IDOT contract 61L47 bid tabulation
West Chicago, section 20-00084-00-CH. Let by Illinois DOT on August 1, 2025, Dupage, District 01. 5 bids received; low bid $1,807,185 by Everlast Blacktop Inc..
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 132
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Everlast Blacktop Inc. | $1,807,185 | Low |
| 2 | Schroeder Asphalt Services, Inc. | $2,019,656 | +12% |
| 3 | Alliance Contractors, Inc. | $2,054,889 | +14% |
| 4 | Plote Construction, Inc. | $2,181,976 | +21% |
| 5 | A Lamp Concrete Contractors, Inc. | $2,374,977 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Everlast Blacktop Inc. | 2. Schroeder Asphalt Services, Inc. | 3. Alliance Contractors, Inc. | 4. Plote Construction, Inc. | 5. A Lamp Concrete Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | T-betula nigra 2-1/2 (A2002320) | EACH | 3 | $900.00 | $770.00 | $950.00 | $950.00 | $795.00 |
| 2 | T-celtis occid 2 (A2002916) | EACH | 5 | $900.00 | $770.00 | $925.00 | $925.00 | $585.00 |
| 3 | T-platanus occ 2 (A2005816) | EACH | 5 | $900.00 | $715.00 | $925.00 | $925.00 | $795.00 |
| 4 | T-quercus bicol 2 (A2006516) | EACH | 1 | $975.00 | $770.00 | $950.00 | $950.00 | $585.00 |
| 5 | S-amoupha fruit CG 3G (C2C003G3) | EACH | 10 | $300.00 | $100.00 | $75.00 | $75.00 | $126.00 |
| 6 | S-cornus obliq CG 3G (C2C015G3) | EACH | 7 | $300.00 | $100.00 | $75.00 | $75.00 | $135.00 |
| 7 | S-sambucus canad 3'C (C2C09636) | EACH | 8 | $300.00 | $100.00 | $100.00 | $100.00 | $114.00 |
| 8 | S-viburn lentag CG 5G (C2C100G5) | EACH | 6 | $350.00 | $100.00 | $75.00 | $75.00 | $114.00 |
| 9 | S-cephalan occi CG 5G (C2001162) | EACH | 9 | $300.00 | $100.00 | $90.00 | $90.00 | $105.00 |
| 10 | P PL wetlnd 2X4 DPPLG (K0013030) | UNIT | 4.50 | $1,444.00 | $770.00 | $1,900.00 | $1,900.00 | $2,000.00 |
| 11 | Seeding sedge MDW mix (K1005428) | ACRE | 0.30 | $11,000 | $14,500 | $9,680.00 | $9,680.00 | $8,500.00 |
| 12 | Mat stream bed est 24 (XX009719) | SY | 379 | $105.50 | $200.00 | $119.50 | $150.00 | $170.00 |
| 13 | Monitoring well (XX009720) | EACH | 1 | $4,500.00 | $5,200.00 | $1,200.00 | $4,500.00 | $3,600.00 |
| 14 | In stream work plan (XX009721) | LS | 1 | $1,000.00 | $23,000 | $1.00 | $1,000.00 | $2,500.00 |
| 15 | Emergent seed mix (XX009722) | ACRE | 0.10 | $26,000 | $16,500 | $10,000 | $10,000 | $9,000.00 |
| 16 | Low prof praire seed (XX009723) | ACRE | 0.20 | $24,000 | $16,500 | $10,000 | $10,000 | $8,900.00 |
| 17 | Cip end sec ers 42 SP (XX009724) | EACH | 1 | $6,900.00 | $7,300.00 | $46,000 | $6,550.00 | $25,000 |
| 18 | Washout basin (X0326806) | LS | 1 | $2,000.00 | $1,000.00 | $750.00 | $1,500.00 | $1,000.00 |
| 19 | Mowing SPL (X2503110) | ACRE | 50 | $450.00 | $60.00 | $1.00 | $1.00 | $190.00 |
