IDOT contract 62V37 bid tabulation
Section FAP. Let by Illinois DOT on April 25, 2025, Kane, District 01. 3 bids received; low bid $3,811,382 by Plote Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 127
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Plote Construction, Inc. | $3,811,382 | Low |
| 2 | R. W. Dunteman Company | $4,049,483 | +6.0% |
| 3 | Builders Paving, LLC | $4,322,834 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Plote Construction, Inc. | 2. R. W. Dunteman Company | 3. Builders Paving, LLC |
|---|---|---|---|---|---|---|
| 1 | Tree care (K0026700) | EACH | 19 | $140.00 | $140.00 | $300.00 |
| 2 | Constructn layout SPL (X0320050) | LS | 1 | $20,000 | $15,900 | $25,000 |
| 3 | EM veh P S LSC 20 3C (X0324085) | LF | 718 | $2.00 | $1.83 | $1.85 |
| 4 | Outdr RTD NTWRK cable (X1400102) | LF | 1,032 | $2.00 | $1.84 | $1.85 |
| 5 | Ped signal post 10 FT (X1400367) | EACH | 10 | $2,100.00 | $2,087.10 | $2,100.00 |
| 6 | Ped signal post 5 FT (X1400378) | EACH | 14 | $1,750.00 | $1,741.85 | $1,750.00 |
| 7 | CC&G RMVL repl < = 10 (X4400501) | LF | 13 | $75.00 | $169.48 | $102.00 |
| 8 | CC&G RMVL repl > 10FT (X4400503) | LF | 1,387 | $80.00 | $72.76 | $77.00 |
| 9 | Pro man/CB con OV SS (X6025604) | EACH | 1 | $7,000.00 | $6,985.00 | $7,000.00 |
| 10 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,750.00 | $2,500.00 | $3,500.00 |
| 11 | Temp info signing (X7200061) | SF | 100 | $20.00 | $20.00 | $16.00 |
| 12 | Intercept EX conduit (X8100863) | EACH | 3 | $850.00 | $850.00 | $850.00 |
| 13 | Exp & rel EX unit DCT (X8161000) | LF | 80 | $37.25 | $37.25 | $37.25 |
| 14 | Accessible ped signal (X8760200) | EACH | 44 | $2,100.00 | $2,056.76 | $2,055.00 |
| 15 | Conc FDN TY A 12D (X8780012) | LF | 96 | $450.00 | $444.38 | $445.00 |
| 16 | Det loop repl (X8860105) | LF | 5,443 | $37.00 | $36.75 | $36.75 |
| 17 | Vid veh det sys SN AP (X8891009) | EACH | 5 | $11,000 | $10,455 | $10,500 |
| 18 | Rem & rein FO CBL con (X8950512) | LF | 390 | $5.00 | $4.71 | $4.70 |
| 19 | Drainage STR cleaned (Z0018500) | EACH | 19 | $350.00 | $450.00 | $450.00 |
| 20 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 6 | $580.00 | $577.50 | $575.00 |
| 21 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 |
| 22 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 23 | Earth excavation (20200100) | CY | 85 | $50.00 | $79.44 | $50.00 |
| 24 | Trench backfill (20800150) | CY | 2 | $23.00 | $23.00 | $23.00 |
| 25 | Topsoil F & P 4 (21101615) | SY | 553 | $9.00 | $9.00 | $10.00 |
| 26 | Seeding CL 2A (25000210) | ACRE | 0.25 | $5,000.00 | $5,000.00 | $7,500.00 |
| 27 | Nitrogen fert nutr (25000400) | LB | 10 | $3.00 | $3.00 | $5.00 |
