IDOT contract 62V73 bid tabulation
Section FAP. Let by Illinois DOT on April 25, 2025, Cook, District 01. 3 bids received; low bid $991,171 by Plote Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 54
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Plote Construction, Inc. | $991,171 | Low |
| 2 | Builders Paving, LLC | $1,035,999 | +5.0% |
| 3 | Peter Baker & Son Co. | $1,189,358 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Plote Construction, Inc. | 2. Builders Paving, LLC | 3. Peter Baker & Son Co. |
|---|---|---|---|---|---|---|
| 1 | Tree limb rem 4-10 (X2010100) | EACH | 7 | $175.00 | $175.00 | $175.00 |
| 2 | Tree rem<6 unit flush (X2010108) | UNIT | 43.10 | $24.00 | $24.00 | $24.00 |
| 3 | Tree limb rem over 10 (X2010200) | EACH | 11 | $250.00 | $250.00 | $250.00 |
| 4 | Selective clearing (X2010516) | UNIT | 63.98 | $355.00 | $355.00 | $355.00 |
| 5 | Grading & shap SHLDRS (X2020110) | UNIT | 272 | $40.00 | $22.00 | $60.00 |
| 6 | Prun safety/equip CLR (X2100002) | UNIT | 69.37 | $260.00 | $360.00 | $260.00 |
| 7 | CC&G RMVL repl < = 10 (X4400501) | LF | 30 | $150.00 | $150.00 | $390.95 |
| 8 | SS cleaned 12 (X5537800) | LF | 180 | $2.50 | $2.50 | $2.50 |
| 9 | Centerln rum strip 16 (X6420114) | LF | 14,010 | $0.30 | $0.35 | $0.90 |
| 10 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,200.00 | $3,000.00 | $1,000.00 |
| 11 | Temp info signing (X7200061) | SF | 51.40 | $18.00 | $18.00 | $25.00 |
| 12 | HS THPL PM LN 4 (X7800815) | LF | 22,766 | $0.50 | $0.55 | $0.55 |
| 13 | Drainage STR cleaned (Z0018500) | EACH | 6 | $500.00 | $500.00 | $500.00 |
| 14 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 |
| 15 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 16 | Tree remov 6-15 (20100110) | UNIT | 240.40 | $27.00 | $27.00 | $27.00 |
| 17 | Tree remov over 15 (20100210) | UNIT | 15.20 | $36.00 | $36.00 | $36.00 |
| 18 | Seeding CL 3 (25000300) | ACRE | 1.47 | $3,900.00 | $3,880.00 | $3,880.00 |
| 19 | Erosion contr blanket (25100630) | SY | 7,109 | $1.00 | $1.00 | $0.99 |
| 20 | Stone riprap CL A3 (28100105) | SY | 5 | $500.00 | $500.00 | $120.00 |
| 21 | Bit matls tack CT (40600290) | LB | 25,618 | $0.01 | $0.01 | $0.01 |
| 22 | Long joint sealant (40600370) | LF | 17,639 | $2.60 | $3.00 | $3.70 |
| 23 | Mix CR JTS flangewys (40600400) | TON | 86 | $100.00 | $350.00 | $75.00 |
| 24 | HMA surf rem butt JT (40600982) | SY | 148 | $25.00 | $15.00 | $1.00 |
| 25 | HMA SC IL-9.5 D N70 (40604062) | TON | 4,782 | $80.00 | $66.00 | $85.00 |
| 26 | Protective coat (42001300) | SY | 36.67 | $5.00 | $8.00 | $0.01 |
| 27 | HMA surf rem 1 1/2 (44000155) | SY | 56,928 | $3.00 | $2.75 | $2.47 |
| 28 | CL D patch T2 15 (44201827) | SY | 300 | $40.00 | $170.00 | $250.00 |
| 29 | CL D patch T3 15 (44201831) | SY | 200 | $40.00 | $155.00 | $230.00 |
| 30 | CL D patch T4 15 (44201833) | SY | 300 | $40.00 | $145.00 | $195.00 |
| 31 | Agg wedge SHLD type B (48102100) | TON | 369 | $45.00 | $45.00 | $68.00 |
| 32 | Pipe culv cleaned 15 (60920015) | LF | 30 | $10.00 | $10.00 | $10.00 |
| 33 | Shoulder rum strip 8 (64200108) | LF | 28,111 | $0.50 | $0.25 | $0.45 |
| 34 | Mobilization (67100100) | LS | 1 | $50,000 | $40,000 | $63,796 |
| 35 | Traf cont-prot 701201 (70100450) | LS | 1 | $1.00 | $1.00 | $100.00 |
| 36 | Traf cont-prot 701306 (70100460) | LS | 1 | $1.00 | $40,000 | $100.00 |
| 37 | TR cont & prot 701501 (70102620) | LS | 1 | $44,200 | $1.00 | $77,145 |
| 38 | TR cont & prot 701502 (70102622) | LS | 1 | $1.00 | $1.00 | $100.00 |
| 39 | TR cont & prot 701602 (70102632) | LS | 1 | $3,000.00 | $1.00 | $100.00 |
| 40 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1.00 | $100.00 |
| 41 | Short term pavt mking (70300100) | LF | 12,401 | $0.01 | $0.01 | $0.01 |
| 42 | SHRT TRM pavt MK rem (70300150) | SF | 6,200 | $0.01 | $0.01 | $0.01 |
| 43 | Temp PVT MK LTR & sym paint (70300211) | SF | 540 | $0.01 | $0.01 | $0.01 |
| 44 | Temp PVT MK line 4 - paint (70300221) | LF | 184,863 | $0.01 | $0.01 | $0.01 |
| 45 | Temp PVT MK line 12 - paint (70300261) | LF | 1,206 | $0.01 | $0.01 | $0.01 |
| 46 | Temp PVT MK line 24 - paint (70300281) | LF | 224.40 | $0.01 | $0.01 | $0.01 |
| 47 | Temp PVT MK L4 T4 tape (70307120) | LF | 6,201 | $0.01 | $0.01 | $0.01 |
| 48 | THPL PVT MK LTR & sym (78000100) | SF | 180 | $6.00 | $5.75 | $5.75 |
| 49 | THPL PVT MK line 4 (78000200) | LF | 38,855 | $0.90 | $0.85 | $0.85 |
| 50 | THPL PVT MK line 12 (78000600) | LF | 402 | $3.50 | $3.35 | $3.32 |
| 51 | THPL PVT MK line 24 (78000650) | LF | 75 | $5.75 | $5.75 | $5.75 |
| 52 | Raised refl pavt MKR (78100100) | EACH | 646 | $35.00 | $35.00 | $35.00 |
| 53 | Raised ref PVT MK rem (78300200) | EACH | 646 | $10.00 | $12.00 | $10.00 |
| 54 | PVT MKG rem WTR blast (78300202) | SF | 20,759 | $0.01 | $1.40 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.