| 20 | Perimeter eros bar SP (X2800400) | LF | 260 | $4.00 | $11.00 | $10.00 | $10.00 | $10.00 |
| 21 | Temp access- com ent (X4022000) | EACH | 1 | $800.00 | $200.00 | $1.00 | $350.00 | $500.00 |
| 22 | HMA driveway pavt 10 (X4060294) | SY | 69 | $100.80 | $120.00 | $130.00 | $300.00 | $79.00 |
| 23 | PC conc sidewalk 5 SP (X4240430) | SF | 3,349 | $14.00 | $15.00 | $21.05 | $13.50 | $12.00 |
| 24 | Detectable warn SPL (X4240800) | SF | 146 | $69.00 | $50.00 | $40.00 | $45.00 | $35.00 |
| 25 | Dewatering (X5021507) | LS | 1 | $15,000 | $12,000 | $1.00 | $5,000.00 | $51,000 |
| 26 | Cofferdam typ 1 IS WW (X5021512) | EACH | 1 | $15,000 | $9,500.00 | $1.00 | $1,000.00 | $24,500 |
| 27 | Man TA 10 dia T1F CL (X6022110) | EACH | 2 | $18,920 | $28,500 | $40,000 | $26,255 | $37,300 |
| 28 | Comb CC&G TB6.12 SPL (X6064200) | LF | 3,081 | $38.00 | $55.00 | $74.75 | $50.00 | $51.50 |
| 29 | Temp constr fence (X6640638) | LF | 2,375 | $6.00 | $30.00 | $27.33 | $27.33 | $5.00 |
| 30 | Traf cont & prot SPL (X7010216) | LS | 1 | $65,286 | $50,000 | $105,500 | $180,000 | $332,825 |
| 31 | Temp info signing (X7200061) | SF | 90 | $30.00 | $27.50 | $20.00 | $12.00 | $25.00 |
| 32 | Temp TR signal timing (X8900104) | EACH | 1 | $800.00 | $1,250.00 | $600.00 | $600.00 | $600.00 |
| 33 | Stab constr entrance (Z0013797) | SY | 69 | $35.00 | $18.00 | $45.00 | $70.00 | $25.00 |
| 34 | Construction layout (Z0013798) | LS | 1 | $8,000.00 | $20,000 | $14,900 | $25,000 | $14,900 |
| 35 | RR prot liability ins (Z0048665) | LS | 1 | $5,000.00 | $4,000.00 | $5,000.00 | $7,500.00 | $5,000.00 |
| 36 | Temp pavement (Z0062456) | SY | 727 | $90.60 | $80.00 | $78.25 | $35.00 | $43.00 |
| 37 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 38 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 39 | Tree remov 6-15 (20100110) | UNIT | 379 | $17.50 | $16.00 | $14.50 | $16.00 | $14.50 |
| 40 | Tree remov over 15 (20100210) | UNIT | 501 | $19.00 | $19.00 | $16.45 | $20.00 | $16.45 |
| 41 | Temporary fence (20101000) | LF | 800 | $10.00 | $5.65 | $4.00 | $4.00 | $1.00 |
| 42 | Tree root pruning (20101200) | EACH | 10 | $140.00 | $130.00 | $95.00 | $95.00 | $95.00 |
| 43 | Earth excavation (20200100) | CY | 2,581 | $45.00 | $46.00 | $50.00 | $55.00 | $77.00 |
| 44 | Rem & disp uns matl (20201200) | CY | 477 | $45.00 | $55.00 | $10.00 | $85.00 | $40.00 |
| 45 | Porous gran embank (20700220) | CY | 28 | $58.00 | $60.00 | $76.00 | $90.00 | $160.00 |
| 46 | Trench backfill (20800150) | CY | 183 | $58.00 | $26.00 | $50.00 | $23.00 | $60.00 |
| 47 | Geotech fab F/GR stab (21001000) | SY | 717 | $2.00 | $3.00 | $1.00 | $5.50 | $3.00 |
| 48 | Topsoil F & P 4 (21101615) | SY | 4,600 | $5.14 | $8.80 | $4.50 | $4.50 | $8.00 |