| 28 | Potassium fert nutr (25000600) | LB | 10 | $3.00 | $3.00 | $5.00 |
| 29 | Sodding salt tolerant (25200110) | SY | 118 | $29.50 | $29.50 | $65.00 |
| 30 | Supple watering (25200200) | UNIT | 8 | $25.00 | $25.00 | $1.00 |
| 31 | Inlet filters (28000510) | EACH | 24 | $200.00 | $260.00 | $200.00 |
| 32 | Agg subgrade impr 12 (30300112) | SY | 121 | $45.00 | $28.03 | $45.00 |
| 33 | Sub gran mat B 4 (31101200) | SY | 2,065 | $7.00 | $14.97 | $7.00 |
| 34 | Sub gran mat B 8 (31101600) | SY | 649 | $15.00 | $17.75 | $15.00 |
| 35 | HMA base cse 12 1/4 (35501333) | SY | 27 | $160.00 | $175.45 | $225.00 |
| 36 | HMA BC wid 12 1/4 (35600725) | SY | 42 | $160.00 | $232.86 | $225.00 |
| 37 | Bit matls tack CT (40600290) | LB | 44,776 | $0.01 | $0.74 | $0.01 |
| 38 | Long joint sealant (40600370) | LF | 54,830 | $2.40 | $2.48 | $3.00 |
| 39 | Mix CR JTS flangewys (40600400) | TON | 90 | $150.00 | $354.66 | $250.00 |
| 40 | HMA surf rem butt JT (40600982) | SY | 550 | $25.00 | $21.75 | $25.00 |
| 41 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 9,750 | $120.00 | $122.76 | $115.00 |
| 42 | Protective coat (42001300) | SY | 2,650 | $0.10 | $0.74 | $0.10 |
| 43 | PC conc sidewalk 5 (42400200) | SF | 9,351 | $11.00 | $8.65 | $9.50 |
| 44 | PC conc sidewalk 8 (42400410) | SF | 50 | $12.00 | $24.82 | $11.00 |
| 45 | Detectable warnings (42400800) | SF | 871 | $45.00 | $34.24 | $40.00 |
| 46 | Pavement rem (44000100) | SY | 64 | $30.00 | $38.28 | $30.00 |
| 47 | HMA surf rem 1 3/4 (44000156) | SY | 98,847 | $4.10 | $3.62 | $3.00 |
| 48 | HMA surf rem 2 (44000157) | SY | 10 | $8.00 | $150.05 | $25.00 |
| 49 | Comb curb gutter rem (44000500) | LF | 3,980 | $11.00 | $12.80 | $10.00 |
| 50 | Sidewalk rem (44000600) | SF | 8,546 | $3.50 | $2.51 | $3.00 |
| 51 | Median removal (44003100) | SF | 5,977 | $4.00 | $2.25 | $3.50 |
| 52 | CL D patch T2 12 (44201789) | SY | 500 | $30.00 | $138.55 | $100.00 |
| 53 | CL D patch T3 12 (44201794) | SY | 500 | $30.00 | $120.57 | $100.00 |
| 54 | CL D patch T4 12 (44201796) | SY | 500 | $30.00 | $103.93 | $100.00 |
| 55 | CB TC T24F&G (60208240) | EACH | 1 | $6,300.00 | $6,285.00 | $6,285.00 |
| 56 | CB adjust (60250200) | EACH | 1 | $500.00 | $485.00 | $485.00 |
| 57 | Man adjust (60255500) | EACH | 1 | $650.00 | $650.00 | $650.00 |
| 58 | Inlets adjust (60260100) | EACH | 7 | $500.00 | $485.00 | $485.00 |
| 59 | Inlets adj new T1F CL (60260400) | EACH | 1 | $1,200.00 | $1,125.00 | $1,125.00 |
| 60 | Inlets adj new T11F&G (60261300) | EACH | 9 | $1,300.00 | $1,285.00 | $1,285.00 |
| 61 | Valve box adj (60266600) | EACH | 2 | $425.00 | $425.00 | $425.00 |
