IDOT contract 62P73 bid tabulation
Section 2024-1053-RS&N,SR,RS. Let by Illinois DOT on June 13, 2025, Lake, District 01. 2 bids received; low bid $16,944,587 by Curran Contracting Company.
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 98
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Curran Contracting Company | $16,944,587 | Low |
| 2 | Peter Baker & Son Company and Berger Excavating Contractors, Inc. JV | $22,569,122 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Curran Contracting Company | 2. Peter Baker & Son Company and Berger Excavating Contractors, Inc. JV |
|---|---|---|---|---|---|
| 1 | TV inspect of sewer (X0325207) | LF | 168 | $4.50 | $10.00 |
| 2 | Grading & shap SHLDRS (X2020110) | UNIT | 1,476 | $37.00 | $215.00 |
| 3 | CC&G RMVL repl < = 10 (X4400501) | LF | 50 | $250.00 | $150.00 |
| 4 | CC&G RMVL repl > 10FT (X4400503) | LF | 50 | $212.25 | $150.00 |
| 5 | SS cleaned 12 (X5537800) | LF | 885 | $3.40 | $3.00 |
| 6 | SS cleaned 30 (X5538400) | LF | 168 | $6.00 | $10.00 |
| 7 | Inlets reconst SPL (X6026800) | EACH | 1 | $20,000 | $6,000.00 |
| 8 | FR & lids adjust SPL (X6030310) | EACH | 1 | $3,500.00 | $3,000.00 |
| 9 | Centerln rum strip 16 (X6420114) | LF | 3,681 | $1.75 | $3.20 |
| 10 | Engr FLD off A SPL (X6700410) | CAL MO | 16 | $6,000.00 | $1,500.00 |
| 11 | TR cont surveill SPL (X7010240) | CAL DAY | 80 | $1,250.00 | $1,250.00 |
| 12 | Speed display trailer (X7010410) | CAL MO | 16 | $800.00 | $800.00 |
| 13 | Traf cont-prot TC8 (X7010808) | EACH | 6 | $1,200.00 | $1,200.00 |
| 14 | Temp info signing (X7200061) | SF | 243.10 | $25.00 | $25.00 |
| 15 | HS THPL PM LN 4 (X7800815) | LF | 7,363 | $0.85 | $0.85 |
| 16 | Det loop repl (X8860105) | LF | 1,917 | $19.43 | $28.10 |
| 17 | Construction layout (Z0013798) | LS | 1 | $115,000 | $6,000.00 |
| 18 | Drainage STR cleaned (Z0018500) | EACH | 59 | $330.00 | $330.00 |
| 19 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 20 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 21 | Earth excavation (20200100) | CY | 39,990 | $37.50 | $68.50 |
| 22 | Rem & disp uns matl (20201200) | CY | 6,490 | $35.00 | $68.50 |
| 23 | Geotech fab F/GR stab (21001000) | SY | 14,610 | $2.50 | $2.00 |
| 24 | Topsoil F & P 4 (21101615) | SY | 4,761 | $6.00 | $6.00 |
| 25 | Seeding CL 2A (25000210) | ACRE | 1 | $2,600.00 | $2,600.00 |
| 26 | Nitrogen fert nutr (25000400) | LB | 60 | $2.00 | $2.00 |
| 27 | Potassium fert nutr (25000600) | LB | 60 | $2.00 | $2.00 |
| 28 | Erosion contr blanket (25100630) | SY | 4,761 | $0.90 | $0.90 |
| 29 | Inlet & pipe protect (28000500) | EACH | 46 | $150.00 | $150.00 |
| 30 | Inlet filters (28000510) | EACH | 20 | $185.00 | $185.00 |
| 31 | Agg subgrade improve (30300001) | CY | 7,780 | $45.00 | $82.00 |
| 32 | Agg subgrade impr 12 (30300112) | SY | 63,248 | $24.00 | $41.00 |
| 33 | Sub gran mat C (31102000) | CY | 4,011 | $65.00 | $75.00 |
| 34 | HMA base cse 6 (35501308) | SY | 513 | $58.00 | $78.80 |
| 35 | HMA base cse 8 (35501316) | SY | 1,939 | $70.00 | $103.10 |
| 36 | HMA base cse 9 3/4 (35501323) | SY | 556 | $50.00 | $58.00 |
| 37 | HMA BC wid 6 1/4 (35600701) | SY | 50,344 | $29.00 | $34.40 |
| 38 | Bit matls PR CT (40600275) | LB | 114,524 | $0.01 | $1.00 |
| 39 | Bit matls tack CT (40600290) | LB | 68,271 | $1.00 | $1.50 |
| 40 | Long joint sealant (40600370) | LF | 96,405 | $2.65 | $3.80 |
| 41 | Mix CR JTS flangewys (40600400) | TON | 200 | $300.00 | $250.00 |
| 42 | HMA surf rem butt JT (40600982) | SY | 425 | $20.00 | $1.00 |
| 43 | HMA repl over patch (40601005) | TON | 2,520 | $100.00 | $66.00 |
| 44 | HMA SC IL-9.5 D N50 (40604060) | TON | 275 | $240.00 | $313.80 |
| 45 | HMA SC IL-9.5 D N70 (40604062) | TON | 235 | $100.00 | $115.00 |
| 46 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 24,426 | $112.50 | $125.40 |
