IDOT contract 62R02 bid tabulation
Section 2021-181-SW. Let by Illinois DOT on April 25, 2025, Cook, District 01. 4 bids received; low bid $1,609,615 by Triggi Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 75
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Triggi Construction, Inc. | $1,609,615 | Low |
| 2 | Alliance Contractors, Inc. | $1,662,027 | +3.0% |
| 3 | M.Q. Sewer Water Contractors, Inc. d/b/a M. Q. Construction Company | $1,795,675 | +12% |
| 4 | MYS, Incorporated | $1,941,733 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Triggi Construction, Inc. | 2. Alliance Contractors, Inc. | 3. M.Q. Sewer Water Contractors, Inc. d/b/a M. Q. Construction Company | 4. MYS, Incorporated |
|---|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $50,000 | $24,900 | $1,000.00 | $27,247 |
| 2 | Rem & rein bric paver (X0327611) | SF | 12 | $25.00 | $25.00 | $50.00 | $95.59 |
| 3 | Ped signal post 10 FT (X1400367) | EACH | 2 | $2,000.00 | $1,601.10 | $1,601.10 | $2,100.97 |
| 4 | Ped signal post 5 FT (X1400378) | EACH | 26 | $1,850.00 | $1,370.85 | $1,370.85 | $1,919.33 |
| 5 | HMA driveway PVT rem (X4400082) | SY | 359.80 | $25.00 | $1.00 | $30.00 | $25.27 |
| 6 | CC&G RMVL repl < = 10 (X4400501) | LF | 48 | $80.00 | $126.65 | $150.00 | $163.46 |
| 7 | CC&G RMVL repl > 10FT (X4400503) | LF | 2,498 | $65.00 | $126.65 | $150.00 | $74.47 |
| 8 | SS cleaned 12 (X5537800) | LF | 800 | $7.00 | $1.00 | $12.00 | $1.09 |
| 9 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,000.00 | $500.00 | $3,500.00 | $2,236.84 |
| 10 | Accessible ped signal (X8760200) | EACH | 50 | $2,500.00 | $1,838.70 | $1,838.70 | $2,582.44 |
| 11 | Conc FDN TY A 12D (X8780012) | LF | 112 | $750.00 | $347.63 | $347.63 | $633.58 |
| 12 | Drainage STR cleaned (Z0018500) | EACH | 13 | $500.00 | $350.00 | $900.00 | $382.99 |
| 13 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 7 | $1,750.00 | $605.00 | $605.00 | $1,778.17 |
| 14 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 |
| 15 | Earth excavation (20200100) | CY | 220 | $100.00 | $20.00 | $200.00 | $126.80 |
| 16 | Topsoil F & P 4 (21101615) | SY | 1,175 | $2.50 | $6.00 | $12.00 | $15.69 |
| 17 | Nitrogen fert nutr (25000400) | LB | 23 | $1.00 | $4.00 | $10.00 | $30.33 |
| 18 | Potassium fert nutr (25000600) | LB | 23 | $1.00 | $4.00 | $10.00 | $30.33 |
| 19 | Sodding salt tolerant (25200110) | SY | 1,175 | $40.00 | $19.00 | $15.00 | $34.09 |
| 20 | Supple watering (25200200) | UNIT | 5 | $1.00 | $0.01 | $250.00 | $1.09 |
| 21 | Agg subgrade impr 12 (30300112) | SY | 141 | $1.00 | $18.80 | $25.00 | $39.68 |
| 22 | Bit matls tack CT (40600290) | LB | 635 | $1.00 | $0.01 | $3.00 | $0.11 |
| 23 | HMA BC IL-19.0 N50 (40603080) | TON | 12 | $500.00 | $960.00 | $1,500.00 | $382.99 |
| 24 | HMA SC IL-9.5 D N50 (40604060) | TON | 65 | $500.00 | $711.15 | $1,200.00 | $492.41 |
| 25 | Protective coat (42001300) | SY | 2,175 | $0.10 | $0.01 | $2.00 | $5.28 |
| 26 | PC conc sidewalk 5 (42400200) | SF | 14,468 | $15.00 | $18.10 | $16.00 | $25.15 |
| 27 | Detectable warnings (42400800) | SF | 1,593 | $35.00 | $40.00 | $50.00 | $48.06 |
| 28 | HMA surf rem 2 (44000157) | SY | 578 | $50.00 | $30.00 | $85.00 | $77.00 |
| 29 | Drive pavement rem (44000200) | SY | 22 | $25.00 | $20.00 | $50.00 | $31.52 |
| 30 | Sidewalk rem (44000600) | SF | 15,190 | $5.00 | $2.00 | $5.00 | $6.63 |
| 31 | Median removal (44003100) | SF | 56 | $10.00 | $15.00 | $75.00 | $9.35 |
| 32 | Agg wedge SHLD type B (48102100) | TON | 0.65 | $500.00 | $500.00 | $1,000.00 | $1,312.23 |
| 33 | HMA shoulders 10 (48203037) | SY | 117.50 | $100.00 | $246.80 | $260.00 | $164.14 |
| 34 | CB adjust (60250200) | EACH | 2 | $550.00 | $265.00 | $1,000.00 | $601.84 |
