.00$7.75$6.90$2.00
116Temp conc barrier (70400100)LF588$24.00$80.00$41.00$32.50$42.00
117Rel temp conc barrier (70400200)LF588$14.00$10.00$12.00$5.85$16.00
118Imp attn temp FRN TL2 (70600255)EACH2$6,800.00$4,950.00$4,316.00$4,316.00$32,000
119Imp attn rel FRN TL2 (70600322)EACH2$3,600.00$2,650.00$2,294.00$2,294.00$3,000.00
120Sign panel T1 (72000100)SF93$57.00$35.00$40.00$23.00$25.00
121Remov sin pan assy TA (72400100)EACH3$169.00$85.00$100.00$75.00$250.00
122Rem & rel sign panel asmbly TA (72400205)EACH3$360.00$450.00$225.00$125.00$500.00
123Remov sign panel T1 (72400310)SF19$44.00$25.00$40.00$10.00$15.00
124Terminal marker - DA (72501000)EACH2$60.00$300.00$30.00$30.00$50.00
125Teles STL sin support (72800100)LF560$19.20$19.50$20.00$7.00$20.00
126THPL PVT MK LTR & sym (78000100)SF221$6.00$6.00$5.25$5.25$7.00
127THPL PVT MK line 4 (78000200)LF1,562$1.45$1.50$1.35$1.35$1.60
128THPL PVT MK line 6 (78000400)LF327$2.88$3.30$2.85$2.85$2.35
129THPL PVT MK line 12 (78000600)LF277$5.75$6.00$5.25$5.25$4.75
130THPL PVT MK line 24 (78000650)LF109$11.00$11.00$10.00$10.00$7.00
131Raised refl pavt MKR (78100100)EACH33$104.00$110.00$98.00$98.00$146.25
132Grdrail ref type A (78200005)EACH3$40.00$12.00$10.00$10.00$33.00
IDOT contract 61L47: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy