IDOT contract 61M49 bid tabulation
Maywood, section 23-00142-00-LT. Let by Illinois DOT on June 12, 2026, Cook, District 01. 4 bids received; low bid $1,709,017 by Sjostrom & Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 12 JUN 2026
- Pay items
- 66
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sjostrom & Sons, Inc. | $1,709,017 | Low |
| 2 | R. W. Dunteman Company | $1,776,250 | +4.0% |
| 3 | Utility Dynamics Corporation | $1,813,844 | +6.0% |
| 4 | Alliance Contractors, Inc. | $1,927,315 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sjostrom & Sons, Inc. | 2. R. W. Dunteman Company | 3. Utility Dynamics Corporation | 4. Alliance Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | T-gled tri 2.5 (A2004622) | EACH | 11 | $851.47 | $810.00 | $750.00 | $665.00 |
| 2 | T-tilia cord GS 2-1/2 (A2008120) | EACH | 8 | $861.98 | $820.00 | $750.00 | $650.00 |
| 3 | T-acer frem cel 2-1/2 (B2000130) | EACH | 10 | $998.64 | $950.00 | $750.00 | $635.00 |
| 4 | T-malus CRLB TF 2 (B2003116) | EACH | 9 | $814.68 | $775.00 | $700.00 | $595.00 |
| 5 | T-syrg RT IS TF 2-1/2 (B2006320) | EACH | 8 | $861.98 | $820.00 | $750.00 | $650.00 |
| 6 | E-thuja occid 6' (D2003772) | EACH | 10 | $788.40 | $750.00 | $700.00 | $595.00 |
| 7 | Test hole (XX003338) | EACH | 25 | $281.08 | $495.12 | $800.00 | $200.00 |
| 8 | Conc truck washout (XX006821) | LS | 1 | $1,311.66 | $3,000.00 | $4,000.00 | $750.00 |
| 9 | Bicycl repair station (XX009334) | EACH | 1 | $4,120.83 | $5,651.64 | $5,150.00 | $10,000 |
| 10 | Decorative LT P TY A (XX009377) | EACH | 66 | $4,437.67 | $3,730.00 | $3,800.00 | $4,221.55 |
| 11 | Rem & rein bric paver (X0327611) | SF | 300 | $39.94 | $38.00 | $80.00 | $40.00 |
| 12 | Luminaire LED special (X1400238) | EACH | 66 | $3,065.92 | $3,540.00 | $2,850.00 | $2,916.60 |
| 13 | R R FL beacon A comp (X1400326) | EACH | 8 | $16,823 | $13,200 | $14,800 | $16,004 |
| 14 | Stump removal (X2010404) | EACH | 5 | $5.25 | $150.00 | $400.00 | $225.00 |
| 15 | Clearing & grubbing (X2010512) | SY | 4,000 | $10.51 | $11.50 | $5.00 | $3.90 |
| 16 | Temp info signing (X7200061) | SF | 54 | $50.00 | $25.00 | $35.00 | $25.00 |
| 17 | Reloc EX LT unit SPL (X8440116) | EACH | 1 | $3,488.59 | $5,060.00 | $2,400.00 | $3,318.69 |
| 18 | Benches (Z0003850) | EACH | 14 | $3,228.74 | $5,111.79 | $2,500.00 | $4,000.00 |
| 19 | Bicycle racks (Z0003855) | EACH | 4 | $1,948.26 | $4,126.07 | $2,500.00 | $1,500.00 |
| 20 | Tree remov 6-15 (20100110) | UNIT | 150 | $63.08 | $60.00 | $36.00 | $33.00 |
| 21 | Tree remov over 15 (20100210) | UNIT | 320 | $94.61 | $90.00 | $50.00 | $44.00 |
| 22 | Tree prun 1-10 (20101300) | EACH | 5 | $157.68 | $150.00 | $180.00 | $160.00 |
| 23 | Tree prun over 10 (20101350) | EACH | 4 | $315.35 | $300.00 | $270.00 | $240.00 |
| 24 | Earth excavation (20200100) | CY | 90 | $152.06 | $182.39 | $260.00 | $50.00 |
| 25 | Topsoil F & P 4 (21101615) | SY | 4,600 | $8.57 | $8.15 | $10.00 | $9.00 |
| 26 | Nitrogen fert nutr (25000400) | LB | 57 | $3.68 | $3.50 | $4.00 | $3.00 |
| 27 | Phosphorus fert nutr (25000500) | LB | 57 | $3.83 | $3.50 | $4.00 | $3.00 |
| 28 | Potassium fert nutr (25000600) | LB | 57 | $3.83 | $3.50 | $4.00 | $3.00 |
| 29 | Interseed CL 1A (25003110) | ACRE | 0.83 | $3,941.98 | $3,750.00 | $4,500.00 | $4,100.00 |