| 49 | Seeding CL 2A (25000210) | ACRE | 0.50 | $2,500.00 | $6,000.00 | $4,840.00 | $4,840.00 | $2,400.00 |
| 50 | Seeding CL 4 (25000310) | ACRE | 0.20 | $2,800.00 | $5,600.00 | $4,840.00 | $4,840.00 | $5,000.00 |
| 51 | Nitrogen fert nutr (25000400) | LB | 37 | $1.00 | $3.50 | $1.00 | $1.00 | $4.00 |
| 52 | Potassium fert nutr (25000600) | LB | 37 | $1.00 | $3.50 | $1.00 | $1.00 | $4.00 |
| 53 | Wildlife friendly ecb (25100645) | SY | 4,600 | $3.00 | $3.40 | $3.00 | $3.00 | $1.80 |
| 54 | Supple watering (25200200) | UNIT | 40 | $1.00 | $170.00 | $0.10 | $0.10 | $0.25 |
| 55 | Temp eros contr seed (28000250) | LB | 96 | $1.00 | $11.50 | $0.10 | $0.10 | $3.75 |
| 56 | Temp ditch checks (28000305) | LF | 20 | $18.00 | $13.50 | $150.00 | $150.00 | $25.00 |
| 57 | Perimeter eros bar (28000400) | LF | 1,219 | $2.40 | $5.70 | $3.00 | $3.00 | $5.00 |
| 58 | Inlet filters (28000510) | EACH | 30 | $170.00 | $220.00 | $25.00 | $200.00 | $15.00 |
| 59 | Temp eros contr blank (28001100) | SY | 4,600 | $2.00 | $1.15 | $0.10 | $0.10 | $0.90 |
| 60 | Stone riprap CL A3 (28100105) | SY | 36 | $95.00 | $275.00 | $200.00 | $245.00 | $114.00 |
| 61 | Filter fabric (28200200) | SY | 36 | $2.00 | $10.00 | $1.00 | $6.00 | $7.75 |
| 62 | Agg subgrade improve (30300001) | CY | 1,066 | $58.00 | $59.00 | $50.00 | $75.00 | $40.00 |
| 63 | Agg subgrade impr 12 (30300112) | SY | 2,893 | $18.40 | $20.35 | $29.50 | $32.00 | $31.00 |
| 64 | Sub gran mat B 4 (31101200) | SY | 477 | $5.12 | $9.50 | $10.00 | $18.00 | $12.50 |
| 65 | Bit matls PR CT (40600275) | LB | 5,755 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 66 | Bit matls tack CT (40600290) | LB | 8,310 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 67 | Long joint sealant (40600370) | LF | 4,401 | $5.70 | $6.20 | $5.27 | $6.60 | $5.27 |
| 68 | Mix CR JTS flangewys (40600400) | TON | 52 | $138.00 | $300.00 | $325.00 | $150.00 | $150.00 |
| 69 | HMA surf rem butt JT (40600982) | SY | 163 | $22.00 | $12.00 | $15.00 | $10.39 | $26.00 |
| 70 | HMA BC IL-19.0 N50 (40603080) | TON | 1,177 | $93.10 | $87.00 | $89.00 | $102.00 | $99.00 |
| 71 | P HMA BC IL-4.75 N50 (40603200) | TON | 518 | $116.67 | $125.00 | $135.00 | $140.00 | $142.00 |
| 72 | HMA SC IL-9.5 D N50 (40604060) | TON | 1,321 | $84.46 | $90.00 | $90.00 | $100.00 | $105.00 |
| 73 | PCC driveway pavt 6 (42300200) | SY | 30 | $141.00 | $165.00 | $107.00 | $150.00 | $124.00 |
| 74 | Pavement rem (44000100) | SY | 1,914 | $14.00 | $11.50 | $20.00 | $19.50 | $22.50 |
| 75 | HMA surf rem 2 (44000157) | SY | 12,311 | $2.70 | $3.00 | $2.15 | $4.10 | $2.65 |
| 76 | Drive pavement rem (44000200) | SY | 69 | $18.00 | $45.00 | $20.00 | $40.00 | $21.00 |
| 77 | Curb rem (44000300) | LF | 20 | $9.00 | $14.00 | $15.00 | $12.00 | $13.75 |