| 62 | Conc curb TB (60600605) | LF | 13.50 | $70.00 | $113.44 | $72.00 |
| 63 | Comb CC&G TB6.12 (60603800) | LF | 2,113 | $36.00 | $37.44 | $37.00 |
| 64 | Comb CC&G TY B-6.24 (60605000) | LF | 1,885 | $56.00 | $42.37 | $57.00 |
| 65 | Comb CC&G TM6.06 (60608600) | LF | 29 | $60.00 | $78.93 | $62.00 |
| 66 | Comb CC&G TM6.12 (60609200) | LF | 27 | $60.00 | $87.69 | $62.00 |
| 67 | Comb CC&G TM6.24 (60610400) | LF | 32 | $65.00 | $93.85 | $67.00 |
| 68 | Conc median surf 4 (60618300) | SF | 4,933 | $10.00 | $7.00 | $8.00 |
| 69 | Conc median surf 6 (60618320) | SF | 34 | $20.00 | $33.32 | $15.00 |
| 70 | Corrugated med (60624600) | SF | 1,030 | $25.00 | $22.11 | $19.00 |
| 71 | Non SPL waste disposl (66900200) | CY | 125 | $100.00 | $88.32 | $100.00 |
| 72 | Soil disposal analy (66900530) | EACH | 5 | $980.00 | $980.00 | $980.00 |
| 73 | Reg sub P-const plan (66901001) | LS | 1 | $5,300.00 | $5,300.00 | $5,300.00 |
| 74 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 | $500.00 |
| 75 | Reg sub mon (66901006) | CAL DAY | 30 | $700.00 | $700.00 | $700.00 |
| 76 | Mobilization (67100100) | LS | 1 | $210,000 | $238,300 | $533,300 |
| 77 | Traf cont-prot 701421 (70100310) | LS | 1 | $2,000.00 | $1.00 | $1.00 |
| 78 | TR cont & prot 701606 (70102625) | LS | 1 | $75,000 | $6,600.00 | $1.00 |
| 79 | TR cont & prot 701601 (70102630) | LS | 1 | $1.00 | $38,000 | $115,300 |
| 80 | TR cont & prot 701602 (70102632) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 81 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $11,000 | $1.00 |
| 82 | TR cont & prot 701801 (70102640) | LS | 1 | $1,500.00 | $51,405 | $1.00 |
| 83 | Short term pavt mking (70300100) | LF | 37,740 | $0.01 | $0.01 | $2.00 |
| 84 | SHRT TRM pavt MK rem (70300150) | SF | 12,580 | $0.01 | $0.01 | $0.01 |
| 85 | Temp PVT MK LTR & sym paint (70300211) | SF | 8,721 | $0.01 | $1.50 | $1.25 |
| 86 | Temp PVT MK line 4 - paint (70300221) | LF | 77,091 | $0.01 | $0.24 | $0.30 |
| 87 | Temp PVT MK line 6 - paint (70300241) | LF | 35,043 | $0.01 | $0.36 | $0.45 |
| 88 | Temp PVT MK line 8 - paint (70300251) | LF | 6,144 | $0.01 | $0.50 | $0.65 |
| 89 | Temp PVT MK line 12 - paint (70300261) | LF | 18,657 | $0.01 | $0.75 | $0.95 |
| 90 | Temp PVT MK line 24 - paint (70300281) | LF | 3,918 | $0.01 | $1.50 | $1.60 |
| 91 | Reloc sin pan assy TA (72400500) | EACH | 1 | $1,250.00 | $100.00 | $400.00 |
| 92 | Reloc sign panel T1 (72400710) | SF | 50 | $50.00 | $35.00 | $20.00 |
| 93 | Teles STL sin support (72800100) | LF | 65 | $20.00 | $20.00 | $15.00 |
| 94 | THPL PVT MK LTR & sym (78000100) | SF | 2,907 | $4.15 | $4.15 | $5.50 |