| 47 | Pavement rem (44000100) | SY | 12,767 | $55.00 | $19.00 |
| 48 | HMA surf rem 1 3/4 (44000156) | SY | 200,507 | $2.65 | $4.25 |
| 49 | Drive pavement rem (44000200) | SY | 2,451 | $11.06 | $15.60 |
| 50 | HMA RM OV patch 3 (44002212) | SY | 15,000 | $15.00 | $5.00 |
| 51 | CL D patch T2 10 (44201765) | SY | 1,000 | $175.00 | $90.00 |
| 52 | CL D patch T3 10 (44201769) | SY | 2,000 | $115.00 | $90.00 |
| 53 | CL D patch T4 10 (44201771) | SY | 2,500 | $75.00 | $90.00 |
| 54 | Agg wedge SHLD type B (48102100) | TON | 10,199 | $37.00 | $64.50 |
| 55 | Conc HDWL for P drain (60100060) | EACH | 323 | $674.35 | $415.00 |
| 56 | Pipe underdrain 4 SP (60108100) | LF | 6,460 | $48.30 | $26.00 |
| 57 | Pipe underdr T 2 4 (60108204) | LF | 114,565 | $12.92 | $19.25 |
| 58 | SPBGR TY A 6FT posts (63000001) | LF | 325 | $37.56 | $37.56 |
| 59 | Traf bar term T2 (63100045) | EACH | 2 | $1,947.82 | $1,947.82 |
| 60 | TR bar TRM T1 SPL tan (63100167) | EACH | 2 | $3,862.28 | $3,862.28 |
| 61 | Shoulder rum strip 8 (64200108) | LF | 124,835 | $0.66 | $0.33 |
| 62 | Non SPL waste disposl (66900200) | CY | 10,800 | $70.00 | $70.00 |
| 63 | Soil disposal analy (66900530) | EACH | 8 | $1,650.00 | $1,270.00 |
| 64 | Reg sub P-const plan (66901001) | LS | 1 | $3,350.00 | $3,400.00 |
| 65 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $500.00 |
| 66 | Engineered barrier (66901005) | SY | 115 | $58.00 | $35.00 |
| 67 | Reg sub mon (66901006) | CAL DAY | 80 | $675.00 | $700.00 |
| 68 | Mobilization (67100100) | LS | 1 | $1,000,000 | $2,056,732 |
| 69 | Traf cont-prot 701421 (70100310) | LS | 1 | $175,000 | $605,000 |
| 70 | Traf cont-prot 701411 (70100420) | EACH | 6 | $500.00 | $500.00 |
| 71 | Traf cont-prot 701201 (70100450) | LS | 1 | $100.00 | $100.00 |
| 72 | Traf cont-prot 701306 (70100460) | LS | 1 | $100.00 | $100.00 |
| 73 | TR cont & prot 701501 (70102620) | LS | 1 | $25,000 | $100.00 |
| 74 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1.00 |
| 75 | Changeable message SN (70107025) | CAL DAY | 60 | $40.00 | $40.00 |
| 76 | Night work zone light (70200100) | LS | 1 | $16,000 | $1,000.00 |
| 77 | Short term pavt mking (70300100) | LF | 34,228 | $0.40 | $0.55 |
| 78 | SHRT TRM pavt MK rem (70300150) | SF | 5,705 | $2.50 | $3.00 |
| 79 | Temp PVT MK LTR & sym paint (70300211) | SF | 5,046 | $1.35 | $1.35 |
| 80 | Temp PVT MK line 4 - paint (70300221) | LF | 310,704 | $0.45 | $0.45 |
| 81 | Temp PVT MK line 6 - paint (70300241) | LF | 24,662 | $0.70 | $0.70 |
| 82 | Temp PVT MK line 8 - paint (70300251) | LF | 7,124 | $0.90 | $0.90 |
| 83 | Temp PVT MK line 12 - paint (70300261) | LF | 4,256 | $1.35 | $1.35 |
| 84 | Temp PVT MK line 24 - paint (70300281) | LF | 984 | $2.70 | $2.70 |
| 85 | Temp PVT MK L4 T4 tape (70307120) | LF | 18,467 | $1.25 | $1.25 |
| 86 | Terminal marker - DA (72501000) | EACH | 2 | $44.67 | $44.67 |
| 87 | THPL PVT MK LTR & sym (78000100) | SF | 2,371 | $5.75 | $5.75 |
| 88 | THPL PVT MK line 4 (78000200) | LF | 133,231 | $0.80 | $0.80 |
| 89 | THPL PVT MK line 6 (78000400) | LF | 10,977 | $0.95 | $0.95 |
| 90 | THPL PVT MK line 8 (78000500) | LF | 3,314 | $1.95 | $1.95 |
| 91 | THPL PVT MK line 12 (78000600) | LF | 1,757 | $3.32 | $3.32 |
| 92 | THPL PVT MK line 24 (78000650) | LF | 348 | $5.75 | $5.75 |
| 93 | Pref PL PM TD STD L4 (78004620) | LF | 16,806 | $7.25 | $7.25 |
| 94 | Mod ureth PM line 4 (78009004) | LF | 7,383 | $1.40 | $1.40 |
| 95 | GRV RCSD PVT MRKG 5 (78011025) | LF | 16,806 | $0.75 | $0.75 |
| 96 | Raised refl pavt MKR (78100100) | EACH | 4,023 | $36.00 | $36.00 |
| 97 | Grdrail ref type A (78200005) | EACH | 9 | $14.12 | $14.12 |
| 98 | Raised ref PVT MK rem (78300200) | EACH | 3,833 | $15.00 | $23.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.