| 30 | Sodding (25200100) | SY | 4,600 | $11.30 | $10.75 | $20.00 | $17.20 |
| 31 | Supple watering (25200200) | UNIT | 252 | $42.05 | $40.00 | $50.00 | $40.00 |
| 32 | Temp eros contr seed (28000250) | LB | 95 | $10.51 | $10.00 | $10.00 | $8.00 |
| 33 | Perimeter eros bar (28000400) | LF | 3,000 | $4.00 | $3.80 | $4.00 | $3.80 |
| 34 | Inlet filters (28000510) | EACH | 40 | $218.61 | $290.00 | $300.00 | $25.00 |
| 35 | Temp eros contr blank (28001100) | SY | 4,600 | $1.05 | $1.00 | $4.00 | $1.75 |
| 36 | Sub gran mat B 6 (31101400) | SY | 80 | $19.19 | $78.48 | $55.00 | $12.00 |
| 37 | Bit matls tack CT (40800029) | LB | 135 | $10.00 | $0.01 | $5.00 | $0.01 |
| 38 | Incidental HMA surf (40800050) | TON | 50 | $478.46 | $359.14 | $500.00 | $150.00 |
| 39 | Protective coat (42001300) | SY | 550 | $6.15 | $1.00 | $4.00 | $1.00 |
| 40 | PC conc sidewalk 5 (42400200) | SF | 4,800 | $15.64 | $12.22 | $29.00 | $14.00 |
| 41 | Detectable warnings (42400800) | SF | 400 | $24.05 | $36.89 | $40.00 | $40.00 |
| 42 | Pavement rem (44000100) | SY | 250 | $33.59 | $47.96 | $75.00 | $25.00 |
| 43 | Comb curb gutter rem (44000500) | LF | 200 | $28.83 | $29.35 | $60.00 | $25.00 |
| 44 | Sidewalk rem (44000600) | SF | 4,800 | $3.17 | $3.58 | $5.00 | $5.00 |
| 45 | Comb CC&G TB6.12 mod (60604100) | LF | 200 | $58.96 | $84.97 | $110.00 | $200.00 |
| 46 | Non SPL waste disposl (66900200) | CY | 5 | $526.22 | $292.84 | $250.00 | $500.00 |
| 47 | Soil disposal analy (66900530) | EACH | 1 | $1,377.07 | $1,310.00 | $1,200.00 | $900.00 |
| 48 | Reg sub P-const plan (66901001) | LS | 1 | $3,731.74 | $3,550.00 | $5,500.00 | $4,200.00 |
| 49 | Reg sub F con report (66901003) | LS | 1 | $525.59 | $500.00 | $2,500.00 | $500.00 |
| 50 | Reg sub mon (66901006) | CAL DAY | 5 | $788.40 | $750.00 | $1,100.00 | $750.00 |
| 51 | Mobilization (67100100) | LS | 1 | $103,217 | $106,494 | $118,000 | $431,600 |
| 52 | TR cont & prot 701501 (70102620) | LS | 1 | $25,000 | $227,400 | $20,000 | $6,000.00 |
| 53 | TR cont & prot 701801 (70102640) | LS | 1 | $13,000 | $6,000.00 | $25,000 | $6,000.00 |
| 54 | Sign panel T1 (72000100) | SF | 750 | $30.00 | $23.50 | $35.00 | $23.50 |
| 55 | Metal post TY A (72900100) | LF | 1,300 | $20.00 | $17.00 | $30.00 | $17.00 |
| 56 | Metal post TY B (72900200) | LF | 500 | $20.00 | $20.00 | $35.00 | $20.00 |
| 57 | THPL PVT MK line 12 (78000600) | LF | 1,600 | $7.00 | $4.30 | $7.00 | $4.30 |
| 58 | Mod ureth PM line 12 (78009012) | LF | 340 | $20.00 | $16.50 | $7.00 | $16.50 |
| 59 | Elect serv install (80400100) | EACH | 2 | $8,029.43 | $2,390.00 | $4,500.00 | $7,638.38 |
| 60 | Elect util serv conn (80400200) | LS | 1 | $10,000 | $10,000 | $10,000 | $10,000 |
| 61 | Undrgrd C galvs 2 1/2 (81028210) | LF | 120 | $73.93 | $68.75 | $50.00 | $70.33 |
| 62 | Undrgrd C galvs 3 (81028220) | LF | 380 | $72.79 | $101.00 | $60.00 | $69.25 |
| 63 | UD 4#6#6GXLPUSE 1 1/4 (81603100) | LF | 7,600 | $28.41 | $17.15 | $30.00 | $27.02 |
| 64 | EC C XLP use 1C 2 (81702150) | LF | 500 | $9.44 | $7.00 | $11.00 | $8.98 |
| 65 | LT cont basem 240V100 (82500350) | EACH | 2 | $22,413 | $13,700 | $12,400 | $21,321 |
| 66 | Rem elcbl FR con (89502300) | LF | 150 | $20.99 | $1.00 | $2.00 | $19.96 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.