| 78 | Comb curb gutter rem (44000500) | LF | 2,009 | $8.00 | $10.00 | $15.00 | $9.00 | $9.50 |
| 79 | Sidewalk rem (44000600) | SF | 2,267 | $2.00 | $4.75 | $2.00 | $4.00 | $2.25 |
| 80 | Conc barrier remov (44001980) | LF | 31 | $38.00 | $100.00 | $10.00 | $48.00 | $35.50 |
| 81 | CL D patch T1 8 (44201737) | SY | 622 | $82.00 | $84.00 | $83.00 | $75.00 | $50.00 |
| 82 | CL D patch T2 8 (44201741) | SY | 498 | $82.00 | $84.00 | $82.00 | $75.00 | $40.00 |
| 83 | CL D patch T3 8 (44201745) | SY | 415 | $82.00 | $82.00 | $81.00 | $75.00 | $40.00 |
| 84 | Conc headwall removal (50104400) | EACH | 1 | $6,500.00 | $500.00 | $2,000.00 | $386.00 | $6,400.00 |
| 85 | Pipe culvert remov (50105220) | LF | 90 | $70.00 | $11.00 | $20.00 | $386.00 | $14.00 |
| 86 | P cul CL A 1 eqrs 42 (542A5497) | LF | 4 | $500.00 | $4,200.00 | $578.00 | $3,885.00 | $2,060.00 |
| 87 | P cul spec 12 (54205047) | LF | 100 | $125.00 | $205.00 | $124.00 | $185.00 | $168.00 |
| 88 | PRC FL end S EQ RS 54 (54214539) | EACH | 1 | $13,950 | $7,500.00 | $8,500.00 | $6,850.00 | $12,950 |
| 89 | Storm sew CL A 1 12 (550A0050) | LF | 29 | $150.00 | $185.00 | $120.00 | $165.00 | $155.00 |
| 90 | Storm sew CL A 1 15 (550A0070) | LF | 112 | $160.00 | $195.00 | $133.00 | $170.00 | $184.00 |
| 91 | SS CL A 1 eqrs 54 (550A4720) | LF | 46 | $540.00 | $585.00 | $477.50 | $525.00 | $786.00 |
| 92 | Storm sewer rem 54 (55102000) | LF | 92 | $80.00 | $11.50 | $20.00 | $10.00 | $50.00 |
| 93 | Pipe underdr T 2 4 (60108204) | LF | 200 | $58.00 | $52.00 | $26.50 | $47.00 | $71.00 |
| 94 | CB TA 4 dia T1F OL (60200105) | EACH | 1 | $4,900.00 | $6,800.00 | $6,800.00 | $6,125.00 | $5,700.00 |
| 95 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $4,900.00 | $5,400.00 | $7,100.00 | $4,885.00 | $6,000.00 |
| 96 | Inlets TA T11F&G (60236800) | EACH | 1 | $3,000.00 | $2,425.00 | $4,300.00 | $2,125.00 | $3,800.00 |
| 97 | CB adj new T1F OL (60250400) | EACH | 7 | $850.00 | $1,250.00 | $1,000.00 | $1,125.00 | $1,225.00 |
| 98 | Inlets adj new T1F CL (60260400) | EACH | 2 | $800.00 | $1,250.00 | $1,000.00 | $1,125.00 | $1,275.00 |
| 99 | SPBGR TY A 6FT posts (63000001) | LF | 225 | $30.00 | $34.00 | $30.11 | $30.11 | $49.00 |
| 100 | TR bar TRM T1 SPL tan (63100167) | EACH | 2 | $4,900.00 | $3,500.00 | $3,131.00 | $3,131.00 | $4,200.00 |
| 101 | Non SPL waste disposl (66900200) | CY | 20 | $100.00 | $110.00 | $98.00 | $225.00 | $110.00 |
| 102 | Soil disposal analy (66900530) | EACH | 1 | $3,000.00 | $1,700.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 103 | Reg sub P-const plan (66901001) | LS | 1 | $3,200.00 | $4,400.00 | $4,000.00 | $3,400.00 | $3,400.00 |
| 104 | Reg sub F con report (66901003) | LS | 1 | $3,200.00 | $600.00 | $500.00 | $500.00 | $500.00 |