| 95 | THPL PVT MK line 4 (78000200) | LF | 25,697 | $0.68 | $0.68 | $0.78 |
| 96 | THPL PVT MK line 6 (78000400) | LF | 11,681 | $1.00 | $1.00 | $0.95 |
| 97 | THPL PVT MK line 8 (78000500) | LF | 2,048 | $1.35 | $1.35 | $1.25 |
| 98 | THPL PVT MK line 12 (78000600) | LF | 6,219 | $2.10 | $2.10 | $2.50 |
| 99 | THPL PVT MK line 24 (78000650) | LF | 1,306 | $4.15 | $4.15 | $5.50 |
| 100 | Raised refl pavt MKR (78100100) | EACH | 1,138 | $39.00 | $39.00 | $33.00 |
| 101 | Raised ref PVT MK rem (78300200) | EACH | 1,138 | $10.00 | $13.85 | $16.00 |
| 102 | PVT MKG rem WTR blast (78300202) | SF | 27,510 | $0.01 | $1.25 | $1.40 |
| 103 | Undrgrd C galvs 2 (81028200) | LF | 577 | $35.00 | $34.92 | $35.00 |
| 104 | Undrgrd C galvs 3 (81028220) | LF | 130 | $55.00 | $54.56 | $54.50 |
| 105 | Undrgrd C galvs 4 (81028240) | LF | 487 | $63.00 | $62.43 | $62.50 |
| 106 | Handhole (81400100) | EACH | 2 | $4,775.00 | $4,771.62 | $4,800.00 |
| 107 | DBL handhole (81400300) | EACH | 1 | $15,000 | $14,279 | $14,500 |
| 108 | UD 3#4#6GXLPUSE 1 1/4 (81603090) | LF | 78 | $57.00 | $56.14 | $56.00 |
| 109 | LP F M 15BC 8 5/8X6 (83600356) | EACH | 2 | $1,500.00 | $1,424.20 | $1,425.00 |
| 110 | Bkwy dev TR B 15BC (83800205) | EACH | 2 | $1,210.00 | $1,205.55 | $1,200.00 |
| 111 | Rem pole FDN (84200804) | EACH | 2 | $710.00 | $706.25 | $705.00 |
| 112 | Reloc EX LT unit (84400105) | EACH | 2 | $1,900.00 | $1,832.50 | $1,850.00 |
| 113 | Main EX TR sig instal (85000200) | EACH | 6 | $1,100.00 | $1,086.67 | $1,100.00 |
| 114 | Elcbl C signal 14 2C (87301215) | LF | 7,989 | $1.10 | $1.06 | $1.05 |
| 115 | Elcbl C signal 14 3C (87301225) | LF | 5,360 | $1.25 | $1.21 | $1.20 |
| 116 | Elcbl C signal 14 5C (87301245) | LF | 1,749 | $1.55 | $1.55 | $1.55 |
| 117 | Elcbl C signal 14 7C (87301255) | LF | 1,322 | $1.90 | $1.88 | $1.90 |
| 118 | Elcbl C lead 14 1PR (87301305) | LF | 1,132 | $1.20 | $1.19 | $1.20 |
| 119 | Elcbl C egrdc 6 1C (87301900) | LF | 265 | $1.60 | $1.60 | $1.60 |
| 120 | Drill EX handhole (87900200) | EACH | 24 | $850.00 | $850.00 | $850.00 |
| 121 | Ped SH LED 1F BM CDT (88102717) | EACH | 16 | $675.00 | $665.53 | $665.00 |
| 122 | Temp TR sig install (89000100) | EACH | 1 | $147,000 | $146,438 | $150,000 |
| 123 | Rem elcbl FR con (89502300) | LF | 15,559 | $0.65 | $0.63 | $0.65 |
| 124 | Remov EX TS equip (89502375) | EACH | 6 | $1,030.00 | $1,027.50 | $1,050.00 |
| 125 | Rebuild EX handhole (89502376) | EACH | 1 | $1,450.00 | $1,437.50 | $1,500.00 |
| 126 | Remov EX handhole (89502380) | EACH | 6 | $630.00 | $622.50 | $625.00 |
| 127 | Remov EX conc FDN (89502385) | EACH | 2 | $630.00 | $622.50 | $625.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.