| 35 | CB reconst (60252800) | EACH | 1 | $1,650.00 | $5,335.00 | $2,500.00 | $1,805.53 |
| 36 | Man adjust (60255500) | EACH | 2 | $550.00 | $265.00 | $1,000.00 | $601.84 |
| 37 | Inlets adjust (60260100) | EACH | 2 | $550.00 | $265.00 | $1,000.00 | $601.84 |
| 38 | Inlets reconst (60262700) | EACH | 1 | $1,100.00 | $4,580.00 | $2,500.00 | $1,203.68 |
| 39 | Valve box adj (60266600) | EACH | 12 | $385.00 | $265.00 | $500.00 | $399.40 |
| 40 | FR & grates adjust (60300105) | EACH | 1 | $550.00 | $265.00 | $1,000.00 | $601.84 |
| 41 | FR & lids adjust (60300305) | EACH | 21 | $550.00 | $265.00 | $750.00 | $601.84 |
| 42 | FR & lids T1 OL (60406000) | EACH | 1 | $455.00 | $425.00 | $750.00 | $497.89 |
| 43 | FR & lids T1 CL (60406100) | EACH | 1 | $455.00 | $425.00 | $750.00 | $497.89 |
| 44 | Comb CC&G TB6.12 (60603800) | LF | 141 | $55.00 | $76.65 | $125.00 | $86.31 |
| 45 | Conc med TSB6.12 (60619600) | SF | 18 | $25.00 | $275.00 | $50.00 | $258.97 |
| 46 | Non SPL waste disposl (66900200) | CY | 220 | $100.00 | $60.00 | $60.00 | $198.24 |
| 47 | Soil disposal analy (66900530) | EACH | 10 | $1,250.00 | $1,250.00 | $1,680.00 | $1,597.61 |
| 48 | Reg sub P-const plan (66901001) | LS | 1 | $5,850.00 | $4,200.00 | $3,500.00 | $3,282.77 |
| 49 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 | $3,500.00 | $3,173.34 |
| 50 | Reg sub mon (66901006) | CAL DAY | 8 | $850.00 | $1,500.00 | $1,200.00 | $1,094.26 |
| 51 | Mobilization (67100100) | LS | 1 | $60,000 | $286,604 | $100,000 | $159,583 |
| 52 | TR cont & prot 701501 (70102620) | LS | 1 | $1.00 | $1.00 | $2.00 | $5,471.28 |
| 53 | TR cont & prot 701606 (70102625) | LS | 1 | $65,000 | $9,000.00 | $35,000 | $27,356 |
| 54 | TR cont & prot 701601 (70102630) | LS | 1 | $1.00 | $1.00 | $1.00 | $5,471.28 |
| 55 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1.00 | $1.00 | $5,471.28 |
| 56 | TR cont & prot 701801 (70102640) | LS | 1 | $10,000 | $1.00 | $1.00 | $27,356 |
| 57 | Rem & rel sign panel T1 (72400735) | SF | 8 | $25.00 | $30.00 | $50.00 | $82.07 |
| 58 | THPL PVT MK line 6 (78000400) | LF | 7,046 | $5.00 | $0.65 | $3.00 | $2.19 |
| 59 | THPL PVT MK line 12 (78000600) | LF | 216 | $10.00 | $7.00 | $6.00 | $4.38 |
| 60 | THPL PVT MK line 24 (78000650) | LF | 1,592 | $20.00 | $13.00 | $10.00 | $8.75 |
| 61 | PVT MKG rem WTR blast (78300202) | SF | 893 | $5.00 | $4.00 | $10.50 | $13.13 |
| 62 | Undrgrd C galvs 2 (81028200) | LF | 470 | $75.00 | $64.86 | $64.86 | $73.21 |
| 63 | Main EX TR sig instal (85000200) | EACH | 7 | $7,500.00 | $11,184 | $11,184 | $7,440.95 |
| 64 | Elcbl C signal 12 3C (87301125) | LF | 850 | $4.75 | $2.67 | $2.67 | $4.92 |
| 65 | Elcbl C signal 14 2C (87301215) | LF | 3,230 | $4.50 | $2.83 | $2.83 | $4.81 |
| 66 | Elcbl C egrdc 6 1C (87301900) | LF | 731 | $5.25 | $6.58 | $6.58 | $5.58 |
| 67 | Conc FDN TY A (87800100) | LF | 4 | $500.00 | $371.63 | $371.63 | $479.06 |
| 68 | Drill EX handhole (87900200) | EACH | 28 | $1,050.00 | $801.75 | $801.75 | $1,134.74 |
| 69 | Ped SH LED 1F BM CDT (88102717) | EACH | 6 | $1,000.00 | $1,197.60 | $1,197.60 | $1,043.92 |
| 70 | Det loop T1 (88600100) | LF | 700 | $50.00 | $28.05 | $28.05 | $41.36 |
| 71 | Reloc EX TS post (89501150) | EACH | 1 | $1,050.00 | $1,473.00 | $1,473.00 | $1,134.74 |
| 72 | Mod EX contr cab (89502210) | EACH | 7 | $3,500.00 | $550.00 | $550.00 | $3,605.58 |
| 73 | Rem & RE elcbl FR con (89502350) | LF | 430 | $2.50 | $6.62 | $6.62 | $2.19 |
| 74 | Remov EX TS equip (89502375) | EACH | 7 | $2,750.00 | $992.25 | $992.25 | $2,976.38 |
| 75 | Rebuild EX handhole (89502376) | EACH | 9 | $4,000.00 | $2,925.00 | $2,925.00 | $4,108.94 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.