| 105 | Reg sub mon (66901006) | CAL DAY | 5 | $1,250.00 | $800.00 | $725.00 | $750.00 | $750.00 |
| 106 | Engr field office A (67000400) | CAL MO | 6 | $2,500.00 | $4,000.00 | $500.00 | $4,500.00 | $2,500.00 |
| 107 | Mobilization (67100100) | LS | 1 | $102,294 | $68,000 | $125,400 | $129,000 | $142,450 |
| 108 | Changeable message SN (70107025) | CAL DAY | 360 | $38.00 | $45.00 | $30.00 | $22.00 | $1.00 |
| 109 | Short term pavt mking (70300100) | LF | 423 | $6.00 | $3.00 | $4.00 | $6.50 | $1.00 |
| 110 | SHRT TRM pavt MK rem (70300150) | SF | 1,542 | $1.10 | $4.00 | $0.01 | $6.40 | $1.00 |
| 111 | Temp PVT MK LTR & sym T4 tape (70307100) | SF | 221 | $7.70 | $5.00 | $7.75 | $3.45 | $3.00 |
| 112 | Temp PVT MK L4 T4 tape (70307120) | LF | 1,562 | $2.95 | $2.00 | $1.35 | $1.18 | $1.00 |
| 113 | Temp PVT MK L6 T4 tape (70307130) | LF | 327 | $3.30 | $2.50 | $2.05 | $1.75 | $1.25 |
| 114 | Temp PVT MK L12 T4 tape (70307160) | LF | 277 | $5.50 | $5.00 | $4.10 | $3.45 | $1.50 |
| 115 | Temp PVT MK L24 T4 tape (70307210) | LF | 109 | $7.70 | $9.00 | $7.75 | $6.90 | $2.00 |
| 116 | Temp conc barrier (70400100) | LF | 588 | $24.00 | $80.00 | $41.00 | $32.50 | $42.00 |
| 117 | Rel temp conc barrier (70400200) | LF | 588 | $14.00 | $10.00 | $12.00 | $5.85 | $16.00 |
| 118 | Imp attn temp FRN TL2 (70600255) | EACH | 2 | $6,800.00 | $4,950.00 | $4,316.00 | $4,316.00 | $32,000 |
| 119 | Imp attn rel FRN TL2 (70600322) | EACH | 2 | $3,600.00 | $2,650.00 | $2,294.00 | $2,294.00 | $3,000.00 |
| 120 | Sign panel T1 (72000100) | SF | 93 | $57.00 | $35.00 | $40.00 | $23.00 | $25.00 |
| 121 | Remov sin pan assy TA (72400100) | EACH | 3 | $169.00 | $85.00 | $100.00 | $75.00 | $250.00 |
| 122 | Rem & rel sign panel asmbly TA (72400205) | EACH | 3 | $360.00 | $450.00 | $225.00 | $125.00 | $500.00 |
| 123 | Remov sign panel T1 (72400310) | SF | 19 | $44.00 | $25.00 | $40.00 | $10.00 | $15.00 |
| 124 | Terminal marker - DA (72501000) | EACH | 2 | $60.00 | $300.00 | $30.00 | $30.00 | $50.00 |
| 125 | Teles STL sin support (72800100) | LF | 560 | $19.20 | $19.50 | $20.00 | $7.00 | $20.00 |
| 126 | THPL PVT MK LTR & sym (78000100) | SF | 221 | $6.00 | $6.00 | $5.25 | $5.25 | $7.00 |
| 127 | THPL PVT MK line 4 (78000200) | LF | 1,562 | $1.45 | $1.50 | $1.35 | $1.35 | $1.60 |
| 128 | THPL PVT MK line 6 (78000400) | LF | 327 | $2.88 | $3.30 | $2.85 | $2.85 | $2.35 |
| 129 | THPL PVT MK line 12 (78000600) | LF | 277 | $5.75 | $6.00 | $5.25 | $5.25 | $4.75 |
| 130 | THPL PVT MK line 24 (78000650) | LF | 109 | $11.00 | $11.00 | $10.00 | $10.00 | $7.00 |
| 131 | Raised refl pavt MKR (78100100) | EACH | 33 | $104.00 | $110.00 | $98.00 | $98.00 | $146.25 |
| 132 | Grdrail ref type A (78200005) | EACH | 3 | $40.00 | $12.00 | $10.00 | $10.00 | $33.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.