IDOT contract 61L52 bid tabulation
Round Lake, section 21-00085-00-BT. Let by Illinois DOT on June 13, 2025, Lake, District 01. 2 bids received; low bid $521,885 by Alliance Contractors, Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 58
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Alliance Contractors, Inc. | $521,885 | Low |
| 2 | Campanella and Sons, Inc. | $672,482 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alliance Contractors, Inc. | 2. Campanella and Sons, Inc. |
|---|---|---|---|---|---|
| 1 | Detectable warn SPL (X4240800) | SF | 97 | $40.00 | $85.00 |
| 2 | CC&G RMVL repl > 10FT (X4400503) | LF | 78 | $200.00 | $75.00 |
| 3 | Temp info signing (X7200061) | SF | 86 | $20.00 | $20.00 |
| 4 | Construction layout (Z0013798) | LS | 1 | $5,000.00 | $32,000 |
| 5 | Drain util STR adj (Z0017400) | EACH | 6 | $300.00 | $1,000.00 |
| 6 | SS 1 wat MN 12 (Z0056648) | LF | 18 | $129.35 | $289.20 |
| 7 | Tree remov 6-15 (20100110) | UNIT | 315 | $22.00 | $19.00 |
| 8 | Tree remov over 15 (20100210) | UNIT | 17 | $28.00 | $27.00 |
| 9 | Tree trunk protection (20101100) | EACH | 53 | $100.00 | $150.00 |
| 10 | Tree root pruning (20101200) | EACH | 53 | $125.00 | $90.00 |
| 11 | Tree prun 1-10 (20101300) | EACH | 40 | $25.00 | $55.00 |
| 12 | Tree prun over 10 (20101350) | EACH | 13 | $75.00 | $163.00 |
| 13 | Earth excavation (20200100) | CY | 545 | $40.00 | $117.80 |
| 14 | Rem & disp uns matl (20201200) | CY | 412 | $40.00 | $117.80 |
| 15 | Furnished excavation (20400800) | CY | 64 | $1.00 | $128.65 |
| 16 | Trench backfill (20800150) | CY | 107 | $100.00 | $106.15 |
| 17 | Topsoil exc & plac (21101505) | CY | 375 | $50.00 | $152.95 |
| 18 | Grading & shap ditch (21400100) | LF | 1,327 | $30.00 | $41.30 |
| 19 | Seeding CL 5 (25000320) | ACRE | 1 | $4,500.00 | $4,500.00 |
| 20 | Nitrogen fert nutr (25000400) | LB | 77 | $2.00 | $2.00 |
| 21 | Phosphorus fert nutr (25000500) | LB | 77 | $2.00 | $2.00 |
| 22 | Potassium fert nutr (25000600) | LB | 77 | $2.00 | $2.00 |
| 23 | Erosion contr blanket (25100630) | SY | 3,369 | $1.25 | $1.25 |
| 24 | Temp eros contr seed (28000250) | LB | 85 | $7.00 | $7.00 |
| 25 | Temp ditch checks (28000305) | LF | 195 | $15.00 | $15.00 |
| 26 | Perimeter eros bar (28000400) | LF | 2,082 | $2.75 | $2.75 |
| 27 | Inlet filters (28000510) | EACH | 5 | $190.00 | $190.00 |
| 28 | Agg subgrade improve (30300001) | CY | 109 | $65.00 | $112.10 |
| 29 | Agg base cse B 4 (35101600) | SY | 64 | $20.00 | $42.00 |
| 30 | Agg base cse B 6 (35101800) | SY | 1,687 | $30.00 | $24.00 |
| 31 | Bit matls PR CT (40600275) | LB | 3,797 | $0.01 | $0.01 |
| 32 | HMA SC IL-9.5 D N50 (40604060) | TON | 190 | $185.00 | $185.00 |
| 33 | Incidental HMA surf (40800050) | TON | 4 | $185.00 | $185.00 |
| 34 | PC conc sidewalk 5 (42400200) | SF | 565 | $25.00 | $18.00 |
| 35 | Sidewalk rem (44000600) | SF | 210 | $5.00 | $4.50 |
| 36 | Aggregate SHLDS B 6 (48101500) | SY | 510 | $30.00 | $43.50 |
| 37 | PRC flar end sec 12 (54213657) | EACH | 5 | $2,000.00 | $2,445.00 |
| 38 | Storm sew CL A 1 12 (550A0050) | LF | 485 | $110.35 | $83.10 |
| 39 | Fire hydnts to BE MVD (56400100) | EACH | 2 | $13,250 | $12,411 |
| 40 | CB TA 4 dia T8G (60200805) | EACH | 1 | $11,280 | $5,463.00 |
| 41 | CB TC T8G (60207605) | EACH | 3 | $10,367 | $3,158.00 |
| 42 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $11,150 | $5,200.00 |
| 43 | Man reconst (60257900) | EACH | 1 | $7,750.00 | $5,800.00 |
| 44 | VV reconst (60266100) | EACH | 1 | $7,750.00 | $5,800.00 |
| 45 | Non SPL waste disposl (66900200) | CY | 20 | $50.55 | $94.85 |
| 46 | Soil disposal analy (66900530) | EACH | 1 | $1,400.00 | $1,800.00 |
| 47 | Reg sub P-const plan (66901001) | LS | 1 | $4,200.00 | $3,400.00 |
| 48 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 |
| 49 | Reg sub mon (66901006) | CAL DAY | 10 | $725.00 | $700.00 |
| 50 | Mobilization (67100100) | LS | 1 | $30,938 | $57,000 |
| 51 | Traf cont-prot 701201 (70100450) | LS | 1 | $5,300.00 | $10,781 |
| 52 | TR cont & prot 701801 (70102640) | LS | 1 | $100.00 | $100.00 |
| 53 | Sign panel T1 (72000100) | SF | 53 | $30.00 | $30.00 |
| 54 | Remov sin pan assy TA (72400100) | EACH | 8 | $90.00 | $90.00 |
| 55 | Reloc sin pan assy TA (72400500) | EACH | 1 | $400.00 | $400.00 |
| 56 | Teles STL sin support (72800100) | LF | 60 | $17.00 | $17.00 |
| 57 | THPL PVT MK line 6 (78000400) | LF | 140 | $9.00 | $8.20 |
| 58 | THPL PVT MK line 12 (78000600) | LF | 316 | $10.00 | $16.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.